Meta Kuna Data Center

project_profile

Meta Kuna Data Center

Updated on Nov 18, 2026, 07:04 PM IST
Written by Siddhi Jain

 

Project at a Glance

Project Name

Meta Kuna Data Center

Project Type

Hyperscale AI-optimized data center 

Project Status

Operational

Project Location

Kuna, Idaho, within Ada County

Owner & Operator

Meta

Capacity

Not disclosed officially

Power Supply

Matched with 100% clean and renewable energy by Meta 

Construction Start Date

September 2022

Construction Completion Date

3 September 2026

 

Project Overview

Meta's Kuna Data Center is one of its first facilities built on a new design to support AI systems. Meta announced the project through Idaho Commerce on 16 February 2022 with an initial USD 800 million investment. It paused the design for about eight months to make it more efficient, and says the campus now represents approximately USD 1.2 billion of capital investment. 

Meta says the main buildings use a closed-loop system with no evaporative water loss, with about 200,000 gallons circulating and replaced only every 7 to 10 years. Meta reports that the facility’s electricity use is matched with 100% clean and renewable energy, supported by renewable-energy projects adding 645 megawatts of capacity in Ada County.

The facility is designed to support the processing, storage, and transmission of data for its global platforms, including Facebook, Instagram, and WhatsApp. Construction supported approximately 1,600 skilled-trade workers, while the completed facility is expected to support around 100 full-time operational jobs. 

 

Kuna Data Center Location

The Meta Kuna Data Center is located in Kuna, Idaho, within Ada County and the Treasure Valley region near Boise. Meta chose the site for its access to infrastructure, renewable energy, an available workforce, and supportive community partners.

The campus is situated on the outskirts of Kuna in an open desert landscape and forms part of Meta’s global data-center infrastructure supporting its technologies and services. 

 

Technical Specifications

Floor Area

More than 750,000 sq ft 

Capacity

Not Officially Disclosed

Cooling

Closed-loop water through dry coolers, no evaporative loss; a smaller part of the campus uses evaporative cooling in rapid-deployment structures

Water Use

About 200,000 gallons in the sealed loop

Offsite Infrastructure

Meta-funded water and wastewater plant transferred to the City of Kuna with capacity for future growth 

 

Project Background

Idaho Commerce announced the project on 16 February 2022 as a USD 800 million, nearly 1 million sq ft server farm that would create 100 permanent jobs. Idaho Power and Meta announced a renewable energy tariff the same month, and the state's 2020 sales tax exemption for data centers investing at least USD 250 million applied. Meta committed to a water and sewer system for Kuna, and groundbreaking followed around September 2022. 

In 2023, the legislature passed House Bill 328, which barred data centers that use the sales tax exemption from being placed in an urban renewal district. Kuna had created an east urban renewal district to capture Meta's property tax and fund water and sewer links for an industrial park; Mayor Joe Stear testified that the bill would effectively end the district. 

Meta paused the design for about eight months to make the center more efficient. In November 2024, Idaho Power announced a power purchase agreement for Pleasant Valley Solar 2 supporting the data center. The campus was formally switched on at a ribbon-cutting on 3 September 2026, and Pleasant Valley Solar 2 reached commercial operation on 21 July 2026. 

 

Kuna Data Opening Date

Meta officially announced the operation of Kuna Data Center on 3 September 2026. It said that the project is fully operational and has begun serving traffic as part of Meta’s global infrastructure. 

The project broke ground in 2022 and took approximately four years to build, with Meta later describing the campus as an AI-optimized data center integrated into its global infrastructure. 

Trusted by Leading Manufacturers & EPCs

Find The Latest Data Center Projects In The United States

Gain exclusive access to our industry-leading database of Data Center Project opportunities with detailed project timelines & stakeholder information

Request Free Trial Learn More

No credit card Up-to-date coverage

 

Stakeholder Detail

Stakeholder 

Role

Meta

Owner & Operator

Idaho Power

Electric Utility

Idaho Public Utilities Commission

Regulator

Hensel Phelps

Contractor

Trout Unlimited

Water Restoration Partner

 

Kuna Data Center Cost

  • Investment: USD 1.2 billion in capital investment in Idaho.

  • Local commitments: USD 100 million or more for a water and wastewater system transferred to Kuna

Project Scope

The following is the project scope of the Kuna Data Center: 

  • Supports Meta Technologies: The Kuna Data Center is part of Meta’s global infrastructure that supports Meta technologies, applications, and programs, including data processing, storage, and transmission for users worldwide. 

  • Network connectivity: Fiber-optic cables connect servers across the campus and link the facility to external networks, enabling Meta’s data-center operations to serve global traffic. 

  • Cooling system: The project uses a closed-loop, liquid-cooled system that recirculates water through cooling coils and dry coolers, with no evaporative water loss and zero operational water use for most of the year. 

  • Water-restoration commitment: As part of Meta’s broader water-stewardship goals, the Kuna project is associated with the Alta Harris Creek Boise River Side Channel Project, intended to improve water quality, restore fish passage, and return approximately 149 million gallons of water annually to the local watershed. 

  • Sustainability scope: The project incorporates water-efficient cooling, renewable-energy matching, and Meta’s broader goal to be water positive by 2030, meaning the company aims to restore more water than it consumes globally where it has owned operations. 

 

Project Timeline

Year

Event

3 September 2026

Kuna Data Center Became Operational

2024

Design paused for about eight months for efficiency changes 

September 2022

Groundbreaking occurred on the Kuna Data Center Project

February 2022

Idaho Power and Meta announce a renewable energy tariff  

16 February 2022

Idaho Commerce announces Meta's USD 800 million Kuna data center; 100 jobs 

 

Benefits

The following are the benefits of the project: 

  • Major capital investment in Kuna: The project invests nearly USD 1.2 billion in the Kuna community, supporting local economic activity during construction and operation. 

  • Construction Jobs: The project supported 1,600 skilled-trade workers at peak construction, creating substantial temporary employment during the build phase. 

  • Permanent operational jobs: Once completed, the data center is expected to support approximately 100 operational jobs in Kuna, including roles in engineering, maintenance, security, and site operations.

  • Improved city water and wastewater infrastructure: Meta invested in a new water and wastewater system for the City of Kuna, which Meta built and then dedicated to the city to own and operate, strengthening local public infrastructure. 

  • New renewable-energy capacity: Meta-supported renewable projects are adding 645 megawatts of new renewable-energy capacity in Ada County, expanding clean-energy supply in the region. 

  • Community and education support: Meta has contributed USD 200,000 to Kuna schools, supporting local education and community initiatives alongside the data-center project. 

 

Conclusion

The Meta Kuna Data Center is both a major technology asset for Meta’s AI-driven services and a significant local infrastructure project for Kuna, combining hyperscale computing capacity with water-efficient design, renewable-energy procurement, and community investment. 

The facility supports the processing, storage, and transmission of data for Meta’s technologies and programs, with a design optimized for the company’s latest AI infrastructure. It represents an investment of USD 1.2 billion with 1,600 skilled-trade workers at peak construction. 

 

Track the Latest Data Center Projects In The United States

Subscribe to our upcoming and ongoing Data Center Projects in the United States with ease to access reliable, high-quality insights on forthcoming and completed Projects across the country.

Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.

Start a free demo to take your business to the next level.

Tags

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile