ACME Solar Holdings Limited has secured 50 MW of contracted capacity in Gujarat Urja Vikas Nigam Limited’s (GUVNL) e-reverse auction conducted under the GUVNL-FDRE-I tender.
The company emerged as a successful bidder in the auction for the procurement of 500 MW of firm and dispatchable renewable energy power, with an additional 500 MW available under the greenshoe option. The tariff discovered in the auction was USD 0.05 per kWh, and ACME Solar will supply round-the-clock renewable power in Gujarat under the terms of the award.
ACME Solar's growing Indian capacity
The win adds to ACME Solar’s growing portfolio of contracted renewable energy capacity in India’s competitive auction market.
The GUVNL-FDRE-I tender, floated by the Gujarat state utility, sought bids for firm and dispatchable renewable energy (FDRE) supply, a category of procurement designed to provide power that is available on demand rather than subject to the inherent intermittency of solar or wind generation alone.
Details of the Auction Outcome
The e-reverse auction was conducted by GUVNL for the procurement of 500 MW of firm and dispatchable renewable energy power, with a greenshoe option providing for an additional 500 MW.
ACME Solar secured 50 MW of contracted capacity in the process, winning at a tariff of USD 0.05 per kWh. The auction format required participants to bid progressively lower tariffs, with the lowest competitive bids being awarded capacity.
The winning tariff of USD 0.05 per kWh represents the price at which ACME Solar will supply round-the-clock renewable power to GUVNL. The FDRE structure under which the capacity was awarded is distinct from conventional solar or wind tenders, as it obligates the developer to provide a firm and dispatchable power supply rather than energy delivered only when generation conditions permit.
Trusted by Leading EPCs & Manufacturers
Find the Latest Renewable Energy Projects in India
Gain exclusive access to our industry-leading database of renewable energy opportunities with detailed project timelines and stakeholder information
Request Free Trial → Learn More →
No credit card Up-to-date coverage
Significance of Firm and Dispatchable Renewable Energy Procurement
Firm and dispatchable renewable energy has emerged as an important category in India’s power procurement landscape.
Unlike standard solar or wind contracts, FDRE tenders require developers to guarantee power availability, typically by combining multiple generation sources, storage, or other balancing mechanisms to ensure supply can be delivered on a round-the-clock basis.
GUVNL, the state-owned power holding company of Gujarat, has been active in procuring renewable energy through competitive bidding to meet the state’s power requirements and renewable energy obligations.
The GUVNL-FDRE-I tender under which ACME Solar secured its 50 MW is part of the utility’s broader effort to bring renewable energy into its supply mix in a form that can be relied upon to meet demand throughout the day.
For developers, FDRE tenders present both an opportunity and a technical challenge. Winning at a tariff of USD 0.05 per kWh requires a project configuration capable of delivering firm supply, and the award reflects ACME Solar’s participation in this evolving segment of the market.
ACME Solar’s Position in the Sector
ACME Solar Holdings Limited is an Indian renewable energy company with an operating portfolio spanning solar and hybrid power generation.
The company has been a regular participant in auctions conducted by central agencies such as the Solar Energy Corporation of India (SECI) and NTPC, as well as state utilities, including GUVNL. The latest award of 50 MW in the GUVNL-FDRE-I auction adds round-the-clock renewable energy supply capacity to the company’s contracted portfolio.
The company’s success in the GUVNL auction comes as competition in India’s renewable energy bidding market remains intense, with tariffs across various tender categories continuing to be driven by scale, financing costs, and grid infrastructure considerations.
The USD 0.05 per kWh tariff discovered in this FDRE auction reflects the premium associated with firm, dispatchable supply compared with plain solar or wind tariffs, given the additional requirements placed on developers to guarantee availability.
Greenshoe Option and Capacity Expansion
The GUVNL-FDRE-I tender provided for a base procurement of 500 MW, with an additional 500 MW available under the greenshoe option. This structure allows the utility to expand the awarded capacity beyond the original target if competitive bids justify additional procurement.
The availability of the greenshoe option in the tender indicates the potential for the total capacity awarded under the auction to exceed the base 500 MW, though the specific allocation of the additional capacity among successful bidders was determined through the auction process.
ACME Solar’s 50 MW award positions the company among the successful bidders in a tender that attracted participation for firm and dispatchable renewable energy supply to Gujarat. The power procured under the auction will be supplied to GUVNL for distribution within the state.
Round-the-Clock Supply Commitment
Under the terms of the award, ACME Solar will supply round-the-clock renewable power in Gujarat at the contracted tariff of USD 0.05 per kWh.
The round-the-clock supply commitment means the power delivered must be available across all hours, distinguishing it from intermittent renewable supply that varies with sunlight or wind conditions.
The award underscores the continuing shift in Indian renewable energy procurement toward structures that treat renewable power as a dependable supply resource.
As states such as Gujarat expand their renewable energy procurement through FDRE and round-the-clock tenders, auctions like the GUVNL-FDRE-I process are becoming an established mechanism for bringing dispatchable clean energy into the grid while ensuring competitive pricing through the e-reverse auction format.
The 50 MW win at USD 0.05 per kWh marks ACME Solar’s latest capacity addition through competitive bidding, and the company will now move toward implementing the project requirements necessary to meet its firm and dispatchable supply obligations under the GUVNL contract.
Staying Ahead in India's Fast-Changing Power Sector
How do leading energy investors keep pace with grid modernization programs, renewable energy tenders, and thermal plant expansions happening across India at the same time?
Tracking power projects across India can be overwhelming when information is scattered across government portals, local news outlets, and regulatory filings. The Global Project Tracking (GPT) platform by Blackridge Research consolidates everything into one streamlined dashboard, giving you real-time visibility across the entire project lifecycle.
From feasibility studies to commissioning, every phase is mapped so you can identify opportunities early, connect with the right stakeholders, and make confident decisions backed by reliable data.
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
Ready to see how the Global Project Tracking (GPT) platform by Blackridge Research can strengthen your Indian power pipeline? Book a Free Demo today and discover the difference data-driven project intelligence can make.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.