Spartanburg County Council in South Carolina approved three proposed data center development agreements on the third and final reading, clearing another step for projects representing a combined anticipated investment of approximately USD 5.5 billion.
The agreement for Valara Holdings LLC passed in a 3-2 vote, with Councilmen Monier Abusaft and Grant DeShields voting against it. The agreements for AIB CLT1 LLC and 300 Jones Road Associates LLC both received approval.
Valara Holdings Project
The proposed 457-megawatt Valara data center is planned for about 300 acres along South Pine Street. The project represents an anticipated investment of roughly USD 2.8 billion and is expected to create 27 full-time jobs.
The development agreement received final approval despite opposition from two council members. The agreement establishes a 10-year development period and includes provisions addressing noise mitigation, lighting, and landscaping.
AIB CLT1 Project
AIB plans to replace its existing Bitcoin mining operation at Tyger River Industrial Park in Moore with a permanent data center building. The 50-megawatt project represents an anticipated USD 1.2 billion investment and is expected to create 28 jobs.
The agreement received unanimous approval on November 16. Under the agreement, AIB CLT1 has committed USD 12.6 million in community benefits over a 12-year period. The contribution could support local road improvements, affordable housing, and other community initiatives.
Trusted by Leading EPCs & Manufacturers
Find the Latest Data Center Projects in the United States
Gain exclusive access to our industry-leading database of data center opportunities with detailed project timelines and stakeholder information.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
300 Jones Road Project
The Jones Road project would redevelop about 137 acres of the former R.R. Donnelley property into a data center with up to 65 megawatts of capacity. The company anticipates investing USD 1.5 billion and creating 25 jobs.
Council unanimously approved the development agreement on its third and final reading. The agreement also includes a USD 9 million community benefit commitment over five years, alongside requirements covering noise mitigation, landscaping, and equipment screening.
Three More Agreements Advance
Alongside the three final approvals, the council gave initial approval to three additional data center development agreements proposed by AIB for Tyger River Industrial Park in Moore. AIB CLT2, CLT3 and CLT4 all passed unanimously on first reading. These proposals will require further readings before receiving final approval.
Public Response
The November 16 meeting drew a large crowd, with residents speaking both for and against the proposed developments. Opponents raised concerns about potential noise, pollution, and the effects of data center operations on nearby communities. Supporters highlighted the anticipated investment, employment opportunities, and additional county revenue.
The debate follows earlier public hearings in which residents questioned the project agreements and requested greater transparency regarding site plans, environmental safeguards, and community commitments.
Don't Just Track the Hyperscale Boom, Stay Ahead of It Across the United States
Data center construction in the United States is moving at breakneck speed, driven by AI workloads, cloud expansion, and edge computing demand. Every delayed tender or missed contract award is a lost opportunity for suppliers, contractors, and investors racing to serve this market.
The Global Project Tracking (GPT) platform by Blackridge Research gives you a real-time window into data center development nationwide, from early-stage announcements to commissioning, so you can position your business before competitors even know a project exists.
Whether you target hyperscale campuses, colocation facilities, or modular builds, decision-ready intelligence on every project phase puts you first in line for new opportunities.
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
Book a free demo today and see how the Global Project Tracking (GPT) platform by Blackridge Research can transform your data center market strategy in the United States.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.