Bonga FPSO: OML 118, Offshore Nigeria

project_profile

Bonga FPSO: OML 118, Offshore Nigeria

Updated on Sep 18, 2026, 04:26 PM IST
Written by Siddhi Jain

 

Project at a Glance

Project Name

Bonga FPSO

Project Location

OML 118, approximately 120 km offshore the Niger Delta, Nigeria 

Project Status

Operational: Bonga Main/Northwest Producing; Bonga North Under Construction; Bonga South West-Aparo FPSO Tender Revived 

Operator

Shell Nigeria Exploration and Production Company Ltd (SNEPCo) 

FPSO Production Capacity

225,000 barrels of oil per day  

FPSO Gas Processing Capacity

150 million standard cubic feet per day  

Recent Maintenance (Turnaround)

February 1 – March 6, 2026 

Bonga North - Peak Production

110,000 barrels of oil per day 

Bonga North - Wells

8 production wells + 8 water injection wells  

Bonga North - Water Depth

900–1,300 metres 

 

Project Overview

The Bonga FPSO is a centrepiece of Nigeria's deepwater oil industry. It is the floating production, storage and offloading (FPSO) vessel that brought Nigeria's first-ever deepwater production online in November 2005 and remains, two decades later, one of the country's single most important pieces of energy infrastructure.

Located approximately 120 km offshore the Niger Delta, it is operated by Shell's Nigerian deepwater subsidiary, SNEPCo. The FPSO has a processing capacity of 225,000 barrels of oil per day (bopd) and 150 million standard cubic feet of gas per day, handling output from the Bonga Main and Bonga Northwest fields.

In December 2024, SNEPCo took the Final Investment Decision (FID) on Bonga North for USD 5 billion, targeting more than 300 million barrels of oil equivalent in recoverable resources, peak production of 110,000 barrels of oil per day, and first oil expected around 2030. 

The Bonga North scope includes drilling and completing 8 production wells and 8 water injection wells in 900-1,300 m water depth, installing new subsea hardware, modifying the existing Bonga FPSO's topsides, and undertaking life-extension work to accommodate the additional production volumes. 

The Bonga FPSO shut down for a 34-day statutory turnaround maintenance programme. It ran from 1 February to 6 March 2026. SNEPCo Managing Director Ronald Adams described the exercise as designed to 'ensure safe, efficient operations for another 15 years.’

 

Bonga FPSO Location

The Bonga FPSO is permanently moored at the Bonga oilfield in Nigeria’s deep offshore waters, about 120 km southwest of the Niger Delta and around 50 nautical miles off the Nigerian coast in the Gulf of Guinea. It operates in Oil Mining Lease (OML) 118, in water depths of approximately 1,000–1,125 metres.

 

Project Background

The Bonga field was discovered in the late 1990s and brought on stream in November 2005 as Nigeria's first deepwater development. It opened the way for the broader deepwater exploration and development across OML 118 and neighbouring blocks.

Bonga Northwest was developed as the first satellite tie-back to the original FPSO, adding incremental production without requiring new floating infrastructure. By 2025, however, combined Bonga Main and Northwest output had declined to 121,000 bopd. 

Bonga North had been under evaluation for years before SNEPCo formally reached Final Investment Decision on December 16, 2024. The USD 5 billion sanctioned development targets more than 300 million barrels of oil equivalent in recoverable resources via the production and water injection wells in 900-1,300 m water depth.

Running in parallel to the Bonga North's construction, and the FPSO's own maintenance cycle, is the separate revival of Bonga South West-Aparo, a discovery dating to 2001 that has remained undeveloped for a quarter-century despite being the last of several satellites of the giant Bonga Field that has not reached sanction.

BSWA's complexity is compounded by its status as a straddle structure spanning two different operatorships (Shell-operated OML 118 and Chevron-operated OMLs 132/140). Moreover, it requires an entirely new, dedicated 150,000 bpd FPSO, since it cannot draw on the existing Bonga FPSO's spare capacity in the way Bonga North can.

Shell's January 2026 relaunch of the FPSO tender process represents the most concrete forward momentum BSWA has shown in years, though the project's path to FID is targeted by Shell for 2027.

 

Bonga FPSO Current Status

The Bonga FPSO is currently operational and producing oil after completing a major turnaround maintenance (TAM) in early March 2026. The associated Bonga South‑West/Aparo deepwater project is advancing toward an FID: pre‑FEED is complete, and a preferred FPSO contractor has been selected.

 

Stakeholder Details

Stakeholder Role

Individual/Organisation

Operator

Shell Nigeria Exploration and Production Company Ltd (SNEPCo)  

Regulatory Authority

Nigerian Upstream Petroleum Regulatory Commission (NUPRC) 

Turnaround Contractor Base

55 companies engaged for the February-March 2026 turnaround, 43 wholly Nigerian-owned; 8 of 12 international service providers maintain Nigerian operational bases 

 

Trusted by Leading Manufacturers & EPCs

Find The Latest FPSO Projects In Nigeria

Gain exclusive access to our industry-leading database of FPSO Project opportunities with detailed project timelines & stakeholder information

Request Free Trial Learn More

No credit card Up-to-date coverage

 

Bonga FPSO Project Cost Details

Cost/Financial Item

Details

Bonga North Resource Value

Over 300 million boe recoverable 

Bonga South West-Aparo Estimated Value

Approximately USD 20 billion

Turnaround Maintenance Cost

Not disclosed separately. 

 

 

Project Timeline

Year

Event

2030

First Oil Production expected from Bonga North

2027

Expected Final Investment Decision on Bonga South West-Aparo 

6 March 2026

SNEPCo completes the Bonga FPSO turnaround 

1 February 2026

SNEPCo begins statutory turnaround maintenance on the Bonga FPSO 

January 2026

Shell restarts preparatory work on Bonga South West-Aparo by launching a new FPSO tender

16 December 2024

SNEPCo takes Final Investment Decision on Bonga North 

October 2022

Bonga FPSO undergoes its previously planned/scheduled maintenance turnaround

November 2005

Bonga FPSO comes online 

2001

Bonga South West-Aparo (BSWA) discovered 

 

Design & Engineering Details

Oil Processing Capacity

225,000 barrels of oil per day  

Gas Processing Capacity

150 million standard cubic feet per day  

Water Depth

Exceeding 1,000 metres 

Distance from Shore 

Approximately 120 km offshore Niger Delta, Nigeria 

Field Served (Current)

Bonga Main and Bonga Northwest 

Field to be Added

Bonga North  

Design Life Extension (2026 Turnaround)

A further 15 years of safe, efficient operation 

Turnaround Duration (2026)

34 days (February 1 – March 6, 2026); delivered 11 days ahead of schedule 

Turnaround Scope

Inspections, certification, regulatory checks, integrity upgrades, engineering modifications, subsea assurance activities

 

Conclusion

The Bonga FPSO project, operated by Shell Nigeria Exploration and Production Company (SNEPCo), achieved its first oil in November 2005. It stands as Nigeria’s pioneering deepwater oil development and a cornerstone of the country’s offshore production strategy.

The combination of life‑extension works on the original vessel and the scale of the new development promises to stabilize near‑term production, boost medium‑term output, and attract significant foreign capital while leveraging local content and advanced subsea and digital technologies already proven at Bonga. 

Taken together, the existing Bonga FPSO and the forthcoming Bonga South‑West/Aparo expansion reinforce Nigeria’s position as a competitive deepwater province.

 

 

Track the Latest & Upcoming FPSO Projects In Nigeria

Subscribe to our upcoming and ongoing FPSO Projects in Nigeria with easy access to reliable, high-quality insights on forthcoming and completed Projects across the country.

Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.

Start a free demo to take your business to the next level.

Tags

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile