Project at a Glance | |
Project Name | Petrojarl Rosebank FPSO |
Previous Name | Petrojarl Knarr |
Project Status | Development/pre-start-up phase |
Field Location | Approximately 130 km north-west of the Shetland Islands |
Project Operator | Adura Operations Limited |
FPSO Owner/Lessor | Altera Infrastructure — owner of the Petrojarl Rosebank |
FPSO Refurbishment Location | DP World Drydocks, Dubai |
FPSO Production Capacity | Approximately 70,000 barrels of oil per day |
Gas Production Capacity | More than 21 million cubic feet per day |
First Oil Target | 2026-27 |
Field Life | Approximately 25 years from production start |
Project Overview
The Petrojarl Rosebank FPSO is the Floating Production, Storage & Offloading (FPSO) Vessel for the Rosebank field. It is the UK’s largest undeveloped Oil & Gas Field, located approximately 130 km north-west of the Shetland Islands.
The field, estimated to contain 300 million barrels of oil equivalent, is being developed by Adura Operations Limited (a 50:50 joint venture between Equinor UK and Shell UK), with Adura holding an 80% stake and Ithaca Energy the remaining 20%.
The FPSO, formerly known as the Petrojarl Knarr and rechristened the Petrojarl Rosebank, arrived at its field location west of Shetland in May 2026 after extensive upgrades at DP World's drydocks in Dubai. Drilling of production and injection wells is underway. Phase I production is targeted for 2026-2027.
The Petrojarl Rosebank FPSO will produce approximately 70,000 barrels of oil per day and more than 21 Million Cubic Feet per Day (MMscfd) of gas when operational. Oil will be exported via shuttle tankers to refineries; gas will be transported via a new export pipeline to the West of Shetland Pipeline System and then to the UK national grid.
The FPSO is designed to be electrification-ready, capable of receiving power from a future power-from-shore connection that Equinor, Adura, and the UK government are exploring for the West of Shetland cluster of fields.
Rosebank FPSO Location
Rosebank FPSO is located in the Faroe-Shetland Channel, on the north-west edge of the UK Continental Shelf (UKCS). It is about 130 km northwest of Shetland and roughly 15 km east of the UK/Faroe median line. It is under 1,100 m of water and is associated with UKCS Block 205/2a.
Project Background
The project's path to first oil is the most legally complex of any major UK oil development in recent history. The original production consent, granted by the Conservative UK government in September 2023, was ruled unlawful by Scotland's Court of Session on 29 January 2025.
This ruling followed the UK Supreme Court's landmark June 2024 decision in Finch v Surrey County Council that Environmental Impact Assessments for fossil fuel projects must include an assessment of Scope 3 emissions (the emissions produced when the extracted oil and gas is burned by end users).
Adura has since submitted a new Environmental Impact Assessment incorporating Scope 3 emissions data. The UK's Offshore Petroleum Regulator for Environment and Decommissioning (OPRED) has opened a public consultation that runs until 17 August 2026.
Despite the legal uncertainty over production consent, Adura and its predecessors continued physical development work throughout. TechnipFMC began subsea installation work in 2024. The Petrojarl Rosebank FPSO departed its Dubai upgrade facility in late February 2026.
Trusted by Leading Manufacturers & EPCs
Find The Latest FPSO Projects In The United Kingdom
Gain exclusive access to our industry-leading database of FPSO project opportunities with detailed project timelines & stakeholder information
No credit card Up-to-date coverage
Rosebank FPSO Current Status
Rosebank FPSO is currently in the development/pre-start-up phase, with regulatory consultation opening in July 2026 and Phase I start-up still planned for 2026–2027. In May 2026, the vessel had arrived at the Rosebank field location and was being hooked up to the subsea infrastructure. Drilling of Phase I production and injection wells: four producers and three injectors, is progressing in parallel.
Stakeholder Details
Stakeholder Role | Organisation/Individual |
Operator (80% share) | Adura Operations Limited |
Field Partner (20%) | Ithaca Energy SP E&P Limited |
FPSO Owner | Altera Infrastructure |
Subsea Contractor | TechnipFMC |
Regulatory Authority | Offshore Petroleum Regulator for Environment and Decommissioning (OPRED) |
UK Secretary of State | Secretary of State for Energy Security and Net Zero |
Rosebank FPSO Project Cost
Cost/Financial Item | Details |
Total Rosebank Investment | 8.7 billion pounds |
Original Phase I FID Cost | USD 3.8 billion |
Combined Rosebank + Jackdaw Total Investment | 10.8 billion pounds |
TechnipFMC Subsea Contract | USD 500 million |
GVA Impact | 2.87 billion pounds in gross value added over operational lifespan |
Project Timeline
Year | Event |
2026-2027 | First production expected from the field |
17 August 2026 (Deadline) | OPRED public consultation on Rosebank Environmental Statement closes. |
June 2026 | OPRED opens public consultation on Rosebank Environmental Statement |
May 2026 | Petrojarl Rosebank FPSO arrives at its field location west of Shetland |
February 2026 | Petrojarl Rosebank FPSO departs DP World Drydocks, Dubai |
October 2025 | Adura submits a new full Environmental Impact Assessment for Rosebank incorporating Scope 3 emissions assessment. |
1 December 2025 | Adura Operations Limited launches — Aberdeen-based 50:50 JV combining the UK offshore oil and gas operations of Equinor and Shell. |
Design & Engineering Details
FPSO Previous Name | Petrojarl Knarr |
Charter Agreement | Agreed between Equinor and Altera Infrastructure in 2022 |
Refurbishment Facility | DP World Drydocks, Dubai — extensive upgrades and modifications for West of Shetland service since 2023 |
Oil Production Capacity | Approximately 70,000 barrels of oil per day |
Gas Treatment Capacity | More than 21 million cubic feet per day (MMcfd) |
Electrification Design | FPSO designed to be electrification-ready; future power-from-shore connection being explored for the West of Shetland cluster; electrification would reduce CO2 intensity from ~12 kg to ~3 kg CO2/boe |
Field Mooring | Permanently moored at the Rosebank field location west of Shetland |
Conclusion
Rosebank FPSO plays a significant role in the redevelopment of the UK North Sea, combining a redeployed FPSO with subsea tie-backs to bring a major undeveloped field into production. The vessel is designed to support domestic energy supply while limiting incremental emissions through reuse of an existing vessel and other mitigation measures.
Overall, the Rosebank FPSO represents one of the UK’s most significant offshore developments, supporting production performance and execution, along with regulatory scrutiny, environmental expectations, and the evolving energy transition agenda.
Track the Latest & Upcoming FPSO Projects In The United Kingdom
Subscribe to our upcoming and ongoing FPSO Projects in the United Kingdom with ease to access reliable, high-quality insights on forthcoming and completed Projects across the country.
Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.
Start a free demo to take your business to the next level.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.