Ørsted has announced that the first wind turbine components for its Hornsea 3 offshore wind farm are now on site at ABLE Seaton Port in the North East of England, ready for their journey offshore. The components include blades, nacelles, and towers.
The news was shared by Ørsted, which stated that moving components of this size and structure requires specialist machinery and expert handling.
Scale of the Components
The turbine towers arrive at the port in four sections for assembly on site. When completed, each tower stands just under 130 metres tall. Each wind turbine blade measures 115 metres in length.
A number of the blades are manufactured at the Siemens Gamesa factory in Hull, located just down the coast from the port.
READ NEXT: DWT Wins UK's First Full-Scope Offshore Service Contract for Lynn and Inner Dowsing Wind Farms
Economic Impact Along the Coast
The arrival of components at Able Seaton Port brings the number of ports working with Hornsea 3 in the region to three. According to Ørsted, this is helping to support economic development along the coast.
Through its partnership with Hornsea 3, Able Seaton Port and its contractors have employed approximately 70 new workers. The company expects economic growth to increase by around 40% locally as a result.
Trusted by Leading EPCs & Manufacturers
Find the Latest Offshore Wind Farm Projects in the United Kingdom
Gain exclusive access to our industry-leading database of offshore wind opportunities with detailed project timelines and stakeholder information.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
About Hornsea 3's logistics
The delivery of blades, nacelles, and towers to Able Seaton Port marks the beginning of the assembly and load-out process for the project's first turbines. With towers assembled from four sections on site and blades arriving partly from the Siemens Gamesa facility in Hull, the port is serving as a staging point for the components before they make the long journey offshore.
Hornsea 3 to Feature 197 Offshore Wind Turbines
Hornsea 3 is being developed with a planned generation capacity of approximately 2.9 GW and will comprise 197 offshore wind turbines. Once operational, the project is expected to generate enough renewable electricity to supply more than 3.3 million UK homes. Its scale makes it one of the major offshore wind developments contributing to the UK's renewable energy capacity.
Offshore Construction Advances Alongside Turbine Preparation
The turbine component deliveries are taking place alongside other offshore construction activities. According to Ørsted's third-quarter 2026 project update, 95 of the 197 turbine foundation positions had been installed, while the second offshore converter station had also been completed. The project had reached approximately 40% overall completion, compared with 30% in the second quarter of 2026.
Grid Connection Infrastructure Takes Shape
Alongside offshore installation, Hornsea 3 is progressing the infrastructure required to deliver electricity to the UK transmission network. Ørsted reported that the first export cable was fully installed, while work on the second export circuit was progressing. The company also confirmed the completion of initial enabling and reinforcement works at the Norwich Main Substation, providing an important step towards establishing the project's grid connection and preparing for future power generation.
Powering Ahead: Don't Miss the United Kingdom's Next Big Energy Play
Every year, billions of euros flow into the United Kingdom's power sector, from offshore wind farms to grid modernization programs across the United Kingdom. But how many of these opportunities pass by unnoticed because the right intelligence wasn't on your desk at the right time?
The Global Project Tracking (GPT) platform by Blackridge Research cuts through the noise, delivering verified, real-time data on power projects across the United Kingdom and beyond, so your team can move first, bid smarter, and build stronger pipelines.
Whether you're an EPC contractor, equipment supplier, investor, or policy stakeholder, having a single source of truth for the region's power project landscape changes how you compete.
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
Ready to see the United Kingdom's power project pipeline in full detail? Book a Free Demo of the Global Project Tracking (GPT) platform by Blackridge Research today.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.