DigiCo Infrastructure REIT has signed a 15-year contract for 71 MW of data centre capacity at its SYD1 facility in Sydney, an agreement that takes the site to 100 percent contracted across its planned 88 MW capacity.
The deal is with an unnamed global technology firm and includes investment-grade credit support.
A long-term anchor tenant for SYD1
The contract covers 71 MW of SYD1's total 88 MW capacity, including 20 MW of existing contracted capacity that has been reallocated to the new customer. The remaining 17 MW is leased to colocation customers, according to DigiCo.
The agreement significantly extends the income profile of DigiCo's Australian assets. It increases the weighted average lease expiry of the company's Australian portfolio from around three years to more than 10 years on a pro forma basis.
Weighted average annual escalations are approximately 3 percent, reflecting fixed escalators and CPI-linked reviews.
Expansion work moves ahead at Sydney
Alongside the leasing deal, DigiCo has executed a fixed-price, lump-sum design and construction contract for the next 52 MW of SYD1 capacity. Shape Australia has been appointed head contractor, while Laing O'Rourke will continue as the project's integrated delivery partner.
The expansion will reuse an established data centre site with approved grid capacity and water access. Construction is to be staged around customer requirements.
The first 10 MW is expected to be energised and generating income in late Q4 FY27, with the remaining capacity progressively energised through FY28.
Trusted by Leading EPCs & Manufacturers
Find the Latest Data Center Projects in Australia
Gain exclusive access to our industry-leading database of data center opportunities with detailed project timelines and stakeholder information
Request Free Trial → Learn More →
No credit card Up-to-date coverage
Funding without new equity
DigiCo said the SYD1 expansion remains fully funded through existing liquidity, available debt facilities, and proceeds from US asset sales, without requiring new equity.
The combined capital expenditure estimate for the SYD1 expansion and a 15 MW brownfield expansion at its ADL1 facility in Adelaide is USD 829.08 million over FY27 and FY28.
Once fully operational and stabilised, the two projects are expected to support approximately USD 172.73 million in annual Australian platform EBITDA.
Simon Mitchell, DigiCo's co-head and chief financial officer, said the contract marked a key milestone for the company. He noted that the 15-year agreement provides long-term earnings visibility.
US asset sales underpin the Australian pivot
The contract comes as DigiCo reshapes its portfolio around Australia, prioritising capital deployment into its Australian data centre platform. The company completed the sale of its Chicago data centre, CHI1, on 10 September for USD 750 million.
DigiCo has also agreed to a conditional sale of its LAX1 and LAX2 sites in Los Angeles, with completion of that transaction expected in the first half of FY27.
The planned US divestments are expected to reduce gearing from 39 per cent at the end of FY26 to a pro forma 18 per cent, increasing available liquidity to approximately USD 829.08 million.
Accelerating the Australian growth strategy
The 71 MW agreement fully contracts SYD1's planned 88 MW capacity and, according to the company, accelerates DigiCo's Australian growth strategy.
With a more than 10-year pro forma weighted average lease expiry, roughly 3 percent annual escalations, and USD 829.08 million of expansion capex already committed across Sydney and Adelaide, the company has now laid out a funded pathway to its target of approximately USD 172.73 million in annual Australian platform EBITDA.
Stay Ahead of Australia's Booming Data Center Pipeline
Australia is fast becoming the world's data center hotspot, with hyperscale campuses, edge facilities, and colocation projects racing to meet cloud and AI demand. But with billions of dollars flowing into new builds across markets, the question isn't whether opportunities exist; it's whether you'll spot them before your competitors do.
Fragmented information is the biggest obstacle. Project announcements, tender timelines, and contract awards are scattered across countless sources, making it nearly impossible to build a clear, real-time picture of the regional landscape.
The Global Project Tracking (GPT) platform by Blackridge Research changes that. It consolidates verified intelligence on data center developments across Australia into a single dashboard, so your business development, strategy, and investment teams can act on accurate insights, not guesswork.
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
Book a Free Demo today and see how the Global Project Tracking (GPT) platform by Blackridge Research can help you capture the data center opportunities shaping Australia's digital future.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.