Washington has more than 50 data center projects representing an estimated USD 12.9 billion construction pipeline. The state's combination of abundant hydropower, available land, and established technology infrastructure continues to attract hyperscale, colocation, and enterprise investment. With most projects still in early development, the pipeline points to significant future growth in data centers in Washington State.
The new data center projects in Washington state, including the AWS Wallula Gap Data Center Campus, West Richland Data Center Campus, and Microsoft's EAT06, EAT13, and EAT09 projects are shaping this pipeline to become one of the largest growing data center markets in the United States.
This article explores the upcoming data center projects in Washington, covering major developments, project locations, investment values, development status, and planned capacity.
How Many Data Centers Are in Washington State?
According to the Blackridge Research Data Center Database, Washington currently has more than 50 data center projects. These projects represent a combined construction pipeline valued at approximately USD 12.9 billion, highlighting Washington's growing role in U.S. hyperscale, colocation, and enterprise data center development.
The majority of Washington's tracked pipeline remains in the early development stage. 13 projects are in planning, accounting for approximately 87% of the upcoming project pipeline, while one project is announced and one is under construction. The database tracks approximately 18 MW of capacity for projects currently under construction.
Investment in Washington's upcoming data center projects ranges from approximately USD 100 million to USD 4.8 billion per project, with an average investment of around USD 862 million. This includes major hyperscale developments, proposed AI and cloud campuses, colocation facilities, and enterprise data center projects.
List of New Data Center Projects in Washington (United States)
Data Center Project | Capacity | Developer | Location | Current Stage |
AWS Wallula Gap Data Center Campus | 1,200 MW | Amazon | Walla Walla County, Washington | Planned |
West Richland Data Center Campus | 912 MW | Trammell Crow Company | Benton County, Washington | Proposed |
Microsoft EAT06 | 57 MW | Microsoft | Douglas County, Washington | Under-construction |
Microsoft EAT13 | 57 MW | Microsoft | Chelan County, Washington | Planned |
Microsoft EAT09 | 57 MW | Microsoft | Douglas County, Washington | Planned |
Trusted by Leading EPCs & Manufacturers
Find the Latest Data Center Projects Across United States
Gain exclusive access to our industry-leading database of data center project opportunities with detailed project timelines and stakeholder information.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
AWS Wallula Gap Data Center Campus
The AWS Wallula Gap Data Center Campus is a planned USD 4.8 billion to USD 5 billion hyperscale data center development near Burbank in Walla Walla County, Washington. Developed by Amazon Web Services (AWS), the campus will occupy approximately 553-554 acres at the Wallula Gap Business Park and is planned across four development phases.
Capacity and Campus Infrastructure
The full campus is planned to include 16 single-story data center buildings totaling more than 3.4 million square feet. Each of the four phases is expected to cover approximately 125-134 acres and include around four buildings.
The capacity is approximately 300 MW per phase, although the final total campus capacity has not been officially confirmed by AWS. Early development plans focus on an initial cluster of three buildings within the first phase. The campus is designed primarily for cloud computing and AI workloads. Cooling is expected to rely primarily on air cooling, with water used only during limited operating conditions.
Development Status and Timeline
AWS acquired approximately 554 acres from the Port of Walla Walla for USD 36 million, with the transaction closing in early 2026. The project, initially developed under the name Advance Phase LLC, is progressing through local planning, environmental review, and permitting processes.
As of August 2026, construction has not yet fully commenced, and the project is expected to be developed in phases. Industry tracking indicates potential site development and phased construction between 2028 and 2034, subject to regulatory approvals and infrastructure development.
Key Contractors and Partners
Company / Entity | Role |
Amazon Web Services (AWS) / Amazon Data Services | Developer, owner, and future operator |
Port of Walla Walla | Former landowner and provider of water and process water infrastructure |
Columbia Rural Electric Association (REA) | Local power transmission and substation infrastructure |
Energy Northwest | Clean energy partner; agreement for up to 320 MW from future SMR projects |
Walla Walla County | Environmental review, permitting, and development oversight |
West Richland Data Center Campus
The West Richland Data Center Campus is a proposed large-scale data center development being explored by Trammell Crow Company at the Lewis & Clark Ranch in West Richland, Benton County, Washington. The developer is evaluating approximately 500 to 1,000 acres within the more than 7,000-acre ranch owned by Frank Tiegs LLC.
