Raipur Vizag Expressway: Current Status, Route Map & Timeline
Raipur Visakhapatnam Expressway: Corridor to Economic Growth

Project Profiles

Raipur Visakhapatnam Expressway: Corridor to Economic Growth

Updated on Feb 06, 2026, 01:44 PM IST
Written by Anandu Manoj
Edited by Siddhi Jain

Table of Contents

  • Loading contents...

Project at a Glance 

Project Name 

Raipur Visakhapatnam Expressway

Project Type

Greenfield

Sector

Infrastructure

Subsector

Expressway (Road Transport)

Project Value

INR 16,482 crore (USD 183.5 million)

Project Status

Under Construction

Starting Point

Abhanpur, Raipur, Chhattisgarh

Terminal

Sabbavaram, Vizag, Andhra Pradesh

Project Developer

National Highways Authority of India (NHAI)

Project Construction Start Date

2022

Project Completion Date

December 2026

Special Mention

Under the Bharatmala Pariyojana initiative

 

Project Overview

The Raipur Visakhapatnam Expressway is a large infrastructure project currently under construction in India.  This 465 km, six-lane expressway will be a greenfield development expected to be completed by December 2026.

 

The expressway will connect the cities of Raipur (Chhattisgarh) and Visakhapatnam (Andhra Pradesh), passing through the state of Odisha. The total project value is estimated at INR 16,482 crore and is being developed by the National Highways Authority of India (NHAI) under the Bharatmala Pariyojana Phase I initiative. This initiative aims to improve India's road network throughout the country.

 

The Raipur-Vizag economic corridor will have a positive impact by enhancing trade and connectivity between the three states it traverses. It will also reduce travel times and improve logistics for businesses in the region.

 

Find Road Infrastructure Projects and Tenders in IndiaGet Started Now!

 

Project Background

The Raipur Visakhapatnam Expressway project has a long history dating back to 2014. In that year, the Ministry of Road Transport and Highways (MoRTH) proposed the expressway to improve connectivity, tourism, and economic development in Central India. The Indian government approved the plan in 2017.

 

A noteworthy aspect of the project is the focus on improving infrastructure in Odisha. INR 10,000 crore, a substantial portion of the total project budget of INR 16,482 crore, has been allocated specifically for construction within the state. This highlights the government's commitment to enhancing regional connectivity through this expressway.

 

Union Minister Nitin Gadkari announced the completion of the project's DPR in 2021. The project transitioned from proposal to construction in November 2022 when Prime Minister Narendra Modi laid the foundation stone. To build this massive project, a Hybrid Annuity Model (HAM) is being used. This financing method involves splitting the risks and responsibilities between the government and private contractors.

 

Currently, the project is under construction with most of the land acquisition and bidding processes already completed, except for a few packages in Odisha.  A South Korean firm, YONGMA Engineering Co. Ltd. - Arkitechno Consultants, prepared the Detailed Project Report (DPR) for the expressway.  The entire project has been divided into 19 different packages, each assigned to a specific contractor responsible for completing their section within the designated timeframe and budget.

 

Read: Dwarka Expressway: India's First Elevated Eight Lane Highway 

 

Raipur Visakhapatnam Expressway Route Map

Raipur Visakhapatnam Expressway Route Map

Source: Wikimedia Commons

 

Project Timeline

Raipur Visakhapatnam Expressway Project Timeline

 

Project Scope

The Raipur-Visakhapatnam Expressway aims to remodel travel across three states. By cutting the distance between Raipur and Visakhapatnam from 590 km to 464 km, travel time will be reduced from 14 hours to 7 hours.  This expressway goes beyond its immediate path, planning to connect with the Eastern Economic Corridor, further boosting regional connectivity and economic opportunities. 

 

Project Cost

The total project cost is estimated at approximately INR 16,482 crore (USD 183.5 million), based on the Detailed Project Reports (DPRs) submitted by the three states involved in the project: Chhattisgarh, Odisha, and Andhra Pradesh.

 

Phase 1 - Chhattisgarh 

Category

Cost

Project Cost (approx.)

INR 4068.16 Cr

Resettlement & Rehabilitation Cost (R&R) including land Cost

INR 227.61 Cr

Environment Monitoring Plan Cost

INR 2.90 Cr

Corporate Environment Responsibility (CER) Fund Allocation

INR 20.33 Cr

Total Environment Management Plan Cost (approx.)

INR 9.15 Cr

 

Phase 2 - Odisha Project Cost 

Category

Cost

Total Project Cost (approx.)

INR 8092.00 Cr

Resettlement & Rehabilitation Land Cost

INR 215.87 Cr

Environment Monitoring Plan Cost

INR 5.20 Cr

Corporate Environment Responsibility (CER) Fund Allocation

INR 41.00 Cr

Total Environment Management Plan Cost (approx.)

INR 46.70 Cr

 

Phase 3 - Andhra Pradesh Project Cost 

Category

Cost

Total Project Cost (approx.)

