Wyoming is emerging as a major U.S. data center market, with artificial intelligence, cloud computing, and hyperscale infrastructure driving large-scale development and investment. Blackridge Research tracks upcoming data center projects in Wyoming, representing approximately 3.3 GW of planned capacity and USD 118.5 billion in projected construction expenditure.
Major developments include Google’s Project Tembo, Prometheus’s hyperscale data center projects, Vantage Data Centers’ Project Latigo, and Related Digital’s Cheyenne campus. These projects span AI infrastructure, hyperscale computing, and large-scale data center campuses, with development activity concentrated around Cheyenne, Casper, and Evanston.
This article examines Wyoming’s data center market, highlighting five major upcoming projects alongside their planned capacity, investment, developers, development status, and expected timelines.
Latest List of Top 5 Upcoming Data Center Projects in Wyoming, USA 2026
Data Center Project | Capacity (MW) | Developer | Current Stage |
Google “Project Tembo” (formerly Project Jade), south of Cheyenne | 2,700 MW total power resource, including reserves (Crusoe-era IT campus figure: 1,800 MW; designed to scale to 10,000 MW) | Google (via Jupiter Star Holdings LLC); Tallgrass (on-site power); Black Hills (utility). Crusoe exited in June 2026. | Permitting approved / Pre-construction |
Prometheus Falls Ranch, Casper area (Natrona County) | 1,500 MW | Prometheus Hyperscale; Spiritus and Casper Carbon Capture (power and carbon storage) | Planned (no formal application filed) |
Prometheus Hyperscale WY-1, Evanston (Uinta County) | 1,250 MW initial (potential 5,000 MW) | Prometheus Hyperscale | Permitting approved (conditional use permit, June 2026) |
Vantage “Project Latigo,” Laramie County | 480 MW critical IT (could scale to about 1,000 MW) | Vantage Data Centers | Permitting (zoning approved; no site plan yet) |
Related Digital Cheyenne (CoreWeave anchor tenant) | 302 MW campus critical IT; 88 MW in Phase 1 | Related Digital | Under Construction (Phase 1 due late 2026) |
Trusted by Leading EPCs & Manufacturers
Find the Latest Data Center Projects Across United States
Gain exclusive access to our industry-leading database of data center project opportunities with detailed project timelines and stakeholder information.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
Google Project Tembo Data Center
Google is developing Project Tembo, an approximately USD 17 billion AI data center campus in Laramie County, Wyoming. Located on a 716-acre site in Switchgrass Industrial Park, roughly eight miles south of Cheyenne, the project was previously known as Project Jade and was initially advanced by Crusoe.
Google subsequently assumed control of the development through its subsidiary, Jupiter Star Holdings LLC. The campus is planned to include four data halls, office facilities, logistics buildings, and network infrastructure, with approximately 3.08 million square feet of building space. The project is designed around an initial planned capacity of 2.7 GW, with potential future scalability to 10 GW.
Capacity and Power Infrastructure
The Google Project Tembo data center campus, one of the largest upcoming data center projects in the USA, is designed to provide approximately 2.7 GW of initial planned power capacity, with potential expansion to 10 GW. The proposed development covers 716 acres and includes four data halls with approximately 3.08 million square feet of building space. Its infrastructure is intended to support Google's large-scale AI computing and cloud infrastructure requirements.
The campus's power strategy combines utility electricity with dedicated on-site generation infrastructure. Black Hills Energy is expected to supply approximately 590 MW of power, including a 190 MW transmission service agreement and an additional 400 MW request submitted to state regulators.
Tallgrass Energy is developing a dedicated power hub with approximately 2.1 GW of planned generation capacity. The proposed infrastructure includes a microgrid and natural gas power generation facilities designed to provide a substantial portion of the campus's electricity independently of the regional utility grid.
Development Status and Timeline
2025-Early 2026: The project advanced under the name Project Jade, with Crusoe involved in the initial development alongside Tallgrass Energy.
June 2026: Crusoe announced that work at the Cheyenne site had been paused at the customer's request, while Tallgrass indicated that development of the dedicated power hub was continuing.
July 2026: Google was identified as the customer behind the development, which was renamed Project Tembo and transferred to Google's subsidiary, Jupiter Star Holdings LLC.
2026: Google advanced its revised four-data-hall development plan, while local authorities reviewed supporting facilities and power infrastructure approvals.
September 2026: Laramie County approved a conditional use permit for a two-story campus office building intended to support the data center development.
2026–2027: Site-enabling work, power infrastructure development, equipment procurement, and preparations for facility construction are expected to progress in phases.
Target completion: The campus is expected to reach full buildout around 2031, subject to construction progress, regulatory approvals, and power infrastructure delivery.
Key Contractors and Partners
Company / Entity | Role |
Primary Developer, Owner, and AI Infrastructure Customer | |
Jupiter Star Holdings LLC | Google's Subsidiary Responsible for the Project |
Related Digital | Physical Development and Construction Management Partner |
Tallgrass Energy | Dedicated Power Hub and Microgrid Development Partner |
Black Hills Energy | Utility Power Supplier and Grid Infrastructure Provider |
Bechtel | Engineering, Procurement, and Construction (EPC) Contractor for the Cheyenne Power Hub |
CSE Global | Power Distribution Center Design and Manufacturing Partner |
Laramie County | Local Planning, Permitting, and Development Authority |
Prometheus Hyperscale Data Center - Falls Ranch
Prometheus Hyperscale is proposing a 1.25 GW to 1.5 GW AI data center campus on a 940-acre site at Falls Ranch in Natrona County, approximately 10 miles east of Casper, Wyoming. The estimated USD 500 million investment project is planned to include around 640 acres of data center and computing infrastructure, with the remaining 300 acres allocated to on-site power generation facilities.
Capacity and Power Infrastructure
The Prometheus Hyperscale data center campus is designed to deliver approximately 1.25 GW to 1.5 GW of power capacity across a 940-acre site. The proposed development allocates approximately 640 acres to data halls and computing infrastructure, while 300 acres are reserved for power generation and associated electrical equipment.
The power strategy relies on an islanded microgrid that is designed to generate the campus's electricity independently of the public utility grid. Mesa Power Solutions is partnering with Prometheus to develop and integrate the on-site natural gas generation infrastructure. The proposed system includes natural gas reciprocating engines and turbines, with modular 3 MW power blocks incorporating Jenbacher engine technology to support phased capacity deployment.
Black Hills Energy is expected to supply natural gas through a dedicated pipeline serving the site. The project also includes proposed carbon management measures involving Casper Carbon Capture and Spiritus, including access to underground CO₂ sequestration infrastructure and direct-air capture technology.
Development Status and Timeline
Late 2025: The project emerged as a proposed data center development near the Natrona-Converse county line.
2026: Following community concerns about noise, heat, and traffic, developers revised the site layout to focus the proposed campus on a 940-acre parcel at Falls Ranch within Natrona County.
May 2026: The project received wider attention following reports detailing its proposed capacity, site requirements, and planned natural gas power infrastructure.
August 2026: Prometheus announced its partnership with Mesa Power Solutions to develop the campus's on-site power generation system.
September 2026: Residents raised concerns about the development during a Wyoming Outdoor Council forum, while local planning and zoning discussions continued.
Pending approvals: Developers are pursuing local land-use approvals, including a proposed Planned Unit Development designation. Applicable environmental and air permits will also be important to project implementation.
Construction target: Construction is expected to begin within six months of final approval, according to developer-reported plans.
Target operations: Prometheus has indicated a 2028 operational target, although the proposed 1.25 GW to 1.5 GW campus is expected to require phased development over a longer buildout period.
Key Contractors and Partners
Company / Entity | Role |
Prometheus Hyperscale | Primary Developer and Data Center Project Proponent |
Mesa Power Solutions | On-Site Power Generation Infrastructure Partner |
Jenbacher | Natural Gas Reciprocating Engine Technology Supplier |
Black Hills Energy | Natural Gas Pipeline Infrastructure Provider |
Casper Carbon Capture | Carbon Sequestration and CO₂ Storage Partner |
Spiritus | Direct-Air Capture and Carbon Management Partner |
Orchard Power | Spiritus-Associated Power Development Entity |
Russell Gordy / Falls Ranch | Landowner and Site Provider |
Natrona County | Local Planning, Zoning, and Permitting Authority |
Read Next
Prometheus Hyperscale WY-1 Data Center, Evanston
Prometheus Hyperscale is developing its WY-1 flagship AI data center campus approximately 12 miles east of Evanston in Uinta County, Wyoming, near the Utah border. The project occupies a proposed 506-acre to 640-acre development site within a larger family-owned ranch and is designed to support high-density AI computing workloads. The campus has an initial permitted capacity of approximately 1.25 GW, with long-term expansion plans potentially reaching 5 GW.
Capacity and Power Infrastructure
The Prometheus Hyperscale WY-1 campus is designed to provide approximately 1.25 GW of initial permitted capacity, with a long-term expansion pathway to 5 GW. The development is planned across approximately 506 to 640 acres and is intended to accommodate high-density computing infrastructure for advanced AI applications.
The campus's power strategy centers on an islanded microgrid using on-site natural gas generation supplied through dedicated gas infrastructure. PureWest Energy is identified as a natural gas partner, while Frontier Carbon Solutions is expected to support carbon capture, transportation, and underground sequestration.
The project has also announced a proposed 100 MW advanced nuclear power arrangement with Oklo to support future expansion phases. XL Batteries is associated with a 333 kW long-duration energy storage pilot.
Development Status and Timeline
June 2026: Uinta County commissioners unanimously approved the project's Conditional Use Permit and industrial rezoning.
2026: The project advanced its power, cooling, and connectivity plans, with local officials supporting efforts to attract major technology customers.
Late 2027: Initial capacity delivery of approximately 150 MW is targeted under the developer's phased buildout plan.
Late 2028: The campus is targeting expansion to approximately 450 MW.
Late 2029: The development aims to reach its baseline capacity of more than 1.2 GW.
Long-term expansion: Prometheus has outlined a potential pathway to scale the campus to 5 GW, subject to further development, infrastructure deployment, and customer demand.
Key Contractors and Partners
Company / Entity | Role |
Prometheus Hyperscale | Primary Developer and Data Center Operator |
PureWest Energy | Natural Gas Supply Partner |
Frontier Carbon Solutions | Carbon Capture, Transportation, and Sequestration Partner |
Oklo | Proposed Advanced Nuclear Power Supplier |
XL Batteries | Long-Duration Energy Storage Pilot Provider |
Dominion Energy | Identified Natural Gas Infrastructure Partner; specific WY-1 responsibilities require confirmation |
Lumen Technologies | Fiber-Optic Connectivity and Network Infrastructure Provider |
J.M. Gross Engineering | Engineering Partner for High-Density Liquid Cooling Infrastructure |
Corning | Fiber-Optic Technology and Connectivity Ecosystem Partner |
Uinta County | Local Planning, Zoning, and Permitting Authority |
Vantage Data Centers Project Latigo
Vantage Data Centers is developing Project Latigo, a planned 1,835-acre hyperscale and AI data center campus approximately 12 miles south of Cheyenne in Laramie County, Wyoming. Located along Terry Ranch Road between Interstate 25 and U.S. Highway 85, the project is designed to deliver approximately 480 MW of IT capacity and could attract up to USD 20 billion in total investment.
The initial phase is expected to involve approximately USD 4 billion in investment and include four data center buildings. The master plan also incorporates supporting utility infrastructure and modular workforce housing to accommodate construction personnel during the multiyear development process.
Capacity and Power Infrastructure
Project Latigo is planned as a 480 MW hyperscale data center campus across approximately 1,835 acres. The master plan is designed to support large-scale cloud computing and high-density AI workloads, including deployments requiring advanced cooling and high-power-density server racks. The initial development phase is expected to include four data center buildings and represent approximately USD 4 billion in investment, with further construction planned in stages.
The campus's power strategy includes a 400 MW power development agreement with Liberty Power Innovations (LPI) under a reported five-year arrangement. The planned supply is expected to begin in 2027 and support the initial development phases through dedicated natural gas generation facilities associated with the Bison Ranch Power Generation project. This behind-the-meter approach is intended to provide additional power-supply flexibility while the campus expands.
Development Status and Timeline
September 1, 2026: The Laramie County Board of Commissioners approved the rezoning of the 1,835-acre site to a Planned Unit Development (PUD).
Late 2026: Detailed site engineering, utility coordination, environmental assessments, and planning for workforce accommodation are expected to progress.
2027: Groundbreaking and major site preparation are targeted, alongside planned initial power delivery under the LPI agreement.
2030: The initial phase, comprising four data center buildings and approximately USD 4 billion in investment, is targeted for completion.
Long-term development: The campus is planned to expand in phases toward its total master-planned capacity of approximately 480 MW.
Key Contractors and Partners
Company / Entity | Role |
Vantage Data Centers | Primary Developer and Data Center Operator |
Liberty Power Innovations (LPI) | Power Development Partner and Planned 400 MW Supply Provider |
Bison Ranch Power Generation | Associated On-Site Natural Gas Power Generation Project |
T C Solutions | Local Utility Engineering and Sewer Infrastructure Partner |
Laramie County | Planning, Zoning, and Development Approval Authority |
Read Next
Vantage Project Latigo
Company / Entity | Role |
Vantage Data Centers | Primary Developer and Data Center Operator |
Liberty Power Innovations (LPI) | Power Development Partner and Planned 400 MW Supply Provider |
Bison Ranch Power Generation | Associated On-Site Natural Gas Power Generation Project |
T C Solutions | Local Utility Engineering and Sewer Infrastructure Partner |
Laramie County | Planning, Zoning, and Development Approval Authority |
Related Digital Data Center Campus, Cheyenne
Related Digital is developing a USD 1.2 billion AI data center campus on a 115-acre site in the Cheyenne Business Parkway in Cheyenne, Wyoming. The project is designed to deliver an initial 88 MW of critical IT capacity, with plans to expand to approximately 302 MW and potential long-term master planning provisions for up to 420 MW.
The first phase includes a 184,000-square-foot data center facility leased to CoreWeave under a long-term agreement to support its AI training and inference infrastructure.
Capacity and Power Infrastructure
The Related Digital Cheyenne campus is planned to deliver 88 MW of critical IT capacity in its first phase, within an overall development plan targeting approximately 302 MW. Longer-term master planning provisions could allow the campus to expand to as much as 420 MW, subject to future development plans and infrastructure requirements.
CoreWeave has leased the full initial 88 MW capacity under a long-term agreement, establishing the first phase as dedicated infrastructure for its AI cloud services. The campus's electrical infrastructure is supported by Black Hills Energy, which provides utility service and coordinates grid integration. The first utility transformer was energized in April 2026, enabling further electrical systems testing and commissioning.
Development Status and Timeline
October 2025: Related Digital officially broke ground on the USD 1.2 billion campus alongside Wyoming officials and local economic development representatives.
Early 2026: Clayco advanced structural construction, completed major concrete wall work, and brought the first data hall to a weather-tight condition. Cooling equipment and backup power infrastructure were delivered to the site.
April 2026: The first utility transformer was energized, marking a key milestone in electrical infrastructure deployment.
September 2026: Structural work for the first phase was reported complete, with critical power infrastructure energized and Phase 1 commissioning underway.
Late 2026 to early 2027: Initial operational handover and delivery of the first 88 MW of IT capacity to CoreWeave are targeted.
Subsequent phases: Further development is planned across the remaining campus acreage, with expansion toward approximately 302 MW and potential long-term capacity of up to 420 MW.
Key Contractors and Partners
Company / Entity | Role |
Related Digital | Primary Developer and Investment Platform |
Related Companies | Real Estate Development Platform and Parent Organization |
energyRe | Energy and Transmission Development Partner |
CoreWeave | Anchor Tenant and AI Cloud Infrastructure Operator |
Clayco | Construction Manager and General Contractor |
Black Hills Energy | Electric Utility and Grid Integration Provider |
Cheyenne LEADS | Regional Economic Development Partner |
Overview of the Data Center Market in Wyoming
Wyoming is emerging as a major U.S. data center development market, with artificial intelligence, cloud computing, and hyperscale infrastructure driving large-scale investment. Blackridge Research tracks 15 upcoming data center projects in Wyoming, representing approximately 3.3 GW of planned capacity and USD 118.5 billion in projected construction expenditure. The average investment is around USD 7.9 billion per project, reflecting the scale of the state's proposed data center campuses and supporting power infrastructure.
Major developments include Google’s Project Tembo, the Prometheus hyperscale data center projects, Vantage Data Centers’ Project Latigo, and the Related Digital campus in Cheyenne. These projects span AI-focused computing, hyperscale facilities, and large campuses supported by dedicated power infrastructure. Development activity includes both projects in the planning stage and those already under construction.
Conclusion
Wyoming's data center market is expanding through large-scale hyperscale and AI infrastructure developments. Blackridge Research tracks 15 upcoming projects with a combined capacity of 3.3 GW and projected construction expenditure of USD 118.5 billion. Six projects are already under construction, while nine remain in the planning stage, indicating both active development and a substantial future pipeline.
Find Upcoming Data Center Projects in Wyoming, USA
Unlock United States Data Center Opportunities! Introducing Blackridge Research's Global Project Tracking (GPT) platform:
Instant access to the latest Data Center Facility Projects in the United States
Comprehensive insights from planning to completion
Essential details: scope, CapEx, timelines, and key contacts
User-friendly interface for quick opportunity identification
Want more data center construction insights, including planned projects, active companies, and key decision-makers? Get started with our project tracker demo today.
Why Blackridge’s Global Projects Tracker?
Blackridge’s Global Projects Tracker covers projects from 150 countries and is updated with real-time, accurate, and authentic project developments. By subscribing to our United States Data Center projects database, you can get access to key contact details of ongoing and upcoming projects, project timelines and overviews, and regular alerts on project developments, all served to you through an easy-to-use interface.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.