Project at a Glance

Project Name

Morgan Offshore Wind Farm

Project Type

Greenfield 

Project Sector

Offshore Wind Energy

Project Status

Consent Received

Project Location

Irish Sea

Project Cost

Expected to be £3 billion (approximately USD 4 billion)

Total Windfarm Capacity

1,500 MW (1.5 GW)

Total Wind Turbine Generators

96 turbines

Developer

Morgan Offshore Wind Limited, a joint venture between JERA Nex bp and Energie Baden-Württemberg AG (EnBW).

Owner

  • JERA Nex bp

  • Energie Baden-Württemberg AG (EnBW).

Offshore Substation Plant

4

Onshore cables

12

Project Overview

The Morgan Offshore Wind Farm Project is an offshore project located in the Irish Sea. It is developed by a joint venture between the two leading energy companies, JERA Nex bp, and one of the largest renewable companies in Germany,  Energie Baden-Württemberg AG (EnBW).

It is classified as the Nationally Significant Infrastructure Project (NSIP), as the Development Consent Order (DCO) application has been submitted to the Secretary of State. The Morgan Offshore Wind Farm is positioned to contribute to the UK's offshore wind leasing program's Round 4, helping to reach the government's 50GW target by 2030.

The Morgan Offshore Wind Farm will comprise 96 turbines, constructed 20 miles (32 km) off the Fylde coast with a total generation capacity of 1,500 MW (1.5 GW). It can power up to 1.5 million homes annually.

Morgan Offshore Wind Farm Project Generation Assets

The Morgan Offshore Wind Farm Project comprises the development of the following offshore elements to generate electricity from the wind:

  • Wind turbine generators (up to 96 turbines)

  • Up to four offshore substation platforms

  • Offshore interconnector cables connecting the wind turbine generators

  • Offshore inter-array cables connecting the OSPs

  • Up to four offshore export cables, each approximately 125 km long. 

  • Up to 12 onshore cables, each approximately 30 km long. 

  • An onshore substation.

  • Up to twelve cables from the onshore substation to the Penwortham national grid connection point.

Morgan Offshore Wind Farm Location

Morgan Offshore wind Farm is located in the Irish Sea, approximately 37km off the north-west coast of England and 22km from the Isle of Man. The area it covers is used by shipping and fishing interests, and there are established ferry routes linking Liverpool, Heysham, Belfast, and Douglas.

The project's onshore component involves landing transmission cables near Blackpool and a connection to the National Grid at a substation in Penwortham, Lancashire.  

Morgan Offshore Wind Farm Map

Morgan Offshore Wind Farm Map


40+ reviews

Find the Latest Offshore Wind Projects in the United Kingdom 

Gain exclusive access to our industry-leading database of offshore wind opportunities with detailed project timelines and stakeholder information.

​Collect Your Free Leads Here!

No credit cardUp-to-date coverage

Joined by 750+ industry professionals last month

Project Background

The Morgan Offshore Wind Farm is a major UK renewable energy project located in the Irish Sea, developed by EnBW. It is positioned to contribute to the UK's offshore wind leasing program's Round 4, helping to reach the government's 50GW target by 2030.

In early January 2021, BP-EnBW won a lease area designated as "MO-A," which spans about 290 square kilometers, about 22-30 kilometers from the Cumbria coastline. This proved to be a milestone, marking a significant entry for BP into offshore wind development, leveraging EnBW's established expertise in European renewables. 

In January 2022, the developers received the electricity generation licenses from the UK government for both Morgan and the neighboring Mona site (designated MO-B). These licenses enabled the progression to detailed planning and environmental assessments.

As a Nationally Significant Infrastructure Project (NSIP), the project required a Development Consent Order (DCO) under the UK's Planning Act 2008. The DCO application for Morgan's generation assets was formally submitted to the Planning Inspectorate on 24 April 2024 and accepted for examination on 17 May 2024. 

On 29 August 2025, the Secretary of State for Energy Security and Net Zero, Ed Miliband, granted full development consent, clearing the path for construction.

Project Ownership Details

The project is being developed by Morgan Offshore Wind Limited, a joint venture between JERA Nex bp (a global energy major) and EnBW (Energie Baden-Württemberg AG, a German utility focused on renewables). Both hold a 50 - 50% share in the project. It is closely connected to the adjacent Mona Offshore Wind Farm, with shared transmission infrastructure, but Morgan stands as a distinct generation asset.

Morgan Offshore Wind Farm Project Timeline

Date

Event

2028-29 

Expected commercial operation date

2026-27

Expected construction start date

29 August, 2025

Development consent granted

March 2025

The Planning Inspectorate completes its examination of the DCO application.

17 May 2024

The application is formally accepted and enters the examination phase.

24 April 2024

Application for development consent submitted to the Planning Inspectorate.

January 2022

Electricity Generation License Issued. 

