Hai Long Completes Construction, Connects All 73 Turbines to Taiwan Grid and Held Partner Appreciation Ceremony

project_news

Hai Long Completes Construction, Connects All 73 Turbines to Taiwan Grid and Held Partner Appreciation Ceremony

Updated on Nov 17, 2026, 04:17 PM IST
Written & Edited by Ashish

Taiwan's offshore wind sector has reached a major milestone with the completion of the Hai Long Offshore Wind Project, which held its Construction Completion and Partner Appreciation Ceremony on 17 November.

 

A Decade of Development Culminates in Completion Ceremony

Jointly developed by Japan's Mitsui & Co., Ltd., Canada's Northland Power, and Malaysia's Gentari, the project has completed construction and successfully connected all 73 wind turbines to Taiwan Power Company's (TPC) grid. Nearly 200 partners from government, financial institutions, and the supply chain attended the ceremony, witnessing the addition of more than 1 GW of capacity to Taiwan's green power supply.

Following a decade of development, planning, and construction, Hai Long overcame challenges including the COVID-19 pandemic, complex marine conditions in the Taiwan Strait, and the execution of large-scale engineering works.

 

The project integrated three wind farms into a single development exceeding 1 GW and became the first project in the Asia-Pacific region to sign a contract for 14 MW offshore wind turbines.

Tim Kittelhake, CEO and Project Director of Hai Long Offshore Wind Project, said the achievements reflect the sustained commitment of the international team and Taiwanese industry partners.

 

"The continuity of Taiwan's energy transition policies has provided the stable foundation needed for international investment and infrastructure development on this scale, enabling Hai Long to move from blueprint to reality," he said.

 

Record-Breaking Financing Backed by International Shareholders

Bringing together shareholders from Japan, Canada, and Malaysia, Hai Long reflects international investors' confidence in Taiwan's renewable energy market and its long-term development potential.

 

In 2023, the project secured USD 3.55 billion in project financing, setting a new record for offshore wind financing in the Asia-Pacific region. In 2026, leveraging Taiwan's National Credit Guarantee Mechanism, Hai Long secured an additional USD 1.67 billion in financing.

In total, the project has attracted participation from 35 domestic and international financial institutions, with policy support from export credit agencies across multiple countries, providing a financial foundation for the large-scale renewable energy development.

On the market side, Hai Long 2A, originally awarded under Taiwan's Round 2 selection process and subject to the government's feed-in tariff scheme through a Taiwan Power Purchase Agreement (TPPA), has signed a Corporate Power Purchase Agreement (CPPA) and is expected to formally transition to corporate power purchasing in the near future, setting a precedent for Taiwan's offshore wind industry.

 

According to the project, this transition provides a model for market-based renewable energy transactions and connects large-scale renewable energy development with growing corporate demand for green electricity.

Trusted by Leading EPCs & Manufacturers

Find the Latest Offshore Wind Farm Projects in Taiwan

Gain exclusive access to our industry-leading database of offshore wind opportunities with detailed project timelines and stakeholder information.

Request Free Trial → Learn More →

No credit card Up-to-date coverage

 

Taiwan's Highest Level of Offshore Wind Localization

Hai Long has achieved Taiwan's highest level of localization in offshore wind, helping the domestic industry move beyond capacity expansion toward technological advancement. In addition to its original localization commitment of 21 nacelles, the project procured another 52 locally assembled nacelles, supporting Siemens Gamesa's expansion of its Taichung nacelle assembly facility and enabling nine newly qualified Taiwanese suppliers to join its approved supplier network.

The project has also connected key segments of the offshore wind value chain through Taiwanese suppliers. CSBC-DEME Wind Engineering (CDWE) deployed Green Jade, Taiwan's first large floating crane vessel designed and built domestically, for offshore transportation and installation works.

 

Century Wind Power and CSBC Corporation, Taiwan, contributed to the manufacturing of offshore jacket foundations and pin piles, respectively. TECO Electric & Machinery undertook the onshore substation works, and Dong Fang Offshore provided marine engineering and vessel support services.

Through this participation in an internationally significant project, Taiwan's supply chain has gained practical experience, laying the groundwork for Taiwanese suppliers to expand into international markets.

Looking Towards Full Operations in 2027

With construction completed, Hai Long will continue to advance the administrative and permitting procedures required for full commercial operations, while strengthening local operations and maintenance capabilities to prepare for decades of safe and reliable operations.

The project also emphasizes its partnerships with local communities, aiming to turn a decade of collaboration into lasting shared value. As part of these efforts, Hai Long has partnered with the Changhua Fishermen's Association to provide career transition training for fishers, fully covering training, accommodation, and transportation costs.

 

Working alongside IOG Wind, a subsidiary of International Ocean Group responsible for operations and maintenance services, the programme is designed around actual industry workforce needs.

Powering Ahead: Track Power Projects Across the Taiwan Before Competitors Do

Taiwan power sector is expanding at an unprecedented pace, with billions being committed to power generation, transmission networks, water infrastructure, and renewable integration. But here's the challenge: project intelligence in this region is fragmented across dozens of sources, languages, and regulatory regimes.

 

How do you identify which grid expansion projects are moving to tender, which wind farm plants have just been commissioned, and which government projects are preparing to award contracts, without spending weeks chasing scattered data?

 

The Global Project Tracking (GPT) platform by Blackridge Research consolidates power sector intelligence across Taiwan into a single, continuously updated dashboard, giving your team the early visibility needed to position ahead of the market.

 

  • Upcoming Projects

  • Tender Notices

  • Contract Awards

  • Projects Under Construction

  • Completed Projects

 

Book a Free Demo today and discover how leading power companies, EPC contractors, and equipment suppliers are using the Global Project Tracking (GPT) platform by Blackridge Research to win more business in Taiwan.

Tags

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile