Project at a Glance | |
Project Name | Homer City Energy Campus |
Project Type | Natural gas combined-cycle power plant with a planned hyperscale data center campus |
Project Status | Under Construction |
Project Location | Former Homer City Generating Station in Homer City, Pennsylvania |
Developer | Homer City Redevelopment, LLC |
Generation Capacity | 4.4 GW |
Project Completion Date | First power Q2 2028 (Expected) |
Project Overview
The Homer City Energy Campus is a large-scale redevelopment of the former Homer City Generating Station, once Pennsylvania's largest coal-fired power plant, into a natural gas-powered energy and data center hub in Indiana County, Pennsylvania.
Homer City Redevelopment (HCR) is leading the project, which is designed to meet the growing power demands of artificial intelligence (AI) and high-performance computing (HPC). HCR reported 'first steel' on 1 April 2026, and the first two of seven GE Vernova turbines were delivered and set in late September 2026.
On 2 April 2025, HCR announced a plan for up to 4.4 GW, to serve multiple large AI and high-performance computing customers on a campus of more than 3,200 acres. (The initial generation capacity was 4.5 GW).
Project planners expect more than 10,000 direct on-site construction jobs and approximately 1,000 direct and indirect permanent positions in technology, operations, and energy infrastructure. The switch from coal to natural gas power plants is projected to cut CO2 emissions by 60–65% per megawatt-hour compared with the former coal plant.
The campus would be one of the largest gas-fired power plants in the United States and the largest of its kind in North America upon completion. The project carries an initial capital investment of about USD 10 billion for power infrastructure and site readiness, described as one of the largest such investments in Pennsylvania's history.
Amazon Data Services, Inc. (AWS) filed a preliminary master land development plan with Indiana County for data centers on the campus. The county Planning Commission tabled it on 9 September 2026 and accepted it for a 90-day review on 14 October 2026.
AWS says power would come from FirstEnergy, supported by the 4.4 GW gas plant built by HCR; non-contact cooling water would be returned to the Homer City station for reuse.
Also Read: Top 5 Upcoming Data Center Projects by AWS
Homer City Energy Campus Location
The Homer City Energy Campus is located in Indiana County, Pennsylvania, on the site of the former Homer City Generating Station, about 50 miles east of Pittsburgh.
Historically, the facility was Pennsylvania's largest coal-burning power plant and was directly connected to both the PJM Interconnection and New York Independent System Operator (NYISO) transmission systems.
After nearly 55 years of operation, the plant was permanently decommissioned on 1 July 2023 and is now being transformed into a more than 3,200-acre natural gas-powered energy and data center campus.
Project Background
The Homer City Generating Station opened in 1969, ran for nearly 55 years and was permanently decommissioned on 1 July 2023. EIA records a capacity of 1,888 MW for the retired plant (Energy News Beat citing EIA), while DOE and HCR describe it as a 2 GW plant. Knighthead Capital Management says it has held significant equity in the site for about eight years and leads financing.
HCR announced the redevelopment on 2 April 2025, followed on 15 July 2025 by an agreement in principle with EQT for up to 665,000 MMBtu per day of gas. DEP issued the air plan approval on 18 November 2025 and a Title V renewal on 26 February 2026. Development of the data center side moved to the county in August and September 2026 with AWS's application.
Homer City Energy Campus Current Status & Completion Date
As of November 2026, the Homer City Energy Campus is the largest natural gas-powered plant currently under construction in the United States. Construction is advancing rapidly. The first two of seven turbines were delivered and set in late September 2026.
The remaining five deliveries will continue in phases over the next year. In its latest official announcement on November 20, 2026, Homer City Redevelopment named Aquatech as the water technology partner for the project. The campus remains on track to deliver first power expected by early 2028.
Trusted by Leading Manufacturers & EPCs
Find The Latest Data Center Projects In The United States
Gain exclusive access to our industry-leading database of Data Center Project opportunities with detailed project timelines & stakeholder information
No credit card Up-to-date coverage
Stakeholder Details
Stakeholder | Role |
Homer City Redevelopment | Developer & permit holder |
Knighthead Capital Management | Sponsor & financing lead |
Amazon Data Services, Inc. (AWS) | Data Center Applicant |
Kiewit Power Constructors Co. | EPC Contractor |
GE Vernova | Turbine Supplier |
EQT Corporation | Gas Supplier |
Kyuden Energy Partners | Plant Operator |
Pennsylvania DEP & US DOE | Regulator & Prospective Lender |
Homer City Energy Campus Project Cost
The project's initial capital investment is projected to exceed USD 10 billion for power infrastructure and site readiness.
Project Scope
The following is the project scope of the Homer City Energy Campus:
Site transformation: Converting the decommissioned Homer City coal plant into a more than 3,200-acre energy and technology campus.
AI and hyperscale data centers: Developing natural gas-powered data centers designed to meet growing artificial intelligence and high-performance computing needs.
Grid supply: Serving multiple large data center customers while supplying power to thousands of homes on the local grid.
Transmission connectivity: Using existing infrastructure, including transmission lines connected to PJM Interconnection and NYISO, plus substations and water access.
Site readiness work: Demolition and reclamation of the former plant site to prepare it for construction and redevelopment.
Project Timeline
Year | Event |
Q2 2028 | First power targeted |
Late September 2026 | First two of seven GE Vernova turbines delivered and set |
1 April 2026 | More than 1,000 workers on site; 'first steel' for the switchgear building |
26 February 2026 | DEP issues Title V operating permit renewal 32-00055 |
18 November 2025 | DEP issues Air Quality Plan Approval 32-00457A |
2 April 2025 | HCR and Kiewit announce up to 4.5 GW campus on more than 3,200 acres |
Trusted by Leading Manufacturers & EPCs
Find The Latest Data Center Projects In The United States
Gain exclusive access to our industry-leading database of Data Center Project opportunities with detailed project timelines & stakeholder information
No credit card Up-to-date coverage
Benefits
The following are the benefits of the project
Lower emissions: Replacing coal with natural gas cuts CO2 emissions by 60–65% per megawatt-hour, supporting cleaner power generation.
Reliable power supply: The 4.4 GW gas plant provides dispatchable, around-the-clock electricity to data centers and the regional grid.
Grid support for homes: The project supplies power to thousands of homes on the local grid alongside serving large data center customers.
Employment Opportunities: More than 10,000 direct on-site construction jobs are expected over the build-out. About 1,000 direct and indirect permanent positions in technology, operations, and energy infrastructure.
Economic investment: An initial capital investment projected to exceed $10 billion, one of the largest in Pennsylvania's history.
Conclusion
The Homer City Energy Campus represents a once-in-a-generation transformation of Pennsylvania's largest former coal plant into a modern energy and technology hub. The more than 3,200-acre site will host a 4.4 GW natural gas plant powered by seven GE Vernova 7HA.02 turbines, delivering reliable electricity for AI data centers and the regional grid.
With construction advancing and first power targeted for early 2028, Homer City is positioned to become one of the nation’s premier digital infrastructure and energy campuses. The redevelopment honors the community’s proud industrial past while building a sustainable, technology-driven future for the region.
Track the Latest Data Center Projects In The United States
Subscribe to our upcoming and ongoing Data Center Projects in the United States with ease to access reliable, high-quality insights on forthcoming and completed Projects across the country.
Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.
Start a free demo to take your business to the next level.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.