Pure DC Completes Final Power Transformer Installation at 90 MW Data Center Campus in North London, UK

project_news

Pure DC Completes Final Power Transformer Installation at 90 MW Data Center Campus in North London, UK

Updated on Oct 16, 2026, 11:22 AM IST
Written & Edited by Ashish

Pure Data Centers Group (Pure DC), one of the fastest-growing hyperscale cloud and AI infrastructure platforms across Europe and the Middle East, has completed the installation of the third and final power transformer at its 90 MW LON01 data center campus in North London.

 

The Third Transformer Completes Dedicated Campus Power System

The 75MVA Hitachi transformer is the final major component in a three-transformer installation that brings the substation's total capacity to 150MVA. LON01 is designed to deliver a next-generation, closed-loop, liquid-cooled data center capable of supporting high-density AI inference and cloud workloads.

The new transformer will support a stable and reliable power supply to the campus's B1 and B2 buildings, with dedicated ductwork already in place for the connection to B2. Energisation is planned for later this month. Once energised, the transformer will complete the dedicated power system serving the campus.

 

A 1,000-Tonne Gantry Solution in Place of a 500-Tonne Crane

Installing the transformer required an engineered solution to an unusually complex lifting challenge. Restricted space around the live LON01 substation meant that a conventional 500-tonne crane could not be deployed.

 

Instead, the project team designed and implemented a specialist gantry system with a lifting capacity of 1,000 tonnes, enabling the transformer to be moved safely and precisely into its permanent position.

The transformer was lifted into position in a four-hour operation involving Pure DC's project team, MGE Group, logistics partners and specialist suppliers. The tightly controlled lift followed extensive preparation and coordination to manage the restricted site conditions and complete the work safely alongside existing infrastructure.

Trusted by Leading EPCs & Manufacturers

Find the Latest Data Center Projects in the United Kingdom

Gain exclusive access to our industry-leading database of data center opportunities with detailed project timelines and stakeholder information

Request Free Trial → Learn More →

No credit card Up-to-date coverage

 

An 18-Month Journey from Colombia to North London

The installation was the culmination of an 18-month programme that began with manufacturing in Colombia in March 2025. Following completion of factory testing in June 2026, the transformer travelled by sea to the UK before a carefully coordinated final journey to the campus.

The operation required detailed route and logistics planning, road closures and local authority approvals.

A Living Wall Alongside Brent Reservoir

Beyond the power infrastructure, the campus has an environmental feature planned. After completion of B2, LON01 will be home to one of the world's largest living walls.

 

Over 750,000 plants will wrap around B2 to reduce noise and air pollution, as well as encourage biodiversity of insects and birds next to Brent Reservoir's Site of Special Scientific Interest (SSSI).

Don't Miss the Next Hyperscale Buildout Across the United Kingdom

United Kingdom's data center pipeline is expanding faster than power grids and permitting authorities can keep up, and the developers, contractors, and suppliers who move first capture the value. The question is simple: are you seeing these opportunities before your competitors do, or after the contracts are already signed?

 

The Global Project Tracking (GPT) platform by Blackridge Research gives you a real-time view of data center development across the United Kingdom, from early-stage announcements through final handover. Track colocation campuses, hyperscale facilities, and edge deployments with the depth of intelligence that turns market noise into an actionable pipeline.

 

Every project profile is built on verified sourcing and regular updates, so your business development, strategy, and investment teams can act on information, not assumptions.

 

  • Upcoming Projects

  • Tender Notices

  • Contract Awards

  • Projects Under Construction

  • Completed Projects

 

Book a Free Demo today and see how the Global Project Tracking (GPT) platform by Blackridge Research can sharpen your competitive edge in the United Kingdom's data center market.

Tags

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile