Ocean Winds has announced the installation of the final wind turbine at the 500 MW Dieppe-Le Tréport offshore wind farm, known as EMDT, off the Normandy coast of France. The company, an international offshore wind energy business jointly owned by EDP Renewables and ENGIE, said all 62 turbines are now in place, bringing the project closer to full operation.
The announcement, issued on 27 November 2026, confirms the end of a turbine campaign that Ocean Winds described as lasting around six months and beginning in June 2026.
A Six-Month Installation Campaign
The wind farm comprises 62 wind turbines installed on jacket foundations. According to Ocean Winds, the completion of the installation campaign reflects the safe and coordinated delivery of a complex offshore construction programme. Once the wind farm is operating at full power, it will generate renewable electricity equivalent to the annual consumption of approximately 850,000 people.
The project has already been producing power. EMDT has been progressively generating renewable electricity since first power in July 2026, with turbines connected and electrified as the installation advanced. With every turbine now installed, commissioning continues, and Ocean Winds said the project is expected to reach full power over the coming weeks.
Company Perspective on France
Marc Hirt, Country Manager for France at Ocean Winds, described the milestone as important both for the project and for the company's presence in France. He said it demonstrates the company's ability to deliver complex offshore wind projects and brings the wind farm another step closer to full operation.
Hirt said Ocean Winds, as a long-term owner-operator, is committed to continuing to grow its activities in France. He said this would contribute to the country's energy transition and independence, sovereignty and job creation.
Trusted by Leading EPCs & Manufacturers
Find the Latest Offshore Wind Farm Projects in France
Gain exclusive access to our industry-leading database of offshore wind opportunities with detailed project timelines and stakeholder information.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
More Than a Decade of Development
Frédéric Flaus, Project Director at Éoliennes en Mer Dieppe-Le Tréport, said the installation of the final turbine marks the end of more than ten years of development, consultation and collective effort. He noted that it also follows several years of offshore works, which he said were made possible by the commitment and professionalism of all the project teams and partners.
Flaus said that with its 62 wind turbines and 500 MW of installed capacity, the wind farm will support France's energy transition and energy independence over the long term, as well as the economic vitality of the region. He described himself as very proud of the collective achievement and of the legacy the project will leave for Normandy and its residents.
Dialogue With the Territory and Fishing
Flaus also addressed the project's relationship with local stakeholders. He said the project has been built through dialogue with the territory, and that this dialogue will continue to support long-term coexistence with other maritime activities, notably fishing.
Economic Footprint in Normandy
Ocean Winds said Dieppe-Le Tréport represents a long-term industrial and economic presence in Normandy. According to the company, the project's construction mobilized 3,500 full-time equivalent jobs and generated more than USD 197.35 million in activity for small and medium-sized enterprises.
The project's operations and maintenance base in Dieppe was built entirely by local companies, the company said. Over the wind farm's 25-year operational period, that base will support 70 full-time jobs.
Ownership and Operating Model
Ocean Winds is jointly owned by EDP Renewables and ENGIE and describes itself as an international offshore wind energy company. In the announcement, Hirt positioned the company as a long-term owner-operator, a role that will continue at Dieppe-Le Tréport as the wind farm moves from construction and commissioning into its operational phase.
Next Steps
With all 62 turbines installed on their jacket foundations, the remaining work centres on commissioning. Ocean Winds said that process is continuing and that the wind farm is expected to reach full power over the coming weeks. Until then, the turbines that have been connected and electrified continue to supply renewable electricity, as they have done progressively since July 2026.
Charting Every Megawatt: France Power Pipeline, From Planning Table to Grid Connection
Where will the next wave of power investment land in France, and who will be awarded the contracts to build it? With offshore wind clusters, interconnectors, grid reinforcement, and dispatchable capacity all advancing at once, the picture changes weekly, and teams relying on fragmented sources risk missing the opportunities that matter most.
The Global Project Tracking (GPT) platform by Blackridge Research brings that complexity into focus. It gives power-sector professionals a single, continuously updated view of project activity across France, covering generation, transmission, storage, and the supporting infrastructure that connects them. Instead of piecing together announcements and tender portals by hand, you can follow each project through its entire lifecycle and act while the window is still open.
Whether you are a developer scouting partners, an equipment supplier timing your outreach, a contractor planning your bid pipeline, or an investor assessing market momentum, the platform helps you spot demand earlier and prioritize with confidence. Coverage spans the full project lifecycle, including:
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
See how the Global Project Tracking (GPT) platform by Blackridge Research can sharpen your France power strategy. Book a free demo today.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.