INR 2542.67 crore

Resettlement & Rehabilitation Cost (R&R) including land cost

INR 220 crore

Environment Monitoring Plan Cost

INR 2.89 crore

Corporate Environment Responsibility (CER) Fund Allocation

INR 12.75 crore

Total Environment Management Plan Cost (approx.)

INR 11.80 crore

 

Raipur-Visakhapatnam Expressway Contractor List

For the construction of the National Highway, 19 civil packages have been established, stretching from north to south. The following is a list of the contractors involved.

 

Package

Contractor

State

Distance (km)

CG1

Shalimar Corp

Chhattisgarh

00.000 - 42.852

CG2

Dilip Buildcon Ltd.

Chhattisgarh

42.800 - 99.500

CG3

KMV Projects

Chhattisgarh

99.500 - 124.661

OD1

NKC Projects

Odisha

124.611 - 146.500

OD2

Barbrik

Odisha

146.500 - 179.000

OD3

Adani Transport

Odisha

179.000 - 226.500

OD4

NKC Projects

Odisha

226.500 - 249.000

OD5

HG Infra Engineering

Odisha

249.000 - 293.000

OD6

HG Infra Engineering

Odisha

293.000 - 338.500

OD7

DRA Infracon

Odisha

Scope Unknown

OD8

Max Infra (India)

Odisha

Scope Unknown

OD9

Scope Unknown

Odisha

Scope Unknown

OD10

Scope Unknown

Odisha

Scope Unknown

OD11

Scope Unknown

Odisha

Scope Unknown

AP Package 1

HG Infra

Andhra Pradesh

365.033 - 396.800

AP Package 2

NKC Projects

Andhra Pradesh

396.800 - 421.100

AP Package 3

PSK Infrastructures and Projects

Andhra Pradesh

421.100 - 445.100

AP Package 4

NKC Projects

Andhra Pradesh

445.100 - 464.662

 

Challenges During Construction

The construction of the Visakhapatnam-Raipur expressway faces several challenges:

 

Land Acquisition: This is a major hurdle, with projects worth INR 9,500 crore held up due to difficulties acquiring land in the Vizianagaram district. The district administration is taking steps to expedite the process.

 

Environmental Impact: The highway development can have significant detrimental impacts on nearby wildlife and the environment. Specific measures, like animal crossings and monkey canopies in Udanti Wildlife Sanctuary, are being proposed to mitigate these impacts.

 

Environmental Regulations:  Environmental impact assessments are crucial to account for potential harm and are a legal requirement for obtaining financial support. Completing these assessments can add complexity to the project timeline.

 

Benefits of the Project

The Raipur-Visakhapatnam Expressway project promises a multitude of benefits for the states of Chhattisgarh, Odisha, and Andhra Pradesh:

 

Reduced Travel Time:  Travel time between Raipur and Visakhapatnam will be significantly reduced, dropping from a lengthy 14 hours to a more manageable 7 hours. This will improve connectivity and make travel between these major cities much more convenient.

 

Economic Boost: The expressway will create a crucial corridor connecting Dhamtari's paddy belt and Kondagaon's handicraft hub to a wider national market. This improved accessibility is expected to stimulate trade, generate new jobs, and accelerate economic development throughout the region.

 

Enhanced Regional Connectivity:  The project is designed to connect with the Eastern Economic Corridor in the future, further strengthening regional connections and unlocking new economic opportunities.

 

Improved Quality of Life:  By reducing travel times, boosting economic activity, and creating jobs, the expressway has the potential to significantly improve the overall quality of life for residents in the three states.

 

Raipur Vizag Expressway Opening Date

On 17th January 2025, NHAI announced Koraput segment of the six-lane Raipur-Visakhapatnam economic corridor construction is finished by more than 70% and is likely to be commissioned in October 2025. However, due to the delays faced, the expressway is now scheduled for completion in December 2026 (FY 2026-27). It is set to cut the distance from 597 km on the existing NH-26 to 465 km, saving 132 km and nearly seven hours of travel time.

Conclusion

The Raipur Visakhapatnam Expressway, a crucial infrastructure project in India, spans 464 km, connecting Raipur and Visakhapatnam via Odisha. Scheduled for completion by 2025 with an estimated budget of INR 15,000 crore, it aims to halve travel time between the two cities to 7 hours, fostering regional connectivity and economic growth. Despite challenges like land acquisition and environmental concerns, the project progresses in 19 sections, each managed by designated contractors. Once operational, it promises to boost trade, stimulate economic activity, and enhance the quality of life for residents. 

 

Get Early Access to Tender/Bid Opportunities in Road & Highway Infrastructure Projects in India!

Gain early access to reliable and high-quality insights on upcoming, in-progress, and completed Road & Highway Infrastructure Projects in India. Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for EPC contractors, civil engineers, general contractors, construction project managers, investors, and legal advisory/consulting firms.

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile