Tuas Mega Port Singapore

project_profile

Tuas Mega Port Singapore

Updated on Sep 04, 2026, 01:31 PM IST
Written by Siddhi Jain

 

Project at a Glance

Project Name

Tuas Mega Port

Project Type

Fully Automated Container Terminal 

Project Status

Under phased construction & operation

Project Location

Tuas, western Singapore 

Developer

Maritime and Port Authority of Singapore (MPA) 

First Announced

2012

Total Land Area

Approximately 1,337 hectares 

Total Capacity

65 million TEU (twenty-foot equivalent units) annually 

Development Phases

4 phases total

Official Opening

1 September 2022

Current Operational Berths

14 berths

 

Project Overview

The Tuas Mega Port is Singapore's flagship maritime infrastructure project. It is a fully automated container terminal under construction in four phases in western Singapore that will become the world's single largest fully automated container port when complete in 2040. 

First announced in 2012, the port consolidates all of Singapore's fragmented container terminal operations, currently spread across Tanjong Pagar, Keppel, Brani, and Pasir Panjang, into a single, purpose-built facility. It comprises 66 berths spanning 26 km of deep-water quay, capable of handling 65 million TEU (twenty-foot equivalent units) annually at full capacity. 

The terminal's technology is central to its strategic purpose. Tuas Port deploys automated rail- mounted gantry cranes (aRMGs), with the 208th and final unit of Phase 1's six-year, 208-crane delivery programme completed via a final shipment of five ZPMC-supplied units alongside double-trolley quay cranes and automated guided vehicles (AGVs), all supported by a private 5G network.

PSA has stated Tuas Port will be the world's largest fully automated terminal with automated wharf and yard functions, targeting net-zero emissions by 2050 through electrified equipment (which reduces carbon emissions by approximately 50% versus diesel prime movers) and smart grid management. 

PSA Singapore and COSCO Shipping are also developing a joint logistics hub at Tuas Port. This ecosystem approach reflects Singapore's strategy of positioning Tuas not merely as a container terminal but as an integrated node connecting the port to the Jurong Lake District, Jurong Innovation District, and the wider Tuas Industrial District. 

 

Tuas Mega Port Location

Tuas Mega Port is located in the Tuas area on Singapore’s southwestern coast, along the Straits of Singapore. It is built on reclaimed land and an integrated offshore platform west of the existing Tuas shoreline. The site sits within Singapore’s western industrial belt near the Jurong and Tuas industrial zones, Jurong Innovation District, and Jurong Lake District. 

 

Tuas Mega Port Phases

Phase

Scope

Reclamation

Berth Opens

Status (2026)

Phase 1

20 million TEU capacity; core terminal infrastructure

Feb 2015 - Nov 2021

2021-2027

14 berths open (August 2026); expanding to 18 by 2027

Phase 2

Finger Three Construction

Complete (land transferred April 2026)

First Berth 2028

Land Transferred

Phase 3

Further finger pier expansion

To be determined

2030s (Expected)

Planned. Not yet under active construction

Phase 4

Final expansion to full 66-berth, 65M TEU capacity

To be determined

2040s (Expected)

Planned. Full completion target remains the 2040s

 

Trusted by Leading Manufacturers & EPCs

Find The Latest Energy Infrastructure Projects Around The World

Gain exclusive access to our industry-leading database of Energy Infrastructure Projects opportunities with detailed project timelines & stakeholder information

Request Free Trial Learn More

No credit card Up-to-date coverage


Technical Specifications

Total Capacity (At Completion)

65 million TEU annually 

Total Berths (At Completion)

66 Berths

Total Quay Length

26 km of deep-water berths

Total Land Area

1,337 hectares 

Terminal Layout

Four long 'fingers' with caisson quay walls; 115 hectares of terminal area; finger-pier layout designed for modular expansion

Berth Depth

Up to -23m Chart Datum (CD). Accommodates ultra-large container vessels over 450m in length

Vessel Capability

Designed to handle vessels over 400m long by the 2040s 

Sustainability Target

Net-zero emissions by 2050; electrified equipment reduces emissions ~50% vs diesel; green building construction 

 

Project Background

Singapore's port has been central to the city-state's economy for two centuries. By the early 2010s, the fragmentation of container operations across four separate terminal locations was becoming a structural constraint. 

Each terminal had different capabilities, and the dispersed footprint generated significant inter-terminal transport movements across Singapore's road network, adding cost and congestion.

In 2012, the Singapore Government announced a plan to consolidate all container operations at a single new mega-port in Tuas, at the western tip of the island. Phase 1 land reclamation began in February 2015 and was completed in November 2021.

The first two berths began operations in December 2021. The port was officially opened by the Singapore Government on 1 September, 2022, with three berths fully operational. Five more berths were added through 2022, and expansion continued steadily thereafter. 

By February 2025, Tuas Port had reached the milestone of handling 10 million containers since opening; eight more berths had commenced service by that point. Three additional berths were added by August 2026, bringing the operational total to 14. 

Phase 2 construction advanced decisively in April 2026 with the Maritime and Port Authority of Singapore's formal transfer of reclaimed land for Berths B7 and B8 to PSA Singapore, together with the Singapore Land Authority's land alienation approval. 

This transfer is the regulatory and administrative gateway that allows PSA to commence construction of its own infrastructure at these berths, with further berths in Phase 2 to follow progressively. Construction of Finger Three, one of the four planned quay fingers, has begun, with the first Phase 2 berth targeted for operational status in 2028.

 

Tuas Mega Port Status & Completion Date

Tuas Mega Port is already partially operational, with Phase 1 berths in service from 2021-2022. Full completion of this mega‑port is targeted for 2040, when it will consolidate all of Singapore’s container operations and reach its design capacity.

 

Stakeholder Details

Stakeholder Role

Individual/Organisation

Land Reclamation/Infrastructure Authority

Maritime and Port Authority of Singapore (MPA) 

Terminal Operator

PSA Singapore (PSA International) 

Land Administration

Singapore Land Authority (SLA) 

Crane  Supplier

ZPMC (Shanghai Zhenhua Heavy Industries Co.) 

Marine Construction Contractor

Boskalis  

Logistics Partner

COSCO Shipping 

 

Tuas Mega Port Project Cost

Cost/Financial Item

Details

Phase I Cost

Singapore Dollar 2.42 billion (USD 1.76 billion), for the initial 20 million TEU first phase, covering reclamation and core terminal infrastructure 

Total Estimated Cost

Over USD 20 billion 

PSA Supply Chain Hub @ Tuas

Singapore Dollar 647.5 million (USD 647.5 million) 

Revenue Model

PSA Singapore terminal handling fees and logistics service revenue

 

Project Scope

The following is the project scope of the Tuas Mega Port: 

  • Full Automation & Digital Port System: The port comprises fully automated yards, driverless AGVs, remotely operated ship‑to‑shore cranes and an integrated digital operating system (e.g. PortMentor, CITOS, digital twin) to manage vessel calls, container flows and equipment in real time.

  • Green Infrastructure: The project adds electric AGVs, energy‑efficient cranes, shore‑power berths and other measures to cut carbon emissions per container and reduce overall port‑related emissions and noise.

  • Integrated Logistics & Supply‑chain Hub: The project scope comprises adjacent warehousing, cold‑chain and dangerous‑goods facilities (e.g. PSA Supply Chain Hub @ Tuas) and connectivity to road and future rail links to support end‑to‑end logistics.

  • Safety & Operational Resilience: Automation reduces human exposure to heavy equipment and hazardous zones, while centralised control centres, predictive maintenance and digital twins improve safety, reliability and resilience against disruptions.

 

Trusted by Leading Manufacturers & EPCs

Find The Latest Energy Infrastructure Project Around The World

Gain exclusive access to our industry-leading database of Energy Infrastructure Projects opportunities with detailed project timelines & stakeholder information

Request Free Trial Learn More

No credit card Up-to-date coverage

 

Project Timeline

Year

Event

2040 (Target)

Full completion of the project (Expected)

2028 (Target)

First Phase 2 berth (Finger Three) expected to become operational.  

2027 (Target)

  • 18 berths operational at Tuas Port

  • Phase 1 fully complete with up to 20 million TEU annual capacity

6 August 2026

PSA Singapore announced that the terminal has handled 25 million TEUs

April 2026

MPA formally transfers reclaimed land for Phase 2 Berths B7 and B8 to PSA Singapore

24 February 2025

Tuas Mega Port hits milestone of handling 10 million containers since opening

October 2024

PSA breaks ground on the PSA Supply Chain Hub @ Tuas 

1 September 2022

Tuas Port officially opens, with three berths fully operational. 

December 2021

First two berths at Tuas Port Phase 1 begin operations 

November 2021

Phase 1 land reclamation completed 

February 2015

MPA commences land reclamation works for Tuas Port Phase 1.  

 

Tuas Mega Port Latest News

Below is the latest news of 2026 on the Tuas Mega Port Project:

 

August 2026

Tuas Mega Port achieved a major milestone at an operational level. In August 2026, PSA Singapore announced that the terminal has handled 25 million TEUs since operations commenced in September 2022. At the time of the announcement, the port was operating 14 berths and remained on schedule to expand to 18 berths by 2027 as part of the phased build‑out toward its ultimate 65 million‑TEU capacity in the 2040s. 

 

April 2026

Tuas Mega Port achieved two linked milestones in April 2026:

  • PSA Singapore announced the completion of Phase 1 of its AI‑driven terminal automation at Tuas. It integrates machine‑learning optimisation for automated guided vehicles and quay cranes to improve vessel turnaround times and yard utilisation across the initial operational berths. 

  • Around the same period, the Maritime and Port Authority of Singapore (MPA) handed over the first reclaimed land parcels for Phase 2 (Berths B7 and B8) to PSA in March–April 2026, enabling the operator to begin terminal infrastructure works on the first Phase 2 plots and marking the start of physical construction for the next expansion tranche of the mega‑port. 

 

Benefits

The following are the benefits of the project: 

  • Faster Cargo Volume Ramp-up: The August 2026 milestone of 25 million TEU handled was reached just 18 months after the 10 million TEU milestone in February 2025. It demonstrates an accelerating ramp-up curve as more berths come online and cargo increasingly shifts from the older city terminals. 

  • Eliminate Inter-terminal Transport Inefficiency: The consolidation of Singapore's four fragmented container terminals (Tanjong Pagar, Keppel, Brani, Pasir Panjang) into the single Tuas facility by the 2040s will eliminate substantial inter-terminal transport inefficiency. 

  • Redevelopment Opportunity: The consolidation of ports will free up prime waterfront land at the vacated city terminals for redevelopment into offices and residential use under Singapore's Greater Southern Waterfront masterplan. It creates a multi-billion-dollar urban redevelopment opportunity as a direct consequence of the port.

  • Reduce Logistics Costs: Centralisation cuts inter‑terminal truck movements, saving time and operating costs for shipping lines and cargo owners while streamlining cargo handling.

  • World-class Automation: Fully automated yard cranes, driverless AGVs and remotely operated ship‑to‑shore cranes boost manpower productivity, efficiency and safety.

 

Conclusion

Tuas Mega Port is Singapore’s flagship maritime infrastructure programme, designed to consolidate all major container operations into a single, fully automated terminal on the island’s western coast. 

Upon full completion, Tuas will replace Tanjong Pagar, Keppel, Brani and Pasir Panjang terminals, freeing up prime southern waterfront land for urban redevelopment and concentrating port activity in a modern, future‑ready facility. 

The mega‑port thus serves as both a long‑term engine for Singapore’s maritime economy and a model for next‑generation, sustainable, automated port development. 

Track the Latest Energy Infrastructure Projects Around The World

Subscribe to our upcoming and ongoing Energy Infrastructure Projects Around The World with ease to access reliable, high-quality insights on forthcoming and completed projects across the country

Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.

Start a free demo to take your business to the next level.

Tags