Raipur Visakhapatnam Expressway: Corridor to Economic Growth
Table of Contents
- Loading contents...
Project at a Glance | |
Project Name | Raipur Visakhapatnam Expressway |
Project Type | Greenfield |
Sector | Infrastructure |
Subsector | Expressway (Road Transport) |
Project Value | INR 16,482 crore (USD 183.5 million) |
Project Status | Under Construction |
Starting Point | Abhanpur, Raipur, Chhattisgarh |
Terminal | Sabbavaram, Vizag, Andhra Pradesh |
Project Developer | National Highways Authority of India (NHAI) |
Project Construction Start Date | 2022 |
Project Completion Date | December 2026 |
Special Mention | Under the Bharatmala Pariyojana initiative |
Project Overview
The Raipur Visakhapatnam Expressway is a large infrastructure project currently under construction in India. This 465 km, six-lane expressway will be a greenfield development expected to be completed by December 2026.
The expressway will connect the cities of Raipur (Chhattisgarh) and Visakhapatnam (Andhra Pradesh), passing through the state of Odisha. The total project value is estimated at INR 16,482 crore and is being developed by the National Highways Authority of India (NHAI) under the Bharatmala Pariyojana Phase I initiative. This initiative aims to improve India's road network throughout the country.
The Raipur-Vizag economic corridor will have a positive impact by enhancing trade and connectivity between the three states it traverses. It will also reduce travel times and improve logistics for businesses in the region.
Find Road Infrastructure Projects and Tenders in IndiaGet Started Now!
Project Background
The Raipur Visakhapatnam Expressway project has a long history dating back to 2014. In that year, the Ministry of Road Transport and Highways (MoRTH) proposed the expressway to improve connectivity, tourism, and economic development in Central India. The Indian government approved the plan in 2017.
A noteworthy aspect of the project is the focus on improving infrastructure in Odisha. INR 10,000 crore, a substantial portion of the total project budget of INR 16,482 crore, has been allocated specifically for construction within the state. This highlights the government's commitment to enhancing regional connectivity through this expressway.
Union Minister Nitin Gadkari announced the completion of the project's DPR in 2021. The project transitioned from proposal to construction in November 2022 when Prime Minister Narendra Modi laid the foundation stone. To build this massive project, a Hybrid Annuity Model (HAM) is being used. This financing method involves splitting the risks and responsibilities between the government and private contractors.
Currently, the project is under construction with most of the land acquisition and bidding processes already completed, except for a few packages in Odisha. A South Korean firm, YONGMA Engineering Co. Ltd. - Arkitechno Consultants, prepared the Detailed Project Report (DPR) for the expressway. The entire project has been divided into 19 different packages, each assigned to a specific contractor responsible for completing their section within the designated timeframe and budget.
Read: Dwarka Expressway: India's First Elevated Eight Lane Highway
Raipur Visakhapatnam Expressway Route Map

Source: Wikimedia Commons
Project Timeline

Project Scope
The Raipur-Visakhapatnam Expressway aims to remodel travel across three states. By cutting the distance between Raipur and Visakhapatnam from 590 km to 464 km, travel time will be reduced from 14 hours to 7 hours. This expressway goes beyond its immediate path, planning to connect with the Eastern Economic Corridor, further boosting regional connectivity and economic opportunities.
Project Cost
The total project cost is estimated at approximately INR 16,482 crore (USD 183.5 million), based on the Detailed Project Reports (DPRs) submitted by the three states involved in the project: Chhattisgarh, Odisha, and Andhra Pradesh.
Phase 1 - Chhattisgarh
Category | Cost |
Project Cost (approx.) | INR 4068.16 Cr |
Resettlement & Rehabilitation Cost (R&R) including land Cost | INR 227.61 Cr |
Environment Monitoring Plan Cost | INR 2.90 Cr |
Corporate Environment Responsibility (CER) Fund Allocation | INR 20.33 Cr |
Total Environment Management Plan Cost (approx.) | INR 9.15 Cr |
Phase 2 - Odisha Project Cost
Category | Cost |
Total Project Cost (approx.) | INR 8092.00 Cr |
Resettlement & Rehabilitation Land Cost | INR 215.87 Cr |
Environment Monitoring Plan Cost | INR 5.20 Cr |
Corporate Environment Responsibility (CER) Fund Allocation | INR 41.00 Cr |
Total Environment Management Plan Cost (approx.) | INR 46.70 Cr |
Phase 3 - Andhra Pradesh Project Cost
Category | Cost |
Total Project Cost (approx.) | INR 2542.67 crore |
Resettlement & Rehabilitation Cost (R&R) including land cost | INR 220 crore |
Environment Monitoring Plan Cost | INR 2.89 crore |
Corporate Environment Responsibility (CER) Fund Allocation | INR 12.75 crore |
Total Environment Management Plan Cost (approx.) | INR 11.80 crore |
Raipur-Visakhapatnam Expressway Contractor List
For the construction of the National Highway, 19 civil packages have been established, stretching from north to south. The following is a list of the contractors involved.
Package | Contractor | State | Distance (km) |
CG1 | Shalimar Corp | Chhattisgarh | 00.000 - 42.852 |
CG2 | Dilip Buildcon Ltd. | Chhattisgarh | 42.800 - 99.500 |
CG3 | KMV Projects | Chhattisgarh | 99.500 - 124.661 |
OD1 | NKC Projects | Odisha | 124.611 - 146.500 |
OD2 | Barbrik | Odisha | 146.500 - 179.000 |
OD3 | Adani Transport | Odisha | 179.000 - 226.500 |
OD4 | NKC Projects | Odisha | 226.500 - 249.000 |
OD5 | HG Infra Engineering | Odisha | 249.000 - 293.000 |
OD6 | HG Infra Engineering | Odisha | 293.000 - 338.500 |
OD7 | DRA Infracon | Odisha | Scope Unknown |
OD8 | Max Infra (India) | Odisha | Scope Unknown |
OD9 | Scope Unknown | Odisha | Scope Unknown |
OD10 | Scope Unknown | Odisha | Scope Unknown |
OD11 | Scope Unknown | Odisha | Scope Unknown |
AP Package 1 | HG Infra | Andhra Pradesh | 365.033 - 396.800 |
AP Package 2 | NKC Projects | Andhra Pradesh | 396.800 - 421.100 |
AP Package 3 | PSK Infrastructures and Projects | Andhra Pradesh | 421.100 - 445.100 |
AP Package 4 | NKC Projects | Andhra Pradesh | 445.100 - 464.662 |
Challenges During Construction
The construction of the Visakhapatnam-Raipur expressway faces several challenges:
Land Acquisition: This is a major hurdle, with projects worth INR 9,500 crore held up due to difficulties acquiring land in the Vizianagaram district. The district administration is taking steps to expedite the process.
Environmental Impact: The highway development can have significant detrimental impacts on nearby wildlife and the environment. Specific measures, like animal crossings and monkey canopies in Udanti Wildlife Sanctuary, are being proposed to mitigate these impacts.
Environmental Regulations: Environmental impact assessments are crucial to account for potential harm and are a legal requirement for obtaining financial support. Completing these assessments can add complexity to the project timeline.
Benefits of the Project
The Raipur-Visakhapatnam Expressway project promises a multitude of benefits for the states of Chhattisgarh, Odisha, and Andhra Pradesh:
Reduced Travel Time: Travel time between Raipur and Visakhapatnam will be significantly reduced, dropping from a lengthy 14 hours to a more manageable 7 hours. This will improve connectivity and make travel between these major cities much more convenient.
Economic Boost: The expressway will create a crucial corridor connecting Dhamtari's paddy belt and Kondagaon's handicraft hub to a wider national market. This improved accessibility is expected to stimulate trade, generate new jobs, and accelerate economic development throughout the region.
Enhanced Regional Connectivity: The project is designed to connect with the Eastern Economic Corridor in the future, further strengthening regional connections and unlocking new economic opportunities.
Improved Quality of Life: By reducing travel times, boosting economic activity, and creating jobs, the expressway has the potential to significantly improve the overall quality of life for residents in the three states.
Raipur Vizag Expressway Opening Date
On 17th January 2025, NHAI announced Koraput segment of the six-lane Raipur-Visakhapatnam economic corridor construction is finished by more than 70% and is likely to be commissioned in October 2025. However, due to the delays faced, the expressway is now scheduled for completion in December 2026 (FY 2026-27). It is set to cut the distance from 597 km on the existing NH-26 to 465 km, saving 132 km and nearly seven hours of travel time.
Conclusion
The Raipur Visakhapatnam Expressway, a crucial infrastructure project in India, spans 464 km, connecting Raipur and Visakhapatnam via Odisha. Scheduled for completion by 2025 with an estimated budget of INR 15,000 crore, it aims to halve travel time between the two cities to 7 hours, fostering regional connectivity and economic growth. Despite challenges like land acquisition and environmental concerns, the project progresses in 19 sections, each managed by designated contractors. Once operational, it promises to boost trade, stimulate economic activity, and enhance the quality of life for residents.
Get Early Access to Tender/Bid Opportunities in Road & Highway Infrastructure Projects in India!
Gain early access to reliable and high-quality insights on upcoming, in-progress, and completed Road & Highway Infrastructure Projects in India. Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for EPC contractors, civil engineers, general contractors, construction project managers, investors, and legal advisory/consulting firms.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.