Colocation provider Digital Realty has purchased a largely vacant office complex in Rolling Meadows, Illinois, with plans to demolish the building and construct a 156 MW data center campus approximately 25 miles northwest of Chicago.
Atrium Corporate Center acquisition and development plans
Digital Realty acquired 3800 Golf Road, also known as the Atrium Corporate Center, in Rolling Meadows in September for USD 81.5 million. The 40-acre site in Cook County currently contains a 485,000 square foot (45,058 sqm) three-story office building that was built in 1998.
According to recent city documents, Digital Realty intends to demolish the existing structure and develop two two-story data center buildings totaling approximately 975,000 square feet (90,580 sqm) with 156 MW of IT capacity.
The plans also include a 240 MW ComEd substation on a separate 4.6-acre lot. The proposed data centers would use a closed-loop cooling system designed to reduce water use.
The Rolling Meadows city council was scheduled to meet to discuss the project the week of the report. Digital Realty filed its development application through an entity named Digital Golf Road, LLC.
History of the Rolling Meadows site
The property has changed hands several times over the past decade and a half.
Private real estate investment firm Brennan Investment Group acquired the site in 2023 with plans to demolish the existing building and construct a new 600,000-square-foot (55,741 sqm) industrial park, known as Rolling Meadows Commerce Center or RMC². Those plans did not come to fruition.
Spear Street Capital had previously acquired the site in 2010 for around USD 27 million. Partners Group was also previously a co-owner when the companies foreclosed on the property. Past tenants of the building included AT&T, 3Com, Capital One, and the FAA, though the site has been largely vacant since 2020.
Trusted by Leading EPCs & Manufacturers
Find the Latest Data Center Projects in the United States
Gain exclusive access to our industry-leading database of data center opportunities with detailed project timelines and stakeholder information
Request Free Trial → Learn More →
No credit card Up-to-date coverage
Digital Realty's existing Chicago-area footprint
Digital Realty currently operates several data centers in the Elk Grove Village business park in addition to a campus in Franklin Park.
Its nine facilities in the region total 2.9 million square feet (271,500 sqm) and 175 MW of capacity, meaning the proposed Rolling Meadows campus would nearly double the company's IT capacity in the Chicago area if completed as planned.
Purchase of Hawthorne Race Course in Stickney
The Atrium Corporate Center is not the only Cook County property Digital Realty has acquired recently. The company also purchased the Hawthorne Race Course at 3501 S Laramie Avenue in Stickney, Cook County. The winning bid to acquire the site was made through Allimac 2023 LLC.
The 119-acre horse track, whose roots date back to 1891, closed in July 2026 following financial issues and ultimately bankruptcy. No announcements about any planned data center development at the site have been shared.
Local opposition and planning moratorium
Any future data center proposal at the Hawthorne site may face significant obstacles.
Stickney Township unanimously approved a six-month moratorium on data centers in August, running until February 2027. In addition, the nearby Town of Cicero preemptively passed a resolution over the summer opposing the construction of data centers at the Hawthorne race track.
The situation in Rolling Meadows, by contrast, has progressed to the formal application stage, with the project awaiting discussion by the city council as Digital Realty seeks approval for its 156 MW campus and associated substation.
Stay Ahead of the Next Hyperscale Build in the United States Market
Where will the next gigawatt-scale data center campus break ground, and will your team be positioned to win a slice of the work? From hyperscale campuses to edge facilities, the data center construction pipeline across the United States is moving faster than most suppliers can track on their own.
The Global Project Tracking (GPT) platform by Blackridge Research gives you a live window into this pipeline, so you can identify opportunities long before ground is broken and engage decision-makers at the right moment.
Whether you supply cooling systems, power infrastructure, modular construction, or specialized engineering services, tracking the right projects at the right stage is what separates market leaders from reactive bidders.
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
Ready to see how the Global Project Tracking (GPT) platform by Blackridge Research can sharpen your pipeline in the US market? Book a Free Demo with our team today and get a guided walkthrough tailored to the data center sector.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.