XTX Markets Opens 22.5 MW Data Center in Finland

project_news

XTX Markets Opens 22.5 MW Data Center in Finland

Updated on Nov 26, 2026, 03:16 AM IST
Written & Edited by Harikesh VA

XTX Markets has announced the opening of its first data centre on its new Kajaani campus in Finland, marking what the firm described as an important milestone in its investment in the country, spanning infrastructure, local contracts, education partnerships, and philanthropy.

 

The announcement was made in London and Kajaani, alongside news of new philanthropic commitments totalling more than USD 1.76 million supporting local community projects, education, and workforce development.

 

Data Center Opens With 22.5 MW Capacity

The newly opened facility is set within a 193-hectare site and provides 22.5 MW of IT power capacity with 15,000 square metres of floor space. Construction of the large-scale data centre project began in 2024. A second data centre on the campus is scheduled to become operational in 2027.

The firm has already hired more than 30 full-time employees in Kajaani, including engineers and staff working in operations, security, and maintenance. The site can accommodate 50 permanent employees, and recruitment will continue as operations expand.

 

A New Home for XTX's Compute

XTX Markets uses deep learning to analyse vast amounts of data and forecast prices for financial instruments worldwide. These models require significant computational resources, and with the new facility, compute is for the first time housed in the firm's own data centre infrastructure.

The company is developing a major data centre campus in Kajaani, with ambitions to expand significantly over the coming years. Electricity supply and grid connections have been secured for the first two facilities.

 

However, government expropriation permitting delays mean power availability remains uncertain for the third facility, which is already under construction and due for completion in mid-2028. Further facilities are planned for delivery annually thereafter.

Trusted by Leading EPCs & Manufacturers

Find the Latest Data Center Projects in Finland

Gain exclusive access to our industry-leading database of data center opportunities with detailed project timelines and stakeholder information

Request Free Trial → Learn More →

No credit card Up-to-date coverage

 

Warning Over Bureaucracy and Investment Risk

Mike Irwin, Chief Operating Officer of XTX Markets, struck a cautionary note alongside the opening announcement, warning that the firm's ambitions are being put at risk by government bureaucracy and what he characterised as a worrying lack of engagement.

"We set an ambitious timetable for our first data centre and delivered. Our second facility is scheduled for completion in 2027, with more planned. We've already invested over USD 439.04 million in construction, overwhelmingly with Finnish companies, and have ambitions to invest billions more," Irwin said.

He said that despite repeated attempts to seek guidance and support on the expropriation process for grid development, securing clear answers or even meaningful dialogue had proved extraordinarily difficult. According to Irwin, expropriation permits that once took months can now take years.

"Businesses cannot reasonably be expected to commit billions of dollars while leaving critical infrastructure decisions in administrative limbo. This is not about demanding electricity capacity that doesn't exist. It's about the government's ability to process applications, make decisions, and engage with investors who are already delivering substantial economic benefits," he said.

Irwin emphasised the long-term nature of the firm's commitment to Finland, stating that it will be measured in decades rather than years and that XTX remains willing to work with government and industry, including contributing financially to infrastructure solutions that benefit Finland more broadly.

 

But he warned that long-term commitments require long-term certainty and that without meaningful government engagement, future investment decisions will inevitably be called into question.

Environmental Protections During Construction

XTX Markets said it has used environmental and ecological assessments to guide the design and construction of the Kajaani campus, with a focus on protecting the local environment and minimising disruption to the local habitat.

Site assessments identified areas of particular ecological value, which informed the layout of the campus to help preserve them. The assessments covered biodiversity, woodland types, protected species and water bodies, groundwater, and soil contamination. They also examined archaeological and cultural heritage, alongside potential light and noise impacts.

Environmental protection measures continued throughout construction. When sand martin nests were discovered during work on the project's power line, work was paused until the nesting period had ended.

 

During the design of underground cable routes, surveys using a trained detection dog helped identify potential flying squirrel habitats. Trees were marked for retention, and the cable routes were adjusted to avoid the identified areas.

The data centre also operates without consuming water for cooling, placing no cooling-related demand on the local water supply.

Jukka-Pekka Partanen, Head of XTX Markets Finland, said responsible development means putting environmental considerations at the heart of the firm's decisions, from initial design to the way construction is carried out, including changing plans where necessary to protect wildlife and habitats.

"We recognise the ecological value of this site and the responsibility that comes with developing it. As the campus grows, we're planning further measures to support the local natural environment, alongside our long-term commitment to the Kajaani community," Partanen said.

USD 1.76 Million in New Philanthropic Commitments

To mark the opening, XTX announced new philanthropic commitments totalling more than USD 1.76 million to invest in community facilities, develop local workforce skills, and strengthen maths and science education across Finland.

The commitments include USD 329,279.54 for participatory budgeting to support community projects selected by Kajaani residents through the city's existing participatory budgeting programme, covering the next two rounds in 2027–2028 and 2029–2030.

 

A further USD 197,567.72 will help complete renovations and improve accessibility to Rehjansaari Island in Kajaani, a public site for leisure and recreation activities.

The Päivölä Maths School, one of Finland's specialist maths schools, will receive USD 329,279.54 over two years to support olympiad training delivered there. Additional commitments include support directed toward the Association of Teachers of Mathematics, Physics, Chemistry, and Informatics as part of the broader effort to strengthen math and science education across Finland.

 

The philanthropic programme also encompasses investment in community facilities and the development of local workforce skills.

Powering Finland's Digital Backbone: Never Miss a Data Center Opportunity

How many hyperscale projects broke ground in Finland last quarter without ever appearing on your radar? In a market of absorbing billions in data center capital expenditure, the difference between winning and watching often comes down to timing.

 

The Global Project Tracking (GPT) platform by Blackridge Research gives data center developers, contractors, and suppliers real-time visibility into Finland's fast-moving colocation and edge facility pipeline, from early-stage land acquisition to ribbon-cutting day.

 

  • Upcoming Projects

  • Tender Notices

  • Contract Awards

  • Projects Under Construction

  • Completed Projects

 

Stop relying on fragmented news and industry chatter. Book a Free Demo today and see how the Global Project Tracking (GPT) platform can keep your team ahead of every major data center build across Finland.

Tags

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile