Aukera Energy has reached financial close on its Loch Fergus project in South Ayrshire, Scotland, securing financing from Societe Generale for the construction and operation of a co-located 63 MWp solar photovoltaic plant and a 40.5 MW battery energy storage system. The company announced the milestone on 27 November 2026. The project is expected to begin commercial operation in early 2028.
A Co-Located Project Near Ayr
Located approximately 4 km south-east of Ayr, Loch Fergus combines solar generation and battery storage on a single site. The two assets share combined grid connection infrastructure. The financing from Societe Generale covers both the construction and the operation of the hybrid facility.
Long-Term Contracts Underpin Revenues
The solar PV plant secured a 20-year Contract for Difference in the UK's Allocation Round 7a in February 2026, which provides long-term revenue certainty for its renewable electricity generation. The battery energy storage system, for its part, secured a 15-year Capacity Market agreement in the 2029/30 T-4 auction.
Trusted by Leading EPCs & Manufacturers
Find the Latest Renewable Energy Projects in the United Kingdom
Gain exclusive access to our industry-leading database of renewable energy opportunities with detailed project timelines and stakeholder information
Request Free Trial → Learn More →
No credit card Up-to-date coverage
EDF Agreements Cover Solar Output and Battery Optimisation
To manage the project's generation and its exposure to the electricity market, Aukera has entered into a long-term route-to-market agreement with EDF for the solar output, commencing from commercial operation. According to Aukera, EDF is Britain's largest offtaker of renewable power and will provide the route-to-market expertise and the associated balancing services the project needs.
A separate 12-year optimisation agreement with EDF will enable the battery to participate in wholesale electricity markets, the Balancing Mechanism and ancillary services, supporting grid stability and flexibility.
Aukera describes EDF as Britain's largest battery optimiser. EDF will use its PowerShift platform and 24/7 trading expertise to optimise the asset across multiple markets, helping maximise its commercial value while providing flexibility to the wider electricity system.
A Diversified Revenue Framework
Taken together, the agreements establish what Aukera characterises as a diversified revenue framework for the project. The framework combines contracted income with opportunities to capture value from the growing demand for flexibility across the UK's electricity system.
Aukera Comment
Aiden Yates, Aukera's Managing Director and Head of Structured Finance, said that reaching financial close on Loch Fergus marks an important milestone for the company, reinforcing its continued investment in the UK market and demonstrating its ability to deliver hybrid energy projects that integrate renewable generation, battery storage and long-term storage. The remainder of the statement was not available in the source material provided.
Project Details at a Glance
The project's solar component is rated at 63 MWp, while the battery storage system has a capacity of 40.5 MW. Financing was provided by Societe Generale. The solar plant holds a 20-year Contract for Difference from Allocation Round 7a, awarded in February 2026, and the battery holds a 15-year Capacity Market agreement from the 2029/30 T-4 auction.
EDF is the counterparty to both the solar route-to-market arrangement and the 12-year battery optimization agreement. Commercial operation is expected in early 2028.
Keeping the Lights On: How the United Kingdom's Power Developers Stay Ahead of the Grid Transition
The United Kingdom's power sector is being reshaped at a pace that few markets can match; offshore wind auctions, grid-scale storage buildouts, hydrogen pilot schemes, and nuclear life-extension programs are all moving through the pipeline at once. For developers, EPC contractors, and equipment suppliers, the challenge is not a shortage of opportunity but a shortage of visibility into where that opportunity sits, who owns it, and when it will reach procurement.
Fragmented announcements, shifting commissioning dates, and permitting delays across individual European markets make it easy to miss the window between a project being conceived and a tender being issued. The companies that win work consistently are the ones tracking that window systematically rather than reacting to headlines.
The Global Project Tracking (GPT) platform by Blackridge Research brings the United Kingdom's power project pipeline into a single, continuously updated view, from early-stage feasibility through to final handover, so your business development and bid teams work from the same intelligence.
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
See how the Global Project Tracking (GPT) platform by Blackridge Research can sharpen your pipeline strategy across United Kingdoms power sector. Book a Free Demo to explore the data firsthand.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.