Project at a Glance | |
Project Name | Shinan Ui Offshore Wind Farm |
Project Type | Fixed-Bottom Offshore Wind Farm |
Project Status | Under Construction |
Project Location | Approximately 4 km south-east of Ui Island in Shinan County |
Total Capacity | 390 MW |
Turbines | 26 × Vestas V236-15.0 MW |
Lead Developer/EPC | Hanwha Ocean Co |
Consortium Members | Hanwha Ocean (lead developer + EPC), Korea Midland Power (KOMIPO), SK Eternix, Hyundai Engineering & Construction, Future Energy Fund |
Total Project Cost | KRW 3.4 trillion |
Groundbreaking | 16 July 2026 |
Operation Target | Expected by 2029 |
Project Overview
The Shinan Ui Offshore Wind Farm is one of the largest upcoming wind farm projects in Korea. It is located approximately 4 km south-east of Ui Island in Shinan County, having a total generation capacity of 390 MW.
Comprising 26 Vestas V236-15.0 MW turbines, the project broke ground on July 16, 2026, with commercial operation targeted for 2029. With a total project investment of KRW 3.4 trillion (approximately USD 2.5 billion), it is the first large-scale Korean offshore wind development to be financed entirely with domestic capital.
The project's ownership consortium is led by Hanwha Ocean, which serves simultaneously as lead developer and turnkey EPC (Engineering, Procurement, and Construction) contractor. Consortium partners include Korea Midland Power (KOMIPO, a subsidiary of KEPCO), SK Eternix (SK Group's renewable energy arm), Hyundai Engineering & Construction, and the Future Energy Fund.
Except for the Vestas wind turbines, most key components like substructures, subsea cables, offshore substations, and installation vessels will be sourced from Korean suppliers. When commissioned, Shinan Ui will more than double South Korea's operational offshore wind capacity, from approximately 350 MW today to approximately 740 MW. It represents a decisive step toward the government's target of 10.5 GW of offshore wind by 2030.
Shinan Ui Offshore Wind Farm Location
The Shinan Ui Offshore Wind Farm is located in the waters southeast of Ui Island, in Shinan County, South Jeolla Province (Jeollanam-do), South Korea. It is approximately 4 km southeast of Ui Island, in the Yellow Sea off Korea’s southwest coast.
Technical Specifications
Total Capacity | 390 MW |
Number of Turbines | 26 units |
Turbine Model | Vestas V236-15.0 MW |
Foundation Type | Fixed-bottom foundations |
Annual Output | Sufficient to power approximately 300,000 South Korean households annually |
Subsea Cables | LS Cable & System |
Project Background
South Korea's offshore wind sector has developed far more slowly than those of neighbouring China and Taiwan despite comparable maritime geography and stronger domestic industrial capabilities. As of 2026, Korea has only approximately 350 MW of operational offshore wind capacity, a fraction of Taiwan's fleet and a rounding error against China's capacity of over 42 GW.
Shinan County has emerged as Korea's most significant offshore wind development zone. Shinan is the location of Korea's broader 8.2 GW offshore wind development ambition, of which the Shinan Ui project is the first large-scale commercial phase.
Hanwha Ocean's role as both lead developer and turnkey EPC contractor is a structural innovation for the Korean market. By combining development and EPC in a single entity, the project avoids the interface risks and cost escalation that arise when developers and contractors negotiate scope boundaries. Hanwha Ocean announced the KRW 2.64 trillion turnkey EPC contract in January 2026, with its own share at KRW 1.97 trillion.
Stakeholder Details
Stakeholder Role | Individual/Organisation |
Lead Developer & EPC | Hanwha Ocean Co., Ltd. |
Consortium Partner (Utility) | Korea Midland Power (KOMIPO) |
Consortium Partner (Energy) | SK Eternix |
Consortium Partner (Construction) | Hyundai Engineering & Construction |
Consortium Partner (Fund) | Future Energy Fund |
Turbine Supplier | Vestas Wind Systems A/S |
Subsea Cable Supplier | LS Cable & System |
Steel/Substructure Supplier | Hyundai Steel Industries |
Engineering Consultant | Ramboll |
Co-Lead Arrangers (Finance) | Korea Development Bank (KDB) and Kookmin Bank. Co-lead arrangers of the KRW 2.89 trillion project financing |
Financial Regulator | Financial Services Commission (FSC) |
Trusted by Leading Manufacturers & EPCs
Find The Latest Offshore Wind Farm Projects In South Korea
Gain exclusive access to our industry-leading database of Offshore Wind Farm Projects opportunities with detailed project timelines & stakeholder information
No credit card Up-to-date coverage
Shinan Ui Offshore Wind Farm Current Status
The Shinan Ui Offshore Wind Farm is currently under construction, following a formal groundbreaking and financial close earlier in 2026. The groundbreaking was held on 16 July 2026 in Shinan County and was attended by Hanwha Ocean, Korea Midland Power (KOMIPO), government officials, and consortium partners. Vestas 26 × 15 MW turbine scheduled for delivery by 2027, with commercial operation targeted for 2029.
Shinan Ui Wind Farm Project Cost
Financial Items | Cost |
Total Project Cost | KRW 3.4 trillion (approximately USD 2.5 billion) |
Equity | KRW 510 billion (approximately USD 375 million) |
Total Debt | KRW 2.89 trillion (approximately USD 2.125 billion) |
Senior Loan | KRW 2.5 trillion (approximately USD 1.84 billion) |
Advanced Strategic Industries Fund | KRW 700 billion (approximately USD 515 million) |
Also Read: 5 Key Factors Affecting Floating Offshore Wind Farm Cost Breakdown & Offshore Wind Project Economics
Project Scope
The following is the project scope of the Shinan Ui Wind Farm Project:
Wind turbine supply & installation: Supply, transport, and installation of 26 × Vestas V236‑15.0 MW turbines, including blades, nacelles, towers, and associated balance‑of‑plant interfaces.
Foundations & substructures: Engineering, fabrication, and installation of 26 monopile foundations, transition pieces, and secondary steel to support turbines in the project’s water depths.
Inter‑array cable system: Supply and laying of medium‑voltage inter‑array cables linking each turbine to the OSS, including trenching/burial, protection works, and cable terminations.
Export cable system and landfall: Installation of HV export cables from the offshore substation to the onshore grid connection point, including landfall works, horizontal directional drilling (if required), and onshore cable sealing end compounds.
Project Timeline
Year | Event |
2029 | Expected commercial operation of the project |
16 July 2026 | Groundbreaking ceremony held at the Shinan National Sports Center in Shinan-gun, Jeollanam-do. |
9 April 2026 | Financial Services Commission (FSC) announces that the project financing agreement has been signed |
January 2026 | Hanwha Ocean announces it has signed a turnkey EPC contract for the Shinan Ui offshore wind project. |
2024-2025 | Project development, permitting, and consortium formation. |
Pre 2024 | The Shinan Ui project emerges as the first large-scale commercial phase of this development zone. |
Benefits
The following are the benefits of the project:
Catalyst for 15 MW turbine development: By selecting 26 × Vestas V236‑15.0 MW units, the project creates a clear, bankable demand signal that de‑risks and accelerates Korean development and certification of 15 MW‑class offshore turbines, supporting import substitution and supply‑chain sovereignty ahead of 2030 targets.
Enabler of RE100-compliant tech manufacturing and AI infrastructure: By supplying certified offshore wind power to the Honam AI data centre and semiconductor cluster, the project provides the renewable electricity needed for Samsung, SK Hynix, and AI firms to meet RE100 requirements, enhancing Korea’s industrial competitiveness in global tech supply chains.
Compete for international orders: By supplying substructures, subsea cables, offshore substations, and installation vessels from Korean suppliers, the project establishes an offshore wind value chain capable of delivering Korea’s 10.5 GW 2030 target and competing for international export orders.
Grid stability and renewable integration: The project provides a reference for integrating large offshore wind into KEPCO's system, informing grid codes, forecasting, and balancing for future phases.
Enables real-world testing: By delivering 390 MW of variable offshore generation with advanced power electronics and grid-forming capabilities, it enables real-world testing of frequency regulation, voltage support, and curtailment strategies.
Conclusion
The Shinan Ui Offshore Wind Farm marks a turning point for South Korea’s energy and industrial policy, transitioning from pilot-scale offshore developments to a bankable, utility-grade asset. Using 26 × 15 MW Vestas turbines and an expected completion target by 2029, it will more than double the country’s operational offshore wind capacity and establish a replicable template for subsequent phases under the 10.5 GW 2030 target.
By linking certified renewable output to the Honam AI data centre and semiconductor cluster strategy, it addresses RE100 compliance pressures faced by Samsung, SK Hynix, and emerging AI infrastructure developers, thereby making advanced technology manufacturing and compute in Korea commercially viable in a carbon-constrained global market.
Track the Latest & Upcoming Offshore Wind Farm Projects In South Korea
Subscribe to our upcoming and ongoing Offshore Wind Farm Projects in South Korea with ease to access reliable, high-quality insights on forthcoming and completed projects across the country.
Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.
Start a free demo to take your business to the next level.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.