A massive data center development planned for Grayslake, Illinois, has cleared a significant milestone after village officials issued the first building permit for the project, authorizing construction of an 800,000-square-foot facility that forms the opening phase of a campus expected to draw as much as USD 18 billion in private investment over the coming decade.
A Campus of Unprecedented Scale
The project, known as the Cornerstone development and led by T5 Data Centres, is planned on land along Peterson Road in Grayslake. According to village documents, the latest plans call for approximately 6.7 million square feet of data center space to be built out over seven to ten years.
Earlier approvals had permitted an even larger footprint, allowing for up to roughly 473 acres and as much as 10.1 million square feet of development.
The T5 Chicago IV data center campus has received its initial building permit from the Village of Grayslake, allowing site work to begin on the first 800,000-square-foot facility. The campus is planned across up to 472 acres and could include more than 10 million square feet of data center buildings, with an electrical demand of approximately 1.55 GW.
That first building alone will encompass 800,000 square feet, establishing the foundation for what is envisioned as one of the largest data center campuses in the region.
The project is projected to generate approximately USD 1.4 billion in property tax and permit-fee revenue over its first 20 years. The development is proceeding without local tax incentives, exemptions, or tax-increment financing subsidies.
The additional revenue could support infrastructure, parks, trails, schools, and other community priorities. Grayslake operates with a balanced budget and no municipal debt.
Project Commitments and Community Considerations
The project includes continued engagement with the local community and provisions for incorporating community input into the development process. As part of this approach, an application related to the remediation of local wetlands was voluntarily withdrawn following concerns raised during the review process.
The development also includes work with the village to establish standards related to noise, water use, and electricity consumption. The project is projected to generate approximately USD 1.4 billion in property tax and permit-fee revenue over twenty years, aligning with estimates for the development's fiscal contribution.
Trusted by Leading EPCs & Manufacturers
Find the Latest Data Center Projects Around the United States of America
Gain exclusive access to our industry-leading database of data center opportunities with detailed project timelines and stakeholder information
Request Free Trial → Learn More →
No credit card, up-to-date coverage
Water, Power, and Environmental Requirements
The Grayslake project arrives at a moment when data centers across the United States are facing growing scrutiny over their demands on electricity and water supplies, driven in part by the rapid expansion of artificial intelligence and the computing infrastructure it requires.
Village officials said the planned campus will use closed-loop cooling systems. They estimate that an average data center building within the campus would consume approximately 2,500 to 3,500 gallons of water per day. For the full 6.75-million-square-foot campus, the village estimates total water consumption at approximately 50,000 gallons per day.
On the electricity side, the developer is expected to fund the electrical infrastructure the campus requires, including construction of an electrical substation on the property, according to the village.
Power Your Pipeline: Data Center Intelligence Across the United States
How much revenue are you leaving on the table by reacting to data center opportunities instead of anticipating them? In one of the fastest-expanding infrastructure sectors the United States has seen in decades, the difference between winning and watching comes down to the quality of your project intelligence.
The Global Project Tracking (GPT) platform by Blackridge Research was built for companies that operate at the speed of this market. Whether you are supplying cooling systems, structural steel, fiber cabling, or construction labor, our platform delivers the project-level visibility you need to position your business ahead of procurement cycles, not after they close.
From hyperscale campuses in the Southwest to edge facilities spreading across the United States, our continuously updated data gives your sales and business development teams a reliable foundation to target the right projects at the right time.
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
See exactly how the Global Project Tracking (GPT) platform by Blackridge Research can sharpen your competitive edge in the data center sector. Book a free demo with our team today.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.