January 2021

The joint venture between JERA Nex bp and EnBW secures the seabed lease for the Morgan site in the Irish Sea. 

Project Scope

The project scope of the Morgan Offshore Wind Farm Project includes the following: 

  • Wind Turbines: The Morgan Offshore Wind Farm project comprises up to 96 three-bladed wind turbines, each located at a height of approximately 364 m above Lowest Astronomical Tide, with rotor diameters ranging from 250m to 320m.

  • Navigational safety: A minimum distance of 1,400 m has been established between turbines to address wake efficiency, fisheries access, and navigational safety.

  • Grid Integration: Export cables will run from the offshore substations to a Morgan offshore booster station, before making landfall in Lancashire.

  • Electrical Infrastructure: It comprises Inter-array cables of approximately 390 km and up to three interconnectors, with a total length of 60 km. These will be buried at a depth of 1-2 m, with extra protection applied where burial is unfeasible.

  • Helicopter access: There will be up to four offshore substation platforms, housing step-up transformers, switchgear, and secondary systems, which will be accessible by helicopter.

  • Coordinated Transmission Assets Project: Export to shore will be facilitated through the Coordinated Transmission Assets project, which also includes a Morgan offshore booster station and two new onshore substations in Lancashire.

40+ reviews

Find the Latest Offshore Wind Projects in United Kingdom

Gain exclusive access to our industry-leading database of offshore wind opportunities with detailed project timelines and stakeholder information.

​Collect Your Free Leads Here!

No credit cardUp-to-date coverage

Joined by 750+ industry professionals last month

Morgan Offshore Wind Farm Project Cost

Detailed costing has not been prepared yet, but Morgan OWF is likely to require over £3 billion (approximately USD 4 billion) of investment to deliver the project. It includes the cost of turbine procurement, foundation fabrication, offshore substations, transmission assets, and associated port infrastructure. 

Morgan Offshore Wind Farm Development Consent Order

The Morgan Offshore Wind project received development consent from the Department for Energy Security and Net Zero on 29 August 2025. It involves the development of an offshore wind farm, with an expected generation capacity of 1,500 MW in the Irish Sea.

Developed by JERA Nex bp and EnBW, Morgan Generation is the second project from the UK’s Round 4 leasing round to receive consent, and one of the fastest offshore wind farms in the UK to progress from lease award to approval.

The application was submitted to the Planning Inspectorate for consideration by Morgan Offshore Wind Limited on 24 April 2024 and accepted for examination on 17 May 2024. The formal order is titled "The Morgan Offshore Wind Project Generation Assets Order 2025" and came into force on 22 September 2025.

The consent was granted following a thorough examination process, which included public consultations and recommendations by the Planning Inspectorate, as required for Nationally Significant Infrastructure Projects (NSIPs) under the Planning Act 2008. 

Benefits of the Morgan Offshore Project

The following are the benefits of the Morgan Offshore Wind Farm Project:

 

  • Provides Renewable Electricity: The project, with a total capacity of 1,500 MW, can provide up to 600 GWh of renewable electricity annually. It is equivalent to powering up to 1.5 million homes annually. 

  • Reduces CO2 Emissions: The Morgan Offshore project is expected to reduce CO2 emissions by up to 3 million tonnes per year upon its operation. 

  • Reduce the UK’s Greenhouse Gas Emissions: The project aims to reduce the UK's Greenhouse Gas Emissions and achieve net zero by 2050. Furthermore, it supports the UK’s 50 GW Offshore wind target by 2030. 

  • Boost Employment: The Morgan Offshore project will create up to 3,420 jobs during its construction and operational phase. It creates nearly 710 jobs during its planning phase. The construction phase is expected to create 2,120 new job opportunities. Upon operation, the project is expected to create approximately 590 new jobs. 

  • Grid Infrastructure: Connects to the national grid at Penwortham, Lancashire, in collaboration with the adjacent Morecambe project, optimizing infrastructure and enhancing regional energy resilience.

Conclusion

The Morgan Offshore Wind Farm Project is an offshore wind farm located in the Irish Sea. Being developed by a joint venture between JERA Nex bp and Energie Baden-Württemberg AG (EnBW), the project connects to the National Grid at a substation in Penwortham, Lancashire.  

Recognised as a classified Nationally Significant Infrastructure Project (NSIP), the Morgan Offshore Wind Farm is positioned to contribute to the UK's offshore wind leasing program's Round 4, helping to reach the government's 50GW target by 2030.

The project proved to be of great importance to the UK’s renewable energy future, with the development consent granted in August 2025. In addition to grid connections, Morgan is collaborating with neighboring projects to minimize environmental impact and speed up deployment.

Track the Latest & Upcoming Offshore Wind Farm Projects In The United Kingdom (UK)

Subscribe to our upcoming and ongoing Offshore wind projects around the world with ease to access reliable, high-quality insights on forthcoming and completed Projects across the country.


Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.


Start a free demo to take your business to the next level.

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile