Project at a Glance | |
Project Name | Mumbai Metro Aqua Line |
Project Type | Greenfield |
Project Sector | Infrastructure |
Project Status | Operational |
Project Cost | INR 37,270 crore (approximately USD 4.24 billion) |
Metro Length | 33.5 km |
Total Stations |
|
Operator | MMRC (Mumbai Metro Rail Corporation Limited) |
Starting Point | Aarey JVLR in the North |
Ending Point | Cuffe Parade in South Mumbai |
Final Stretch Inauguration | October 2025 |
Project Overview
The Mumbai Metro Aqua Line project is a metro project operated by MMRC (Mumbai Metro Rail Corporation Limited). It is 33.5 km long with 27 stations (26 underground and 1 at-grade). It starts from Aarey JVLR in the North to Cuffe Parade in South Mumbai. It is also known as the Mumbai Metro Line 3 or Colaba-Bandra-SEEPZ Line.
It connects South Mumbai to Western Suburbs, reducing travel time and easing congestion on the highways. It acts as a user-oriented transportation option for residents, office-goers, and tourists.
Mumbai Metro Aqua Line Opening Date
The project is built in three phases with 26 underground stations and one at-grade station. Its first phase, Aarey Mumbai corridor to Bandra Kurla Complex (BKC), became operational on October 7, 2024. The second phase, which stretches from Bandra Kurla Complex (BKC) to Worli (Acharya Atre Chowk), became operational on May 10, 2025. The final phase of the project became operational on 08 October 2025.
Project Background
The concept for the Mumbai Metro Aqua Line was initiated in 2004, when planners proposed an underground route connecting Colaba and Bandra to relieve congestion on the city's overcrowded roads and railways.
In 2011, the line was extended further north to SEEPZ, increasing its total length to 33.5 km. It is the first fully underground metro line from Cuffe Parade in South Mumbai to Aarey Colony in the north.
In June 2013, the Union Cabinet granted formal clearance for the project, followed by approval from the Maharashtra Cabinet in February 2014. Chief Minister Prithviraj Chavan and Union Minister Venkaiah Naidu laid the foundation stone on 26 August 2014.
The construction work on the corridor commenced on 21st October 2016. It faced legal disputes, resulting in delays.
In July 2016, seven major civil work packages covering tunnels and stations were awarded to international and Indian construction consortia. After mobilization, full-scale construction activities commenced in early 2017, and by October 2017, the first of 17 Tunnel Boring Machines (TBMs) began underground excavation work.
Mumbai Metro Aqua Line Project Ownership Details
The Metro Line 3 project is being developed by the Mumbai Metro Rail Corporation Limited (MMRC). It is a joint venture between the GOI (Government of India) and the GOM (Government of Maharashtra), each holding a 50% share.
40+ reviews
Find the Latest Railway Infrastructure Projects In India
Gain exclusive access to our industry-leading database of infrastructure opportunities with detailed project timelines and stakeholder information.
Collect Your Free Leads Here!
No credit cardUp-to-date coverage
Joined by 750+ industry professionals last month
Project Timeline
YEAR | EVENT |
8 October 2025 | Phase III inaugurated by the Prime Minister Narendra Modi |
10 May 2025 | Phase II inaugurated. |
7 October 2024 | Phase I inaugurated. |
30 August 2022 | First trial run held on a 3 km section between Aarey Colony and Marol Naka. |
May 2021 | All 17 Tunnel Boring Machines completed. |
October 2017 | The first of 17 Tunnel Boring Machines (TBMs) began underground excavation work. |
Early 2017 | Full-scale construction activities commenced |
26 August 2014 | Chief Minister Prithviraj Chavan and Union Minister Venkaiah Naidu laid the foundation stone |
February 2014 | The Maharashtra Cabinet approved the project |
June 2013 | The Union Cabinet granted formal clearance for the project |
Mumbai Metro Aqua Line Route Map
Mumbai Metro Line 3: Aqua Line
The Mumbai Metro Aqua Line is a 33.5 km-long underground tunnel, starting from Aarey JVLR in the north to Cuffe Parade in South Mumbai. It connects a total of 27 stations (26 underground, one at-grade), passing through key locations.
These include Mumbai International Airport Terminal 2 and Terminal 1, Santacruz, Bandra Kurla Complex, Dharavi, Dadar, Worli, Acharya Atre Chowk, Mahalaxmi, Grant Road, Chhatrapati Shivaji Maharaj Terminus (CSMT), Churchgate, Vidhan Bhavan, and terminating at Cuffe Parade.
The Three Phases Of The Mumbai Metro Line 3
The Mumbai Metro Aqua Line (also known as Mumbai Metro Line 3), is being developed in three phases. Below follows a detailed description:
Phase I: Aarey Colony to Bandra-Kurla Complex (BKC)
Phase I focuses on the metro construction between Aarey Colony and Bandra-Kurla Complex (BKC). It is approximately a 13 km long stretch, covering 10 stations. It includes:
Aarey
SEEPZ
MIDC
Airport T2
Marol Naka
Sahar Road
Airport T1
Santacruz
Bandra Colony
BKC
Operational since 7 October 2024, it connects key industrial, commercial, and airport hubs, significantly reducing travel time and easing congestion in Mumbai's north-west corridor.
Phase II: BKC to Worli
The Phase II constructed a metro line between BKC and Worli. It is a nearly 10 km long underground stretch, including six stations. These include:
Dharavi,
Shitaladevi Temple
Dadar West
Siddhivinayak Temple
Worli
Acharya Atre Chowk (Worli Naka).
It has been in operation since 10 May 2025 and incorporates modern amenities, including escalators, elevators, platform screen doors, and driverless compatible trains running every 6 minutes and 20 seconds.
40+ reviews
Find the Latest Railway Infrastructure Projects In India
Gain exclusive access to our industry-leading database of railway infrastructure opportunities with detailed project timelines and stakeholder information.
Collect Your Free Leads Here!
No credit cardUp-to-date coverage
Joined by 750+ industry professionals last month
Phase III: Worli to Cuffe Parade
Phase III of the project is approximately 9.5 km long, an underground stretch connecting Worli to Cuffe Parade. It includes 11 stations, namely:
Science Museum
Mahalaxmi
Grant Road
Girgaon
Kalbadevi
CSMT
Hutatma Chowk
Churchgate
Vidhan Bhavan
Cuffe Parade
Initially, the project expected its Phase III inauguration by September 30, 2025. But it got delayed. Later, Prime Minister Narendra Modi inaugurated it on 8 October 2025.
The operation of the third phase marks the completion of the 31 air-conditioned driverless trains, which reduce travel time across the city and significantly ease congestion while linking suburban rail, monorail, and metro networks.
Mumbai Metro Aqua Line Project Cost
The total estimated cost for the construction of the Mumbai Metro Aqua Line is INR 37,270 crore (approximately USD 4.24 billion). It includes the cost for the underground tunneling and stations construction, procurement and installation of trains and signaling systems, and cost escalations due to delays and complexities.
JICA (Japan International Cooperation Agency) is financing 57.2% of the project through an ODA loan of INR 13,235 crores. The loan includes a 30-year repayment period, a 1.15% interest rate for project activities, and a 0.01% interest rate for consulting services.
Mumbai Metro Line 3 Project Contractors
CONTRACTORS | ROLE |
Mumbai Metro Rail Corporation Ltd. (MMRCL) | Oversees the project management and execution. |
AECOM Asia Co. Ltd., PADECO Co.Ltd (Japan), LBG Inc. (USA), Egis Rail (France) | Responsible for project planning, technical supervision, and design management. |
Alstom Transport India & France | Supplied 31 eight-car driverless trains, Urbalis 400 CBTC signalling systems, telecom, power supply, and automation systems. |
Aarey Depot Works: L&T Construction | Design and construction of depot, maintenance sheds, and operational control center at Aarey. |
Geoconsult India & ILF Consulting Engineers | Ground condition analysis and tunnel structure optimization. |
Delhi Metro Rail Corporation | Contracted to operate and maintain the Mumbai Metro Line 3 for 10 years after commissioning. |
Mumbai Metro Line 3 Project Investors
INVESTORS | ROLE |
Japan International Cooperation Agency (JICA) | Provided a soft loan through ODA assistance with a 1.15% interest rate and a 30-year repayment term. |
Government of India | Provided Equity and Subordinate Debt |
Government of Maharashtra | Provided Equity and Subordinate Debt |
Mumbai International Airport Limited (MIAL) | Constructed and financed three airport metro stations through UDF collection. |
Mumbai Metro Aqua Line Project Expansion
Mumbai Metro Rail Corporation Limited (MMRC) has planned to expand the Mumbai Metro Aqua Line to Navy Nagar in Colaba, Mumbai. The plan for this 5 km expanded stretch was announced in November 2023. The approval from the state and central government is still pending.
The Detailed Project Report (DPR) for the metro expansion plan has been submitted to the relevant authorities. According to the officials, the aim is to improve metro connectivity to the Navy Office in Mumbai.
Benefits
The following are the benefits of the Mumbai Metro Aqua Line:
Improved connectivity: The Mumbai Metro Line 3 provides direct access to Chhatrapati Shivaji Maharaj International Airport (Terminals 1 and 2) via dedicated stations, easing airport commutes.
Reduced Traffic Congestion: Reduces peak-hour traffic on Mumbai's congested roads by providing a high-capacity metro.
Divert commuter volume: The project expects to serve 17 lakh passengers daily by 2031, diverting significant commuter volume from buses and private vehicles.
Reduce Travel Time: It reduces travel time by serving a fast and uninterrupted underground connection, covering the entire 33.5 km stretch in 60 minutes, compared to 120-180+ minutes by road during peak traffic.
Reduce Carbon Dioxide Emissions: The Mumbai Metro Aqua Line project promotes public transport, reducing 3.5 lakh tonnes of CO2 annually.
Boost public transport: The metro line is designed to handle around 1.3 million passengers daily, easing Mumbai's public transport demand.
Conclusion
The Mumbai Metro Aqua Line project is a metro infrastructure project connecting South Mumbai to Western Suburbs and reducing congestion on the highways. It is a 33.5 km long corridor comprising 26 underground and one at-grade station. It is being developed by the Mumbai Metro Rail Corporation Limited (MMRC).
The Mumbai Metro Aqua Line starts from Aarey JVLR in the north and ends at Cuffe Parade in South Mumbai. It is also known as the Mumbai Metro Line 3 or Colaba-Bandra-SEEPZ Line. The project is being developed in three phases, with the final phase operational since October 2025.
Approximately 1.6 million passengers will ride the Mumbai Metro Aqua Line daily, cutting commute times by up to half and significantly reducing road congestion and carbon emissions. Besides easing urban mobility, it symbolizes Mumbai's advancement toward a modern, sustainable transit ecosystem competitive with global metro systems in efficiency and design.
Track The Latest Railway (Train) Infrastructure Projects In India for Business Opportunities.
Subscribe to our upcoming and ongoing Railway Infrastructure Projects in India to access reliable, high-quality insights on forthcoming and completed infrastructure projects across the country
Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.
Start a free demo to take your business to the next level.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.