Project Camellia Data Center

project_profile

Project Camellia Data Center

Updated on Nov 27, 2026, 11:49 AM IST
Written by Siddhi Jain

 

Project at a Glance

Project Name

Project Camellia

Project Type

Hyperscale AI Data Center Campus

Project Status

Site Plan Approved

Project Location

Effingham County, Georgia

Developer

OpenAI

Buildings

Six data center buildings

Power Capacity

3.2 GW

Power Source

Georgia Power grid supply 

Timeline

Announced 22 July 2026; first power in 2028; phased delivery through 2032

 

Project Overview

OpenAI announced Project Camellia Data Center on 22 July 2026 and held a public open house on 23 July at the Effingham College and Career Academy. Its announcement says OpenAI is contracting with Georgia Power for 3.2 GW, delivered in phases between 2028 and 2032.

The facility will use a closed-loop cooling system, create thousands of construction and on-site jobs, provide USD 80 million in community benefits, and up to USD 71 million in Codex credits for Georgia students. It states that significant work remains on infrastructure, phasing, design, financing, and operating model.

The developer entity is Octans GA LLC. The Georgia Development of Regional Impact (DRI) review by the Coastal Regional Commission, reported on 16 September 2026, describes four buildings totaling 4.4 million sq ft with an estimated build-out value of USD 20 billion, and a peak load of 3,210 MW, the largest single electricity consumer in Georgia history. The site plan, approved on 17 November, includes six data center buildings.

Project Camellia Data Center Location

Project Camellia is located in Effingham County, Georgia, within the existing Savannah Gateway Industrial Hub (SGIH) near Rincon. It lies on Gateway Parkway in Rincon, Georgia, on Map 433, Parcel 1E, in the Second District.

 

Technical Specifications

Data Center Building

Six Buildings

Power Supply

3,200 MW at full build-out

Backup Power

Four diesel generators per building for life safety systems only 

Cooling & Water

Uses a closed-loop cooling system

Buffer & Noise

300-foot vegetated buffer next to residential 

 

Project Background

The site sits in the Savannah Gateway Industrial Hub, a previously zoned industrial and warehouse project, owned by the Effingham County IDA and about 12 miles from the Port of Savannah. County Commission Chairman Damon Rahn said the IDA approached the county without naming the project.  

Georgia Power submitted a 100-page contract to the PSC on 15 July 2026. The project was announced on 22 July. The DRI review became public on 16 September, the Corps permit application was filed on 5 October, and the county approved the site plan on 17 November. The Georgia PSC held its first administrative meeting outside Atlanta in nearly 20 years in Savannah on 15 September, where commissioners and staff described added protections against cost shifts to other customers. 

 

Trusted by Leading Manufacturers & EPCs

Find The Latest Data Center Projects In The United States

Gain exclusive access to our industry-leading database of Data Center Project opportunities with detailed project timelines & stakeholder information

Request Free Trial Learn More

No credit card Up-to-date coverage

 

Project Camellia Data Center Current Status

As of November 2026, Project Camellia is a proposed data center campus whose site plan has been approved, but it still needs permits. It is not yet an operating facility. 

The site plan was approved in November 2026, with development planned in phases beginning in 2028 and remaining subject to further permits, inspections, and approvals before construction and operation. 

 

Stakeholder Details

Stakeholder

Role

OpenAI / Octans GA LLC

Developer & operator

Effingham County Industrial Development Authority

Landowner & incentive grantor

Effingham County Board of Commissioners

Zoning and site plan approver

Georgia Power / Southern Company

Power Supplier

 

Project Camellia Data Center Cost Details

  • Project cost: USD 20 billion estimated build-out value (DRI and county). OpenAI states the project would be entirely privately funded and gives no total. 

  • Utility costs: OpenAI would pay the full cost of infrastructure and electric service. Under the PSC's large-load framework, the contract carries minimum bills and financial assurances.

  • Community Benefits: USD 80 million in community benefits and up to USD 71 million in Codex credits are separate from taxes

 

Project Scope

The following is the project scope of the Project Camellia Data Center:

  • Demand-response capability: The data center is designed to reduce its own electricity use during periods of high grid stress. This is intended to support electric-system reliability and reduce potential impacts on other Georgia Power customers. 

  • Closed-loop water cooling: The campus will use a closed-loop cooling system that is filled once and continuously recirculates water, rather than relying on evaporative cooling that continually consumes new water.

  • Treated surface-water supply: The project will use treated surface water only, not groundwater or the Floridan aquifer. Water quantities, conditions, and protections for community needs are to be established through the county’s water and sewer agreement. 

  • Noise mitigation and monitoring: The plan includes a minimum 300-foot vegetative buffer along neighboring non-industrial properties, setbacks beyond minimum requirements where possible, and preservation of existing vegetation. 

 

Trusted by Leading Manufacturers & EPCs

Find The Latest Data Center Projects In The United States

Gain exclusive access to our industry-leading database of Data Center Project opportunities with detailed project timelines & stakeholder information

Request Free Trial Learn More

No credit card Up-to-date coverage

 

Project Timeline

Year

Event

2028-2032

Phased power delivery from Georgia Power 

January 2027

County to revisit moratorium and conditional use ordinance for data centers 

17 November 2026

Commissioners approve the site plan 

15 September 2026

Site plan vote postponed at developer's request 

22 July 2026

OpenAI announces Project Camellia; 23 July open house  

15 July 2026

Georgia Power files its 100-page supply contract with the PSC  

 

Benefits

The following are the benefits of the project: 

  • Support for electric-grid reliability: The data center is designed to proactively reduce its power consumption during periods of high demand, before residential customers are affected. OpenAI says this is intended to support the reliability of Georgia Power’s electric system and its neighbors. 

  • Community benefits: OpenAI has committed USD 80 million in community benefits over the life of the project. These funds are to be informed by the community and directed toward schools, public safety, health care, utilities, workforce training, housing, veterans’ services, and support for small businesses and working families. 

  • Up to USD 71 million in student AI credits: OpenAI will make up to USD 71 million in Codex credits available to eligible Georgia college, community-college, and technical-school students. Eligible students receive USD 100 in credits through their ChatGPT accounts to build technical projects and develop practical AI-related skills. 

  • Stronger long-term tax revenue: OpenAI says the project is expected to create stronger long-term tax revenue than a warehouse development on the same site. 

  • More durable on-site employment: OpenAI states that the data center is expected to support more durable on-site employment than a warehouse project on the same site. 

 

Conclusion

Project Camellia is a long-term, privately funded AI data-center project that OpenAI is designing and developing in Effingham County, Georgia. The project is intended to provide large-scale AI computing infrastructure while creating local economic opportunity, supporting schools and public services, and expanding AI-related skills and career pathways in Southeast Georgia. 

The project is planned to deliver substantial community benefits: OpenAI has committed USD 80 million in community benefits over the life of the project and up to USD 71 million in Codex credits for eligible Georgia students. 

Before construction and operation, it must complete county and state reviews, approvals, permits, and inspections covering water and sewer service, buffers, stormwater, wetlands, utilities, erosion control, building requirements, and fire safety. 

 

Track the Latest Data Center Projects In The United States

Subscribe to our upcoming and ongoing Data Center Projects in the United States with ease to access reliable, high-quality insights on forthcoming and completed Projects across the country.

Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.

Start a free demo to take your business to the next level.

Tags

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile