Talabira Thermal Power Project Highlights

Name

Neyveli Talabira Super Critical Thermal Power Project (NTTPP) 

Location

Talabira, Sambalpur, Odisha, India

Significance

  • So far, the largest planned thermal power plant under the Ministry of Coal 

  • Addressing Energy Demands

  • Economic Development

Capacity

2400 MW

Environmental Compliance

Implementation of state-of-the-art equipment for minimizing environmental impact

Foundation

The foundation stone of Phase I to be laid by PM Shri Narendra Modi in February 2024

 

The NLC Talabira Thermal Power Project is an upcoming thermal power plant being planned under the Ministry of Coal and Coal India Limited. It is deemed to be the largest of its kind that has been planned under the ministry so far. It boasts a projected total capacity of 3,200 MW. Phase I aims to initiate the operation of three 800 MW units by 2028-29, while Phase II will introduce an additional 800 MW unit.

 

The Talabira Thermal Power Project stands as a beacon of progress in India's power generation landscape, positioned to redefine the nation's energy narrative. The project's significance extends beyond its capacity – it represents a transformative force addressing the burgeoning energy demands of the region. With cutting-edge technology and a focus on environmental compliance, the Talabira Thermal Power Project emerges as a cornerstone in fostering a robust and responsible power infrastructure for the nation.

 

Talabira Thermal Power Project Background

The Talabira Thermal Power Project emerges as a distinguished player in the power generation landscape, garnering recognition for its strategic role in augmenting India's energy sector. Commencing with a visionary approach, the project's inception marked a significant milestone in the pursuit of a sustainable and reliable power supply. Its initiation was driven by the pressing need to address escalating energy demands in the region and contribute substantially to the national power grid.

 

As a response to the evolving power dynamics, the Talabira Thermal Power Project holds paramount significance. By adopting advanced technologies and adhering to environmental standards, the project not only aims to bridge the energy deficit but also sets a precedent for responsible and eco-friendly power generation. Its multifaceted approach encompasses not just meeting the immediate energy requirements but also positioning itself as a catalyst for long-term growth and development in the power generation domain.

 


Also Read: Bharat Heavy Electricals Secures $2 Billion EPC Contract for Talabira Thermal Power Project


 

Talabira Thermal Power Project Location

Location

Image Source

 

The project is situated near Kumbhari and Tareikela villages in the Jharsuguda district. The project site spans 1511 acres and is accessible via the Sambalpur–Jharsuguda highway, crossing the Bedhan River through state PWD roads.

Here’s an insight into multiple benefits of the location allotted to the project

  • The allocation of 1200 acres for the power plant, water reservoir, and integrated township ensures a well-organized and compact layout, promoting efficient space utilization.

  • An additional 500 acres near Thelkolai village were allocated for ash disposal.

  • The designated land areas facilitate streamlined operations, allowing for a cohesive integration of power generation, water resource management, and community infrastructure within a centralized location.

  • The allocated land provides room for potential future expansion, accommodating the growing needs of the Talabira Thermal Power Plant and its associated facilities.

  • The strategic location near Bedhan River facilitates the implementation of an innovative pipe conveyor for coal transportation.

  • Utilizing the nearby Hirakud reservoir ensures a consistent and reliable source of water for the Talabira Thermal Power Plant.

  • Two 4-lane roads from Sambalpur–Jharsuguda highway ensure smooth access.

 

Objectives of the Project

The Talabira Thermal Power Project unfolds with a set of clear objectives

  • Contribute significantly to power generation capacity

  • Enhance existing power infrastructure to meet regional and national energy demands

  • Positioned as a crucial player in the energy sector

  • Aims to address escalating energy needs at both regional and national levels

  • Emphasis on sustainable practices to ensure a reliable and uninterrupted power supply

  • Direct alignment with broader national objectives of energy security and accessibility

  • Dedication to meeting the energy needs of the region

  • Promotes practices that minimize ecological consequences

  • Charts a course for long-term resilience and sustainability in the power sector

 

Find Coal Power Plants in IndiaGet Started Now!

 

Talabira Thermal Power Project Scope

The Thalabira Power Plant Project aims for a total capacity of 3,200 MW. This creates ample scope around construction and connectivity development.

  • Phase I targets a set up of three 800 MW sets of power generation equipment eventually 

  • Scope for the deployment of another set of 800 MW power generation units for Phase II in the future

  • Development of auxiliary distribution and transmission facilities

  • Comprehensive planning includes the construction of supporting infrastructure like railways, roadways, etc.

Talabira Thermal Power Project Financial Details

Here’s an insight into the finances of the NTTPP

  • The Talabira Thermal Power Project by NLC India is slated to be the largest thermal power plant under the Ministry of Coal and Coal India Limited, with a planned total capacity of 3,200 MW. 

  • Bharat Heavy Electricals Ltd (BHEL) has been awarded the execution of phase-I, while phase-II tendering is pending. The project is estimated to cost Rs 27,213 crore.

  • The proposed Debt:Equity ratio of the project is 70:30. Where most of the debt will be financed by banks and other domestic financial institutions. The equity is proposed to be financed by internal stakeholders.

 

Talabira Thermal Power Project Technical Specifications

The NTTPP boasts an exhibition of a fair share of technological innovation

  • Talabira Thermal Power Plant boasts a substantial 3x800 MW power generation capacity, emphasizing its significance in meeting energy demands.

  • The facility is preparing to use supercritical technology. This shall benefit several aspects such as production, fuel/energy efficiency, transportation and operational cost, and many more.

  • It is preparing to implement an innovative pipe conveyor for coal transportation from Talabira mines located across the river.

 

Talabira Thermal Power Project Stakeholders Involved

NLC India Ltd (NLCIL) is the key initiator and developer of the Talabira Thermal Power Project, undertaking the establishment of the Neyveli Talabira Super Critical Thermal Power Station (NTTPP) in Odisha.

 

The project involves collaboration with the Odisha government's power trading arm GRIDCO, indicating active participation and support from state authorities.

 

The responsibility for executing phase I has been conferred upon Bharat Heavy Electricals Ltd (BHEL), underscoring the engagement of well-established entities in the power industry. BHEL's various production units situated in Varanasi, Bhopal, Haridwar, Hyderabad, Jhansi, Bengaluru, Ranipet, and Haridwar will manufacture the primary equipment for the project.

 

Future Prospects

Power Supply Impact

  • The Talabira Thermal Power Plant, with its planned 3 x 800 MW capacity, is poised to augment the power supply in the region significantly.

  • Power purchase agreements with Tamil Nadu, Odisha, Kerala, and Puducherry ensure a committed consumer base, addressing the escalating demand for electricity.

 

Contribution to National Energy Security

  • By aligning with the broader national objectives of energy security and accessibility, the Talabira Power Plant emerges as a crucial player in India's energy landscape.

  • Its strategic importance and diversified consumer base underscore its role in ensuring stable and secure energy sources for the nation.

 


Also Read: Global Coal Fired Power Generation Market Report


 

 

Thermal Power Plant

 

Summing Up

The Talabira Thermal Power Project epitomizes India's commitment to sustainable energy solutions and energy security. With its substantial capacity, environmental compliance, and strategic partnerships, the project stands poised to significantly impact the region's power supply while advancing long-term sustainability goals. It represents a pivotal step towards a responsible and resilient energy future for India.

 

Find the Latest Coal Power Plant Projects in India with Ease

Are you looking for a platform that gives you reliable, high-quality, and timely project insights for Coal Power Plant Projects across the globe?

 

Get information about Upcoming and Ongoing Coal Power Plant Projects with Blackridge Research & Consulting – Projects Database.

 

The Global Project Tracking (GPT) platform by Blackridge Research is designed to provide you with the most recent updates across various stages of development:

  • Upcoming projects

  • Tender Notices

  • Contract award announcements

  • Projects in progress or under construction

  • Successfully completed projects.

 

The user-friendly interface helps you obtain early-stage awareness of projects and find the right business opportunity quickly.

 

Each project will have all the essential details, such as scope, capacity, CapEx, status, project description, companies involved, funding information, location, periodic updates, important event dates like construction start date, commissioning dates, and key contact information of project owners and stakeholders.

 

The database is a vital resource for a wide range of entities, including developers, EPC Companies, project owners, construction material suppliers, Concession Companies, Operation and Maintenance (O&M) companies, BIM software providers, consulting and advisory firms, investors, multilateral banks and financial institutions, and law firms.

 

Book a Free demo to learn more about the Latest Coal Power Plant Projects database and how we can help you achieve your goals.

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile