The Ohio Power Siting Board (OPSB) approved the construction of two natural gas-fired electric generation facilities, one in Fairfield County and one in Pickaway County. Each facility will operate "behind-the-meter" to serve the electric load of an adjacent data center and will not be connected to the electric power grid.
Jurisdiction Limited to Generation Facilities
While the OPSB has jurisdiction over the electric generation facility associated with the two sites, the board has no authority over the approval of the data centers themselves. The decisions, announced from Columbus, clear the way for the projects to proceed under a set of conditions adopted by the board in each case.
Fairfield Energy Center
Fairfield Energy Center, LLC, received approval to construct and operate a 1,350 MW generation facility along with a 1,040 MW battery energy storage facility. The project will occupy 122 acres in the Village of Millersport, Walnut Township, in Fairfield County, near the intersection of State Route 37 and State Route 204.
In approving the project, the OPSB adopted an agreement between Fairfield Energy Center and the OPSB staff. Under the agreement, Fairfield Energy Center must adhere to 36 conditions designed to minimize potential impacts during construction and operation of the facility.
Trusted by Leading EPCs & Manufacturers
Find the Latest Data Center Projects in the United States
Gain exclusive access to our industry-leading database of data center opportunities with detailed project timelines and stakeholder information.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
Ashville Energy Center
PowerConneX, Inc. received approval to construct and operate the 800 MW Ashville Energy Center on 110 acres in the Village of Ashville, Pickaway County. The project site is located along State Route 752, east of State Route 23.
For this project, the OPSB adopted and modified an agreement between PowerConneX, the Village of Ashville, and the OPSB staff. The agreement requires PowerConneX to adhere to 41 conditions designed to minimize potential impacts during construction and operation. In addition, PowerConneX must honor the financial commitments it has made to the Ashville community.
Never Miss Another Hyperscale Build in the United States Again
How much pipeline is your team leaving on the table while competitors break ground first? Across the United States, the data center construction boom shows no sign of slowing, and the firms winning contracts are the ones tracking every megawatt from announcement to commissioning.
Blackridge Research built the Global Project Tracking (GPT) platform to give developers, contractors, and suppliers a decisive edge. Instead of relying on scattered news alerts and outdated directories, you get a centralized, continuously updated view of data center projects across the United States, who is building them, where, when, and at what scale.
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
Stop reacting to opportunities after they are gone. Book a Free Demo of the Global Project Tracking (GPT) platform by Blackridge Research today and see every U.S. data center project your business should be chasing.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.