Project at a Glance | |
Project Name | Google Lea County data center |
Project Type | Proposed hyperscale data center |
Project Status | Proposed |
Project Location | Western edge of Hobbs, New Mexico, in Lea County |
Developer/Operator | |
Facility Size | Two data center buildings of about 900,000 sq ft each |
Critical IT Capacity | Not disclosed |
Project Overview
On 14 September 2026, Google announced that it is exploring a data center in Lea County, New Mexico. Many details remain outstanding, and it commits to paying for 100% of the energy Google uses and the infrastructure it needs. Google also launched a project website, leacountydatacenter.com.
Details emerged afterwards from press reporting of Google town halls and county meetings. The reports say two 900,000 sq ft buildings on 1,890 acres on Hobbs' outskirts, built on county land under an option to purchase held by Excelsior Hobbs Power LLC, with Excelsior Energy Capital to build a 2 GW solar field about three miles away.
The project is expected to generate hundreds of long-term operational jobs and thousands of construction jobs, alongside potential investments in schools, hospitals, local infrastructure, affordable housing, and workforce training.
Google also says it will use low-noise equipment, sound walls, and building setbacks to meet or exceed local noise standards, while continuing to share project updates as planning progresses.
Lea County Data Center Location
The proposed Lea County Data Center would be located approximately five miles outside the western edge of Hobbs, New Mexico, in Lea County. Google states that this location was intentionally selected to help insulate nearby residents from potential noise impacts, including during construction, and that the project remains in the early stages of evaluation.
Technical Specifications
Buildings | Two buildings of about 900,000 sq ft each |
Site | 1,890 acres of county-owned land under an option to purchase held by Excelsior Hobbs Power LLC |
IT Capacity | Not disclosed |
Cooling | Closed-loop, air-cooled; evaporative cooling prohibited by county resolution |
Water | Construction: about 900,000 gallons per day |
Noise | Low-noise equipment and sound walls |
Project Background
Lea County, in the Permian Basin on the Texas border, has an established oil, gas, and nuclear fuel economy, and the county has been in talks with data center developers for about two years.
The commission adopted its data center resolution on 26 February 2026 before any Google announcement. Google then announced it was exploring the county on 14 September 2026.
Lea County Data Center Status
As of November 2026, the Lea County Data Center remains a proposed and early-stage project. Google says it is still reviewing the opportunity and evaluating whether Lea County is the right fit for a long-term partnership.
Trusted by Leading Manufacturers & EPCs
Find The Latest Data Center Projects In The United States
Gain exclusive access to our industry-leading database of Data Center Project opportunities with detailed project timelines & stakeholder information
No credit card Up-to-date coverage
Stakeholder Details
Stakeholder | Role |
Project Developer & Operator | |
Excelsior Hobbs Power LLC/Excelsior Energy Capital | Option holder on county land |
Lea County Board of County Commissioners | Landowner, bond issuer, and local regulator |
Lea County Data Center Cost Details
The total estimated cost for the Lea County Google Data Center is not yet disclosed officially.
Project Scope
The following is the Project Scope of the Lea County Data Center Project:
Closed-loop system commissioning: Google estimates that filling and initially flushing the closed-loop cooling system will require 9.5–9.7 million gallons of water. After commissioning, daily consumption is expected to be limited to domestic uses.
Construction water use: Construction is expected to be the highest-water-use phase, with an anticipated daily average of just over 900,000 gallons and a peak average of roughly 1 million gallons per day for about four months.
Energy supply and infrastructure: The energy plan is still being finalized, but Google expects a power mix that is mostly clean energy, supported by gas-powered resources for system balance.
Noise mitigation: The project would use low-noise equipment, sound walls, and building setbacks to meet or exceed local noise requirements. Google also says it will conduct an acoustical study to model and minimize noise impacts on surrounding areas.
Project Timeline
Year | Event |
Late 2029 to 2030 | Possible start of operations |
2027 | Expected groundwork on the data center project |
14 September 2026 | Google blog post announces it is exploring a Lea County data center |
Benefits
The following are the benefits of the project:
Long-term local jobs: Google expects the prospective data center to create hundreds of long-term operational jobs initially and thousands of jobs during construction. These roles would provide employment opportunities for residents in Lea County and the surrounding area.
Workforce development: Google plans to invest in skills-training programs so community members can build careers alongside the data center. This includes potential partnerships to expand skilled-trades training, technology education, and no-cost Google Career Certificate programs.
Support for local businesses: The project could create opportunities for local contractors, service providers, and suppliers during construction and ongoing operations. Google states that data centers can expand the local tax base and generate new economic activity.
Public revenue for community services: Google is discussing an economic-development arrangement that could provide millions of dollars for local schools, hospital facilities, local governments, and affordable housing. Under this arrangement, Google says its payments would exceed 100% of its real property taxes.
Lower water impact than evaporative cooling: The proposed facility would use a closed-loop, air-cooled system, avoiding evaporative cooling. After the initial commissioning, daily water use would be limited mainly to domestic purposes, such as bathrooms and kitchens.
Cleaner energy mix: Google expects the power mix to be primarily clean energy, supported by gas-powered resources for system balance. The project would be designed with Southwest Public Service Company to meet New Mexico’s Energy Transition Act and Renewable Energy Act requirements.
Conclusion
The Lea County Google Data Center remains a prospective, early-stage project. Google is still evaluating whether Lea County is suitable for a long-term partnership and says it will share updates as its review progresses; many key details, including the site plan, building size, construction timeline, water source, and incentive agreements, have not yet been finalized.
If developed, the project is expected to create hundreds of long-term operational jobs initially and thousands of construction jobs. Google also plans to invest in workforce training, local infrastructure, schools, hospitals, and affordable housing, while discussing an economic-development arrangement under which its payments would exceed 100% of its real property taxes.
It also states that it will pay for 100% of the power it uses and the infrastructure directly driven by its growth, use noise-mitigation measures, and comply with applicable environmental and public-health requirements.
Track the Latest Data Center Projects In The United States
Subscribe to our upcoming and ongoing Data Center Projects in the United States with ease to access reliable, high-quality insights on forthcoming and completed Projects across the country.
Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.
Start a free demo to take your business to the next level.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.