Capacity and Power Infrastructure
The project is listed in regional interconnection records as Project L0621, with a proposed power capacity of approximately 912 MW. The project is associated with the Bonneville Power Administration (BPA) transmission system, while Benton Rural Electric Association (REA) is involved in preliminary power and infrastructure feasibility discussions.
The 912 MW figure represents proposed interconnection capacity and remains subject to further studies and project development.
Development Status and Timeline
As of August 2026, the project remains in the feasibility and planning stage, with Trammell Crow evaluating the site and infrastructure requirements. The final campus size, number of buildings, investment value, and end user have not yet been publicly disclosed.
Interconnection records indicate a potential online target of around March 2028, subject to utility approvals, permitting, infrastructure development, and final investment decisions.
Key Contractors and Partners
Company / Entity | Role |
Trammell Crow Company | Project developer |
Frank Tiegs LLC | Landowner |
Benton Rural Electric Association (REA) | Local power and infrastructure coordination |
Bonneville Power Administration (BPA) | Regional transmission system |
City of West Richland | Local planning and development authority |
Read Next
Microsoft EAT06
Microsoft EAT06 is a 57 MW data center project being developed at 875 Urban Industrial Way in East Wenatchee, Douglas County, Washington. The facility forms part of Microsoft's expanding East Wenatchee data center campus supporting cloud and AI infrastructure.
Capacity and Infrastructure
The facility is planned to provide approximately 57 MW of power capacity and cover roughly 240,000 to 244,000 square feet. EAT06 is being developed alongside the adjacent EAT09 facility as part of Microsoft's broader multi-building deployment in the Pangborn/East Wenatchee area.
Douglas County PUD is supporting the high-capacity power infrastructure required for the development. The broader campus also benefits from regional infrastructure projects supporting cooling, power, and connectivity.
Development Status and Timeline
As of August 2026, Microsoft EAT06 is under construction, with site development and building work progressing. The facility is expected to become operational in 2027, subject to construction completion, equipment installation, and grid integration.
Key Contractors and Partners
Company / Entity | Role |
Microsoft Corporation | Developer and future operator |
Evans General Contractors | General contractor |
Stantec | Civil engineering and design services |
Environmental Systems Design (ESD) | Engineering services |
Sheehan Nagle Hartray Architects | Architectural design |
Douglas County PUD | Power and electrical infrastructure |
Advantage Dirt | Site preparation and earthwork |
Microsoft EAT13
Microsoft EAT13 is a planned multi-phase data center development in Malaga, Chelan County, Washington. Developed by Microsoft, the project is located along Malaga Alcoa Highway on a 102.5-acre site and is designed to support the company's expanding cloud and AI infrastructure in Central Washington.
Capacity and Infrastructure
The initial EAT13 data center building is designed for approximately 57 MW of capacity and will cover around 232,239 square feet. The broader site is planned to accommodate up to three data center buildings, allowing for future expansion based on demand.
The development includes supporting infrastructure such as an electrical substation, water tanks, and dedicated water infrastructure. Water demand is estimated at approximately 83 gallons per minute per building, or up to around 121,000 gallons per day.
Development Status and Timeline
Construction on the first phase began in June 2023. As of August 2026, the project is in the construction and development stage, with the first facility progressing toward completion.
The initial EAT13 facility is expected to become operational around 2027, while the timing of additional buildings will depend on Microsoft's future cloud and AI capacity requirements.
Key Contractors and Partners
Company / Entity | Role |
Microsoft Corporation | Developer and future operator |
Chelan County | Local planning and permitting authority |
Chelan County PUD | Regional power and electrical infrastructure |
Malaga Water District / Local water infrastructure | Water supply and infrastructure coordination |
Qcells | Renewable energy supply partner through Microsoft's broader solar procurement agreements |
Microsoft EAT09
Microsoft EAT09 is a planned 57 MW hyperscale data center in East Wenatchee, Douglas County, Washington. The facility forms part of Microsoft's East Wenatchee Campus and is being developed alongside the adjacent EAT06 facility to support Azure cloud and AI workloads.
Capacity and Infrastructure
EAT09 is designed for approximately 57 MW of power capacity and will occupy around 240,000 square feet. The single-story facility is part of Microsoft's broader multi-phase data center development in the Pangborn area.
The project is linked to EAT06, with both facilities forming part of an interconnected development footprint. Douglas County PUD is expected to provide the high-capacity power infrastructure supporting the campus.
Development Status and Timeline
As of August 2026, EAT09 remains in the planned and development stage. The facility is expected to become operational around 2028, subject to construction progress, equipment installation, and utility infrastructure development.
Key Contractors and Partners
Company / Entity | Role |
Microsoft Corporation | Developer and future operator |
Sheehan Nagle Hartray Architects | Architectural and building design |
Environmental Systems Design (ESD) | Engineering and MEP services |
Douglas County PUD | Power infrastructure and utility services |
Chelan-Douglas Regional Port Authority | Regional development and infrastructure support |
KRCI Construction | Cooling water infrastructure contractor |
Read Next
Data Center Market Overview in Washington State
Washington's data center market is divided into several distinct geographic clusters.
Central Washington is the state's largest hyperscale development area, with Quincy serving as a major hub for largest data center developers like Microsoft, Sabey Data Centers, Vantage Data Centers, CyrusOne, H5 Data Centers, and NTT. The region benefits from access to Columbia River hydropower and large-scale industrial sites.
East Wenatchee and Malaga have emerged as additional hyperscale locations, driven primarily by Microsoft's continued expansion. These projects are supported by regional public utility districts and new power, cooling, and water infrastructure.
Seattle and the Puget Sound region operate differently from Central Washington. The Seattle market is more focused on colocation, network connectivity, enterprise infrastructure, and carrier-dense facilities. Operators include Equinix, Digital Realty, Sabey, H5 Data Centers, DataBank, Digital Fortress, and others.
Eastern Washington is becoming an increasingly important location for new large-scale developments. AWS is planning its multibillion-dollar Wallula Gap campus, while Trammell Crow Company is evaluating a large data center development in West Richland.
Data Centers in Washington State: Major Locations
Location | Major Operators | Market Focus |
Quincy | Microsoft, Sabey, Vantage, CyrusOne, H5, NTT | Hyperscale and cloud |
East Wenatchee | Microsoft | Cloud and AI infrastructure |
Malaga | Microsoft | Hyperscale expansion |
Seattle / Puget Sound | Equinix, Digital Realty, Sabey, H5, DataBank | Colocation and connectivity |
West Richland / Tri-Cities | Trammell Crow and proposed developers | Proposed hyperscale and AI infrastructure |
Wallula Gap | AWS | Large-scale cloud and AI campus |
Quincy
Quincy is one of Washington's largest and most established hyperscale data center markets. Its growth has been supported by access to low-cost Columbia River hydropower, high-capacity utility infrastructure, industrial land, fiber connectivity, and a climate suitable for large-scale data center operations. Major operators in Quincy include Microsoft, Sabey Data Centers, Vantage Data Centers, CyrusOne, H5 Data Centers, and NTT.
East Wenatchee
East Wenatchee is a growing Microsoft data center location in Douglas County. Microsoft's EAT06 and EAT09 facilities are part of the company's expanding regional infrastructure supporting cloud and AI workloads.
Malaga
Malaga, located in Chelan County near Wenatchee, is another major Microsoft development area. Microsoft's Malaga campus includes EAT13 and has the potential to support multiple large data center buildings.
Seattle and Puget Sound
Seattle remains Washington's primary colocation and connectivity market. The region has a large concentration of network providers, enterprise infrastructure, cloud connectivity services, and carrier hotels.
The market is structurally different from Quincy and Central Washington because Seattle developments are generally more focused on colocation and network-intensive infrastructure rather than large greenfield hyperscale campuses.
Tri-Cities and West Richland
The Tri-Cities region is emerging as a potential new location for large data center developments. Projects in West Richland and Richland are being evaluated against growing concerns about electricity demand, transmission capacity, and regional infrastructure.
Wallula Gap and Walla Walla County
Wallula Gap Business Park in Walla Walla County is the proposed location of AWS's major multibillion-dollar data center campus. The project represents one of the largest upcoming data center developments in Washington.
AI Data Centers in Washington State
Washington is increasingly attracting infrastructure intended to support artificial intelligence and high-density cloud computing workloads.
Microsoft, AWS, and other hyperscale operators are expanding infrastructure capable of supporting AI workloads, but many individual facilities have not publicly disclosed whether they will be dedicated exclusively to AI training, AI inference, cloud computing, or a combination of workloads.
The strongest AI-related development trends in Washington include:
AWS's large-scale Wallula Gap campus
Microsoft's East Wenatchee and Malaga expansions
Proposed large-load data center developments in West Richland and the Tri-Cities
Growing demand for high-density computing infrastructure
New investments in nuclear, renewable, and grid infrastructure
Washington's AI data center pipeline is therefore best described as a rapidly growing hyperscale and high-density computing market rather than a collection of publicly confirmed AI-only facilities.
Trusted by Leading EPCs & Manufacturers
Find the Latest Data Center Projects Across United States
Gain exclusive access to our industry-leading database of data center project opportunities with detailed project timelines and stakeholder information.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
Seattle Data Center and Colocation Market
Seattle is Washington's primary colocation and connectivity market. Unlike Quincy and Central Washington, where hyperscale campuses dominate, Seattle's data center ecosystem is driven by enterprise customers, network connectivity, cloud on-ramps, financial services, telecommunications, and colocation demand.
Major operators in the Seattle and Puget Sound market include:
Equinix
Digital Realty
Sabey Data Centers
H5 Data Centers
DataBank
Digital Fortress
Lumen
Centeris
Seattle is also an important network hub because of its connection to international subsea cable systems and Pacific Northwest fiber infrastructure.
Seattle Data Center Moratorium
Seattle has also introduced stricter controls on large new data center developments.
In June 2026, the Seattle City Council approved a one-year moratorium affecting certain new large data centers with electricity demand above 20 MVA.
The moratorium can potentially be extended and reflects growing concerns about electricity demand, grid infrastructure, and the impact of large data center loads on the city's power system. The policy development highlights the increasing importance of power availability in determining where future data centers can be developed in Washington.
Data Center Power and Infrastructure in Washington
Access to low-carbon electricity has historically been a major advantage for data center development in Washington. Hydroelectric power from the Columbia River has supported major hyperscale growth in Quincy and the Wenatchee Valley, with key utilities including Grant County PUD, Chelan County PUD, and Douglas County PUD.
However, rapid growth in large-load projects is increasing pressure on power infrastructure. Grant County PUD's large-load queue has reached nearly 2,900 MW of requested peak demand, with data centers accounting for a significant share. New projects may require additional transmission, substations, generation agreements, infrastructure contributions, and longer interconnection timelines.
Washington is also exploring new power sources. Energy Northwest's proposed Cascade Advanced Energy Facility could provide future small modular reactor capacity, with AWS associated with an agreement for up to 320 MW in its initial phase and potential expansion to approximately 960 MW. Helion Energy has also proposed a fusion power project in Malaga linked to a minimum 50 MW power purchase commitment for Microsoft.
Water and cooling infrastructure are another growing consideration. Microsoft's Malaga development requires dedicated cooling water infrastructure, while AWS's Wallula Gap campus is designed primarily around air cooling. As AI workloads increase data center power density, electricity availability, cooling systems, and water infrastructure will become increasingly important factors in Washington's future data center development.
Conclusion
Washington remains an important market for data center projects, supported by hydropower, strong connectivity, available land, and an established technology ecosystem. With more than 50 tracked projects and approximately USD 12.9 billion in pipeline investment, the state's data center development outlook remains strong.
Major projects such as the AWS Wallula Gap Data Center Campus, West Richland Data Center Campus, and Microsoft's EAT06, EAT13, and EAT09 demonstrate the scale of investment expected across the state. However, securing reliable power, transmission capacity, and supporting infrastructure will increasingly determine how quickly these upcoming data centers in Washington State move from planning to construction.
Find Upcoming Data Center Projects in Washington, USA
Unlock United States Data Center Opportunities! Introducing Blackridge Research's Global Project Tracking (GPT) platform:
Instant access to the latest Data Center Facility Projects in the United States
Comprehensive insights from planning to completion
Essential details: scope, CapEx, timelines, and key contacts
User-friendly interface for quick opportunity identification
Want more data center construction insights, including planned projects, active companies, and key decision-makers? Get started with our project tracker demo today.
Why Blackridge’s Global Projects Tracker?
Blackridge’s Global Projects Tracker covers projects from 150 countries and is updated with real-time, accurate, and authentic project developments. By subscribing to our United States Data Center projects database, you can get access to key contact details of ongoing and upcoming projects, project timelines and overviews, and regular alerts on project developments, all served to you through an easy-to-use interface.