Project Matador AI Data Center And Power Campus

project_profile

Project Matador AI Data Center And Power Campus

Updated on Oct 28, 2026, 12:39 PM IST
Written by Siddhi Jain

 

Project at a Glance

Project Name

Project Matador

Project Type

Private, behind-the-meter power and AI data center campus 

Project Status

Under development

Project Location

Carson County, Texas Panhandle 

Project Developer

Fermi Inc. (Fermi America) 

Campus Capacity

17 GW private power and AI campus 

First Data Center

Phase one: 222 MW of total facility power 

Lease Value

About USD 6.5 billion over an initial 15-year term for phase one

Gas Generation Equipment

About 2 GW of generation assets secured 

Turbines Delivered

Six Siemens SGT-800 (Port of Houston, February 2026); three Siemens SGT6-5000F, up to 780 MW combined (Houston, July 2026), first units on site by September 2026; second F-class unit and two generators (October 2026); three GE Vernova 6B (arrived 15 October 2026)

Investment to Date

More than USD 1.5 billion invested in buildout 

 

Project Overview

Project Matador is a private power and AI data center campus on a Texas Tech-owned site in the Panhandle. Developed by Fermi Inc., the project combines large-scale on-site power generation with hyperscale AI-ready data-center capacity, allowing compute tenants to secure dedicated power alongside their facilities. 

It’s the world’s largest private HyperGrid™ campus, with 6 of 17GW already permitted on 8,400 acres in the Texas Panhandle. Matador has secured 2 GW of generation assets and has secured nearly USD 1.5 billion in committed financing from leading lenders.

The ramp beyond the first data center is subject to entering into binding customer agreements. The first lease, for 222 MW of facility power, represents about 1.3 percent of the stated 17 GW. It is described as one of the largest upcoming data centers in Texas. 

The company says it will build the power infrastructure and lease turnkey data center capacity, and describes a behind-the-meter model with no grid interconnection queue, supplemented by 86 MW of utility power from Xcel Energy.

 

Project Matador Location

Project Matador is located in Carson County, Texas, in the Texas Panhandle. It is situated near Amarillo and adjacent to the U.S. Department of Energy’s Pantex Plant. Fermi controls the core site through a 99-year ground lease with the Texas Tech University System, covering approximately 8,400 acres. 

Its location offers proximity to natural-gas production, two major fiber-optic corridors, the Ogallala Aquifer, and the Pantex facility, attributes Fermi considers strategically valuable for fuel supply, connectivity, water access, security, and potential future nuclear development. 

 

Technical Specifications

Campus Capacity (Planned)

17 GW combined power and AI campus 

First Data Center

222 MW of facility power for TensorWave 

Gas Turbines

Siemens SGT-800 (six units), Siemens SGT6-5000F (three units, up to 780 MW combined, plus a second F-class unit), GE Vernova 6B (three units, refurbished)

Gas Supply

Nearly 5 miles of high-pressure gas pipeline installed 

Grid Power

86 MW brought from Xcel Energy 

 

Project Background

Fermi America announced Project Matador as an 11 GW private power and data center campus near Amarillo, later increasing it to 17 GW. The land is owned by the Texas Tech University System and held by Fermi under a 99-year ground lease executed in April 2025, with Texas Tech limited to revenue participation and covenant enforcement per Fermi's NRC application. 

Fermi applied to the NRC in June 2025 for four AP1000 reactors. In September 2025, it signed a non-binding letter of intent with an investment-grade prospective tenant, which later agreed to provide up to USD 150 million for construction but ended the funding agreement in December 2025. A shareholder lawsuit followed. 

In 2026, Fermi obtained a TCEQ air permit (February), took delivery of Siemens SGT-800 turbines in Houston (February), repaid its Macquarie loan and secured new equipment financing (Q1), removed CEO Toby Neugebauer (April), and signed the TensorWave lease (August).

 

Project Matador Current Status

Currently, Project Matador is under development, moving from site works to construction. No data center is operating, and the company reports no operating revenue. Fermi signed its first binding customer agreement on 10 August 2026 (TensorWave, 222 MW, about USD 6.5 billion over 15 years), subject to project guarantees and financing.

Lee McIntire became CEO on 11 August 2026 after founder Toby Neugebauer was removed in April. Gas turbines are arriving on site (October 2026), and an NRC staff preliminary recommendation favours the combined licences for four AP1000 reactors.

Trusted by Leading Manufacturers & EPCs

Find The Latest Data Center Projects In The United States

Gain exclusive access to our industry-leading database of Data Center Project opportunities with detailed project timelines & stakeholder information

Request Free Trial Learn More

No credit card Up-to-date coverage

 

Project Matador Completion Date

Project Matador does not have a single official completion date. Fermi describes it as a multi-phase, multi-decade buildout extending through 2038, with initial commercial energization and first-tenant commissioning planned in late 2027. 

 

Stakeholder Details

Stakeholder

Role

Fermi Inc. (Fermi America)

Developer, owner, & lessor

Toby Neugebauer

Co-founder, former CEO

TensorWave

Anchor tenant

AMD 

Credit support provider

Texas Tech University System

Landowner

Hillcore Energy

Power Developer

CBRE

Data Center O&M

NAES

Gas Fleet Operator

Siemens Energy & GE Vernova

Turbine Suppliers; SGT-800, SGT6-5000F, 6B units delivered

City of Amarillo

Water Supplier

Project Matador Cost Details

Fermi Inc. has not officially disclosed the total estimated cost for Project Matador. Fermi has already invested more than USD 1.5 billion in site buildout as of mid-2026. 

 

Project Scope

The following is the project scope of Project Matador:

  • Private power and AI data-center campus: Fermi is developing an energy-first campus in Carson County, Texas, to supply dedicated power directly to AI and hyperscale computing tenants. 

  • Natural gas-fired generation: The core generation scope includes gas turbines and combined-cycle capacity, supported by dual natural-gas interconnections and firm fuel-supply arrangements. 

  • Battery energy storage and power-quality systems: Fermi will deploy battery energy storage systems (BESS) and related power-quality infrastructure to manage rapid AI load changes, improve reliability, support commissioning, and provide ride-through capability during outages. 

  • Advanced nuclear capacity: The long-term scope includes nuclear baseload power, subject to licensing and regulatory approvals. The U.S. Nuclear Regulatory Commission selected Project Matador as an inaugural participant in its Environmental Impact Statement pilot program, which is intended to help streamline advanced-reactor licensing. 

  • Cooling and water infrastructure: The scope includes on-site water distribution, storage, and cooling-related infrastructure to support power generation and data-center operations. The site overlies the Ogallala Aquifer, and Fermi has secured groundwater rights as part of early site development. 

 

Trusted by Leading Manufacturers & EPCs

Find The Latest Data Center Projects In The United States

Gain exclusive access to our industry-leading database of Data Center Project opportunities with detailed project timelines & stakeholder information

Request Free Trial Learn More

No credit card Up-to-date coverage

 

Project Timeline

Year

Event

2027

First TensorWave data center delivery expected

October 2026

Three GE Vernova 6B turbines and a second Siemens F-class turbine arrive on site

September 2026

First SGT6-5000F turbines on site 

11 August 2026

Lee McIntyre becomes CEO  

10 August 2026

Binding TensorWave lease announced (222 MW, about USD 6.5 billion, 15 years) 

March 2026

Campus capacity raised to 17 GW 

February 2026

TCEQ approves major air permit (about 6 GW); six SGT-800 turbines arrive at Port of Houston 

 

Benefits

The following are the benefits of the project: 

  • Reduced dependence on the public grid: Fermi plans to generate the substantial majority of power on-site through a behind-the-meter private power system. This is intended to reduce reliance on congested transmission networks and long interconnection queues. 

  • Faster access to power: By co-locating generation, substations, and data-center capacity on one campus, Fermi aims to shorten the time required for tenants to secure power and begin operations. This supports faster deployment of AI infrastructure. 

  • Lower transmission losses: The project lowers transmission losses because power is generated close to tenant facilities, reducing long-distance transmission losses. This improves overall energy efficiency compared with importing power from distant sources. 

  • Water conservation: The campus plans to use dry and hybrid cooling, closed-loop water reuse, recycled water, and rainfall capture. Fermi says these measures are designed to reduce water consumption substantially compared with conventional water-cooled systems. 

 

Project Matador Latest News

Below is the latest news of Project Matador:

Three GE Vernova 6B gas turbines arrived at the site (October 15, 2026): 

Fermi announced that three GE Vernova 6B gas turbines were delivered to Project Matador in Carson County after final preparation and transport to the Texas Panhandle. The company said the delivery supports its planned private-grid power buildout, which it now describes as targeting up to 17 GW of capacity. 

 

Conclusion

Project Matador is a strategic project to combine hyperscale AI data centers with dedicated on-site power generation in Amarillo, Texas. Its integrated model, spanning data-center capacity, nuclear, gas, solar, battery, fiber, and cooling infrastructure, positions it as one of the largest powered AI campuses in the United States.

Its phased development model also provides flexibility, allowing infrastructure and capacity to be delivered progressively as demand and financing evolve. Upon completion, it is expected to strengthen the Texas Panhandle’s position as a major hub for artificial intelligence, advanced computing, and digital infrastructure.

 

Track the Latest Data Center Projects In The United States

Subscribe to our upcoming and ongoing Data Center Projects in the United States with ease to access reliable, high-quality insights on forthcoming and completed Projects across the country.

Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies

Start a free demo to take your business to the next level.

Tags