The Nordex Group has received an order for 19 N163/6. X turbines from Romanian energy company Electrica, the German turbine manufacturer, announced on 24 November 2026.
The turbines, drawn from Nordex's Delta4000 series, will equip the 133 MW Crucea Est wind farm in Romania. The order covers both the supply and installation of the turbines, alongside a premium service agreement covering 20 years.
Project Location and Technical Specifications
According to the company, the Crucea Est wind farm will be built in the communes of Crucea and Pantelimon, within Constanța County in the Dobrogea region, near Romania's Black Sea coast.
Turbine hub heights at the site will range from 98 to 125 meters. Installation is scheduled to begin in summer 2027, with substantial completion expected in 2028. The order was announced by Nordex SE as an incoming order.
Executive Commentary
Slava Feklin, Country Manager, Romania and Ukraine, of the Nordex Group, commented on the agreement. "We are very pleased that Electrica has placed its trust in Nordex technology for this important project," Feklin said.
"With 133 MW of capacity, Crucea Est is another significant project for the expansion of wind energy in Romania, further strengthening Nordex's position as one of the leading wind turbine suppliers in the country. The N163/6.X is ideally suited to delivering competitive renewable electricity at sites with strong wind resources, and we look forward to supporting Electrica in the realization of the wind energy project."
Alexandru Chirita, CEO of Electrica S.A., also addressed the signing. "Signing with Nordex Group for the supply and installation of the turbines and their maintenance over 20 years is a step forward in building Electrica's first wind farm, Crucea Est," Chirita said. "It's completion will support the development of the Group's electricity generation segment and Romania's energy transition objectives."
Trusted by Leading EPCs & Manufacturers
Find the Latest Onshore Wind Farm Projects in Romania
Gain exclusive access to our industry-leading database of onshore wind opportunities with detailed project timelines and stakeholder information.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
Electrica's First Wind Farm
The project represents Electrica's first wind farm, according to the CEO's statement. Electrica Group is described in the announcement as a key player in Romania's electricity market and the only Romanian energy group integrated across electricity distribution, supply, generation, and services.
The group serves over 4 million users through distribution networks covering approximately 40% of the country and provides electricity supply, maintenance, and energy services nationwide.
Electrica S.A., the group's holding company, has been listed on the Bucharest and London Stock Exchanges since July 2014 and has a majority private shareholding.
Regional Context
The company notes that Romania is experiencing renewed momentum in the development of onshore wind energy, with the Dobrogea region and Constanța County in particular representing one of the country's key areas for wind power development.
About the Nordex Group
Nordex states that the Group has commissioned more than 67 GW of wind power capacity in over 40 markets since 1985 and generated consolidated sales of around USD 8.31 billion in 2025.
The company currently has more than 11,100 employees, with a manufacturing network that includes factories in Germany, Spain, Brazil, India and USA. Its product portfolio is focused on onshore turbines in the 4 to 7 MW+ classes, which the company says are designed to meet the market requirements of countries with limited available space and regions with constrained grid capacity.
A global service network supports the operation of the turbines. Nordex SE is listed on the MDAX and TecDAX of the Frankfurt Stock Exchange under ISIN DE000A0D6554.
Wiring Romania's Power Future: Track Every Substation, Turbine, and Grid Upgrade in One Place
Romania's power sector is moving faster than most teams can follow. Between retiring thermal plants, surging renewable capacity, cross-border interconnection schemes, and grid modernization programs, the pipeline of opportunities is vast but fragmented across dozens of markets and hundreds of developers. Keeping tabs on it manually is no longer realistic.
The Global Project Tracking (GPT) platform by Blackridge Research brings Romania's entire power project landscape into a single, structured view. From early-stage feasibility studies to energized assets, it gives developers, EPC contractors, equipment suppliers, and investors the intelligence they need to act early rather than react late.
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
See how the Global Project Tracking (GPT) platform by Blackridge Research can sharpen your pipeline across Romania's power markets. Book a free demo today.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.