Ellendale Data Center: Applied Digital’s Polaris Forge 1 

project_profile

Ellendale Data Center: Applied Digital’s Polaris Forge 1 

Updated on Nov 12, 2026, 04:13 PM IST
Written by Siddhi Jain

 

Project at a Glance

Project Name

Polaris Forge 1 (PF1) AI Factory campus 

Project Type

AI / HPC data center campus 

Project Status

Operating, Phased Build-Out 

Project Location

Ellendale, Dickey County, North Dakota 

Developer & Operator

Applied Digital Corporation 

Critical IT Load

400 MW

Construction Start

September 2022 for the site as a crypto and HPC development; AI campus leases announced June 2025 

Completion Date

Expected by 2027

 

Project Overview

Ellendale Data Center, also known as Polaris Forge 1, is Applied Digital's first AI Data Center campus and the anchor of its North Dakota build-out. The campus is designed for 400 MW of critical IT load, all of which is leased to CoreWeave under three leases worth about USD 11 billion in contracted revenue over roughly 15-year terms. 

Capacity has been delivered in phases: the first 100 MW building began service in late October 2025, 75 MW of the second building was delivered on 30 June 2026, and Applied Digital reports 250 MW live as of 1 October 2026. The company also reports a 150 MW building (ELN-04) in development. 

The campus draws on North Dakota's cold climate and wind-rich grid. The site uses excess energy from the city's electric substation, which can hold up to 2 GW of wind power, and PF1 uses up to 400 MW of it. MDU has credited USD 38.4 million to North Dakota customers over three years based on its service to PF1.

 

Ellendale Data Center Location

Polaris Forge 1 is a large-scale AI and high-performance-computing data-center campus located in Ellendale, Dickey County, North Dakota, United States. The campus is generally identified as being northeast of Ellendale, with a listed site address of 9663 87th Ave SE, Ellendale, ND 58436. 

 

Technical Specification

Critical IT Load (Design & Leased)

400 MW: buildings of 100 MW, 150 MW, and 150 MW per the August 2025 lease schedule 

Live Capacity

250 MW as of 1 October 2026 across two buildings and ten data halls 

Building Schedule

Building 1: 100 MW, Q4 2025. Building 2: 150 MW, mid-2026. Building 3: 150 MW, 2027 

Cooling

Closed-loop, waterless, direct-to-chip; more than 220 days of free cooling per year; design PUE 1.18, WUE near zero.

 

Project Background

Applied Digital began building at Ellendale in September 2022 as a crypto and HPC development, and the 180 MW Ellendale hosting facility for cryptocurrency mining is a separate operating asset in the same town. The AI campus, then described as 280 MW of potential capacity, was re-planned as a 400 MW AI Factory for CoreWeave. 

On 2 June 2025, Applied Digital announced two leases of about 15 years with CoreWeave for 250 MW of critical IT load and about USD 7 billion of revenue, with a 150 MW option. On 29 August 2025, it finalised the third 150 MW lease, bringing the campus to 400 MW and about USD 11 billion. 

The first 100 MW building came into service in late October 2025. In August 2025, residents of Ellendale voiced concerns about land use and power demand. The campus was annexed into the city of Ellendale in 2025 so that property taxes go to the city. In 2026, Applied Digital funded ELN-04 with USD 1.59 billion of notes and delivered the first phase of Building 2 on 30 June. 

Trusted by Leading Manufacturers & EPCs

Find The Latest Data Center Projects In The United States

Gain exclusive access to our industry-leading database of Data Center Project opportunities with detailed project timelines & stakeholder information

Request Free Trial Learn More

No credit card Up-to-date coverage

 

Ellendale Data Center Current Status

Ellendale Data Center (Polaris Forge 1) is currently operating and expanding. Applied Digital reports 250 MW of CoreWeave capacity as of 1 October 2026 across two buildings and ten data halls, up from 100 MW in October 2025 and 175 MW as of 30 June 2026. 

A further 150 MW building (ELN-04) is under construction, funded by USD 1.59 billion of senior secured notes priced on 9 June 2026. The campus is designed for 400 MW of critical IT load and is expected to reach full capacity in 2027. 

 

Stakeholder Details

Stakeholder

Role

Applied Digital

Developer & Operator

CoreWeave

Tenant

Montana-Dakota Utilities

Electric Utility

Goldman Sachs Bank USA

Bridge Lender

APLD ComputeCo 3 LLC

Notes Issuer

 

Ellendale Data Center Project Cost

Category

Cost

ELN-04 Financing

USD 1.59 billion. A USD 300 million bridge facility funded for the building's start. 

Lease Revenue

About USD 7 billion for the first 250 MW and about USD 11billion for 400 MW, over roughly 15 years.

 

Project Scope

The following is the project scope of the Ellendale Data Center Project:

  • Provide long-term leased infrastructure. The leases have an approximately 15-year base term, with three five-year renewal options, and are expected to generate about USD 11 billion in aggregate lease revenue over the base term. 

  • Deliver capacity in phased stages. Building 1’s 100 MW phase reached Ready for Service in October 2025; Building 2 (150 MW) was delivered in two 75 MW phases, bringing live campus capacity to 250 MW after the second phase. 

  • Engineer the campus for high-density AI compute. Polaris Forge 1 uses Applied Digital’s proprietary design, including liquid cooling and power-distribution innovations, to support dense AI and HPC workloads. 

  • Prioritize energy efficiency and low water use. The project is designed to optimize energy performance and total cost of ownership, with near-zero water consumption. 

  • Use North Dakota’s climate and renewable-power opportunities. The campus design is intended to harness renewable power and leverage North Dakota’s cool climate to support sustainability and lower operating costs. 

 

Project Timeline

Year

Event

2027

The facility is expected to reach 400 MW full capacity

1 October 2026

250 MW live across two buildings and ten data halls 

July 2026

175 MW live and ELN-04 development  

30 June 2026

Building 2 phase one (75 MW) delivered; 175 MW live 

October 2025

First 100 MW building enters service (first 50 MW, then second 50 MW) 

29 August 2025

Third 150 MW lease finalised; campus 400 MW, about USD 11 billion  

2 June 2025

Two CoreWeave leases announced: 250 MW, about USD 7 billion, with a 150 MW option 

September 2022

Construction begins at Ellendale as a crypto and HPC development  

 

Trusted by Leading Manufacturers & EPCs

Find The Latest Data Center Projects In the United States (US)

Gain exclusive access to our industry-leading database of Data Center Project opportunities with detailed project timelines & stakeholder information

Request Free Trial Learn More

No credit card Up-to-date coverage

Benefits

The following are the benefits of the project:  

  • Community investment and partnerships. The project has been recognized for its community investment and partnerships, reflecting its role in strengthening local relationships and supporting the Ellendale area. 

  • Technological innovation. Polaris Forge 1 applies proprietary design and engineering innovations for high-density AI and high-performance computing (HPC) infrastructure. 

  • Lower electricity costs. By selecting a site with access to stranded or excess regional power, the campus can reduce annual electricity costs by an estimated USD 50 million to USD 60 million compared with other existing 100 MW data centers. 

  • Large long-term cost savings. Applied Digital estimates that the site-selection and cooling-design approach can generate up to USD 2.7 billion in savings over a 30-year lifespan. 

  • Free cooling advantage. North Dakota’s climate provides more than 220 days of free cooling annually, reducing cooling-related operating costs and improving sustainability.

  • Energy efficiency. The campus is designed to achieve a projected Power Usage Effectiveness (PUE) of 1.18, supporting lower energy consumption and operating costs. 

 

Conclusion

Polaris Forge 1 forms part of a fully contracted 400 MW deployment for CoreWeave under long-term lease agreements. The project is part of Applied Digital’s broader effort to convert access to power into operational AI capacity through a repeatable, scalable development model.

The project has demonstrated strong execution through the on-time delivery of Building 1 in October 2025, which reached its full 100 MW critical IT load after the completion of its second 50 MW phase. Applied Digital states that this progress reflects its focus on precision execution, speed-to-market, and purpose-built AI infrastructure delivery. 

As the campus advances toward its broader 400 MW deployment, Applied Digital remains focused on delivering production-scale AI infrastructure with the speed, precision, and sustainability required by modern AI compute. The project also demonstrates the company’s ability to turn power into operational capacity through its repeatable AI Factory model. 

 

Track the Latest Data Center Projects In The United States

Subscribe to our upcoming and ongoing Data Center Projects in the United States with ease to access reliable, high-quality insights on forthcoming and completed Projects across the country.

Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.

Start a free demo to take your business to the next level.

Tags

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile