South African renewable energy developer and independent power producer Mulilo has announced the successful commercial and financial close of the Leeuwpoort Battery Energy Storage System (BESS) project, describing the milestone as a significant step in the delivery of the country's next generation of grid-supporting energy infrastructure.
Project Details
The Leeuwpoort project is a 77 MW / 308 MWh utility-scale battery energy storage facility located near Carletonville in the Merafong City Local Municipality, Gauteng.
The facility will connect to the Midas Main Transmission Substation, which Mulilo says will strengthen the resilience and flexibility of the national grid in a strategically important industrial and energy-demand region shaped by extensive mining activity.
According to the company, Leeuwpoort is the first large-scale battery energy storage project to achieve financial closure in Gauteng, a milestone the developer characterizes as an important step in accelerating South Africa's energy transition and grid modernization.
Procurement Under BESIPPPP Bid Window 2
The project was awarded under Bid Window 2 of the Battery Energy Storage Independent Power Producer Procurement Programme (BESIPPPP). Leeuwpoort is the third Mulilo BESS project to reach financial close this year, following the successful progression of the Mercury and Hartebeesfontein BESS projects.
The facility incorporates the Haohan battery energy storage system, supplied by BYD Energy Storage. Once operational, the Leeuwpoort BESS will provide critical storage capacity and ancillary services to the transmission system under a 15-year power purchase agreement with the National Transmission Company South Africa (NTCSA).
Trusted by Leading EPCs & Manufacturers
Find the Latest Battery Energy Storage System (BESS) in South Africa
Gain exclusive access to our industry-leading database of BESS opportunities with detailed project timelines and stakeholder information.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
Partnership Model and Community Participation
Mulilo states that Leeuwpoort reflects the strength of its partnership model and its commitment to meaningful participation. The Reatile Group serves as the project's strategic empowerment partner, while a local community trust is intended to ensure long-term community participation and shared socio-economic benefits.
In addition to its role as lead sponsor, Mulilo will provide construction management, asset management, operations and maintenance oversight, and social impact management services throughout the lifecycle of the project.
Industry Reaction
Jan Fourie, Chief Executive Officer of Mulilo, commented on the milestone: "The financial close of the Leeuwpoort project marks another significant milestone in Mulilo's commitment to strengthening South Africa's energy system through utility-scale battery energy storage. Projects such as Leeuwpoort play a critical role in enhancing grid stability, unlocking network capacity, and improving energy security."
He added: "Together with our partners and the support of the South African government, we are proud to deliver lasting value for the country while creating meaningful economic opportunities for local communities."
Sunette Smith, Chief Commercial Officer of the Reatile Group, said, "Reatile Group is proud to partner on Leeuwpoort, an important investment in strengthening South Africa's energy security and enabling the transition to a more resilient and sustainable energy system."
Financing and Project Support
Reaching financial close was made possible through the support of Mulilo's shareholders, Copenhagen Infrastructure Partners (CIP) and Norfund, along with collaboration with the Reatile Group, the Department of Electricity and Energy, Eskom, the Independent Power Producers Office, the National Transmission Company of South Africa and the Merafong City Local Municipality.
The project was enabled by a consortium of lenders comprising Absa Bank Limited, Nedbank Limited, and Standard Bank of South Africa Limited. Mulilo says the lending consortium's involvement demonstrates continued confidence in the company's project development and delivery capability.
Key advisers on the transaction included Arup, Bastion, Bowmans, Deloitte, ENS, Fasken, Marsh and Pepper Tree Capital.
Mulilo's Broader Pipeline
Mulilo is a South African renewable energy developer and independent power producer with a track record in the development, construction, and operation of wind, solar, and battery energy storage projects.
The company currently operates approximately 450 MW of renewable energy capacity, has a further 1,853 MW under construction, and has more than 1 GW of projects advancing toward financial close. Mulilo states that this positions the company to realise its medium-term ambition of delivering 5 GW of renewable energy assets.
Stay Ahead of South Africa's Expanding Power Grid
Every month, new generation plants, transmission corridors, and distribution upgrades take shape across South Africa, and the firms that win are the ones tracking them first. How do you compare to competitors who already have early visibility into the continent's next billion-dollar energy investments?
The Global Project Tracking (GPT) platform by Blackridge Research delivers curated, verified intelligence on power projects across every South African market, from solar farms to hydro schemes and grid modernization programs in South Africa. Instead of piecing together news scraps, you get a single, structured source of project intelligence built for business development teams.
Identify stakeholders early, time your outreach to procurement windows, and position your offerings before competitors even know a project exists.
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
Book a Free Demo of the Global Project Tracking (GPT) platform by Blackridge Research and start mapping South Africa's power project pipeline today.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.