Project at a Glance | |
FPSO Name | Errea Wittu |
Development Project | Uaru Development Project—the fifth project on the Stabroek Block, offshore Guyana |
Project Status | Errea Wittu has set sail to Guyana |
Field Location | Uaru oil field, Stabroek Block, approximately 200 km offshore Guyana |
Operator | ExxonMobil Guyana Limited |
Total Development Cost | USD 12.7 billion |
FPSO Builder | MODEC |
First Oil Target | Q4 2026 |
Oil Production Capacity | 250,000 barrels of oil per day (bopd) |
Gas Treatment Capacity | 540 million cubic feet per day (MMscfd) |
Crude Oil Storage | 2 million barrels |
Wells Programme | Up to 10 drill centers; 44 wells total: 21 production wells + 23 water and gas injection wells |
Project Overview
FPSO Errea Wittu, whose name means 'abundance,' is a 250,000-barrel-per-day FPSO (Floating Production, Storage & Offloading) vessel built by MODEC of Japan for ExxonMobil Guyana's Uaru Development Project. It is the fifth project on the prolific Stabroek Block. The vessel has set sail from Singapore to Guyana, with first production at the Uaru field targeted for Q4 2026.
The Errea Wittu will be the largest FPSO in the Stabroek fleet and, when it begins producing, will raise Guyana's installed offshore production capacity from approximately 915,000 barrels per day to approximately 1.2 million bpd. It is built on MODEC's M350 new-build hull design & construction model, which features the highest water injection and water capacity specifications in the Stabroek fleet.
The Uaru field, located offshore Guyana, is estimated to hold more than 800 million barrels of oil. The development plan encompasses up to 10 drill centres, 44 wells (21 producers and 23 injectors), 44 TechnipFMC Subsea 2.0® subsea trees, and 12 manifolds.
Uaru FPSO Location
The Uaru FPSO (Errea Wittu) is located in the ultra-deepwater of the Stabroek Block, approximately 200 km offshore Guyana in the Atlantic Ocean. Operating in water depths of roughly 1,690 m, the facility is positioned at about 16 km northeast of the Liza field and around 200 km from Georgetown.
Project Background
ExxonMobil first identified the Uaru accumulation during the systematic appraisal of the Stabroek Block that followed the transformational Liza discovery in 2015. Uaru was confirmed as a major accumulation with estimated resources exceeding 800 million barrels, making it one of the largest individual discoveries in the block.
The Final Investment Decision for Uaru was taken on April 27, 2023, with a total development investment of USD 12.7 billion. The co-venture structure mirrors that of all Stabroek Block developments: ExxonMobil Guyana (45% operated), with Hess Guyana (30%; now Chevron Guyana following Chevron's USD 53 billion acquisition of Hess in late 2024) and CNOOC Petroleum Guyana (25%). The April 2023 FID followed receipt of government and regulatory approvals from the Government of Guyana and its Petroleum Commission.
MODEC, one of the Top FPSO Companies in the World, was selected as the FPSO builder. It began construction in November 2023 with simultaneous first steel cutting ceremonies in Singapore (for topside modules) and China (for the hull). MODEC's hull was fabricated at COSCO's Chinese yard, with hull works including partial module lifting and integration completed before the China sailaway in late June 2025. The vessel arrived at Seatrium's Singapore yard on June 28, 2025, for full module integration and commissioning.
The Uaru field's subsea infrastructure was being prepared in parallel with the FPSO construction. Jumbo Offshore deployed its J-class heavy lift installation vessel Fairplayer to install the suction anchors and pre-lay the mooring lines for the Errea Wittu's spread mooring system.
Trusted by Leading Manufacturers & EPCs
Find The Latest FPSO Projects In Guyana
Gain exclusive access to our industry-leading database of FPSO Projects opportunities with detailed project timelines & stakeholder information
No credit card Up-to-date coverage
Uaru FPSO Current Status
The Uaru FPSO (Errea Wittu) is currently en route to Guyana and on track for first oil in the fourth quarter of 2026. It departed Singapore in June 2026. Pre‑installation activities at the field have been completed: mooring pre‑installation (including suction anchors and mooring lines) was finished in February 2026.
Stakeholder Details
Stakeholder Role | Individual/Organisation |
Operator | ExxonMobil Guyana Limited |
Co-Venturer (30%) | Chevron Guyana (formerly Hess Guyana Exploration Ltd.) |
Co-Venturer (25%) | CNOOC Petroleum Guyana Ltd. |
FPSO Builder/Operator | MODEC Inc. |
Hull Fabricator | COSCO Shipping (China) |
Integration Yard | Seatrium, Singapore |
Mooring Pre-Installer | Jumbo Offshore (Netherlands) |
Subsea Tree Supplier | TechnipFMC |
Subsea System Installer | Saipem |
Regulatory Authority | Guyana's Environmental Protection Agency (EPA) and Petroleum Commission of Guyana |
Uaru FPSO Project Cost
The total estimated cost for the Uaru FPSO Project is USD 12.7 billion. This figure covers the full field development scope, FPSO construction and integration, and subsea production systems.
Project Timeline
Year | Event |
Q4 2026 | First oil expected from the Uaru FPSO project |
June 2026 | FPSO Errea Wittu departed from Seatrium’s yard in Singapore. |
13 February 2026 | Jumbo Offshore completes mooring pre-installation for FPSO |
28 June 2025 | FPSO Errea Wittu arrives at Seatrium Singapore. |
November 2023 | First steel cutting ceremonies for the Errea Wittu FPSO |
27 April 2023 | ExxonMobil Guyana and co-venturers Hess Guyana (30%) and CNOOC Petroleum Guyana (25%) announce the final investment decision. |
Design & Engineering Details
FPSO Type | New build FPSO |
Oil Production Capacity | 250,000 barrels of oil per day (bopd) |
Gas Treatment Capacity | 540 million cubic feet per day (MMcfd) |
Water Injection Capacity | 350,000 barrels per day |
Produced Water Capacity | 300,000 barrels per day |
Crude Oil Storage | 2 million barrels |
Water Depth | 1,690m |
Mooring System | Spread mooring |
Hull Design | MODEC M350 |
Hull Fabrication | COSCO Shipping (China) |
Integration | Seatrium, Singapore |
Wells Programme | 10 drill centres; 44 wells—21 production wells + 23 water/gas injection wells |
Subsea Trees | 44 TechnipFMC Subsea 2.0® trees |
Commercial Model | MODEC lease-and-operate |
Conclusion
The Uaru development marks ExxonMobil’s fifth major offshore project on the Stabroek Block and is on track for first oil in Q4 2026, with the Errea Wittu FPSO now en route from Singapore to Guyana. Once operational, Uaru will add up to 250,000 bpd of gross oil production capacity.
The project’s integration of the Uaru, Mako, and Snoek accumulations under a single FPSO hub demonstrates the continued scale‑up and replication of the Stabroek development model, with Uaru serving as a key near‑term growth driver for ExxonMobil’s Guyana portfolio.
Also Read: FPSO Jaguar Whiptail: Latest Updates (2026)
Track the Latest & Upcoming FPSO Projects In Guyana
Subscribe to our upcoming and ongoing FPSO Projects in Guyana with ease to access reliable, high-quality insights on forthcoming and completed projects across the country.
Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.
Start a free demo to take your business to the next level.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.