Neoen, France's leading independent renewable energy producer, has commenced construction on three solar farms and one wind farm across the country, adding a combined 101 MW of capacity to its growing portfolio. The announcement, made in Paris on 24 September 2026, brings Neoen's total capacity in France to more than 2.5 GW in operation or under construction.
A Military Base Becomes the Region's Biggest Solar Site
The most prominent of the four projects is the BA 217 Solar Farm, a 41 MWp installation to be built at the Bretigny-sur-Orge military base in Essonne, south of Paris.
Spanning the municipalities of Plessis-Pâté and Bretigny-sur-Orge, the project was originally awarded to Neoen in 2021 through a tender process run by the French Ministry of the Armed Forces under its "Place au Soleil" initiative.
Construction was able to begin only after extensive clearing of unexploded ordnances at the site. Eiffage Energie Systèmes has been appointed to handle both the construction and maintenance of the farm, which is scheduled to begin operating in the first half of 2028. Upon commissioning, BA 217 will be the largest solar farm in the Île-de-France region.
READ NEXT: ESR Acquires Aquila Clean Energy APAC, Adding 1.6 GW Renewables Portfolio Across Asia-Pacific
Two Agrisolar Farms Blend Sheep Farming with Renewable Generation
Two of the four new projects are agrisolar farms, designed to combine agricultural activity with electricity production. The Saint-Just Solar Farm, rated at 30 MWp and located in the Cher department, will include the installation of a new sheep pen to house a flock of 150 sheep.
Construction and subsequent maintenance of the Saint-Just site have been contracted to Sireos. The farm is expected to enter operation in the first half of 2028.
The second agrisolar project, La Ferme des Cros Solar Farm in the Charente department, carries a capacity of 16 MWp. As with the BA 217 project, Eiffage Énergie Systèmes has been appointed to oversee its construction and maintenance. La Ferme des Cros is also scheduled for commissioning in the first half of 2028.
Both agrisolar farms reflect an approach that Neoen says involves close consultation with landowners, farmers, local stakeholders and government authorities to ensure the projects are integrated into their surrounding communities.
Trusted by Leading EPCs & Manufacturers
Find the Latest Renewable Energy Projects in Find the Latest Renewable Energy Projects in France
Gain exclusive access to our industry-leading database of renewable energy opportunities with detailed project timelines and stakeholder information.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
Wind Farm in Haute-Vienne to Power Equivalent of 12,000 Homes
The fourth project, the Moulin à Vent Wind Farm in the Haute-Vienne region, will consist of three wind turbines delivering a total output of 14 MW. The farm is projected to generate approximately 28.5 GWh of electricity annually, equivalent to the annual consumption of around 12,000 people, a figure Neoen describes as more than half the population of the Haut-Limousin en Marche area.
Construction of the Moulin à Vent project has been awarded to a consortium comprising Vestas, Atlas Fondations and Colas. Commissioning is scheduled for late 2027, making it the first of the four projects to become operational. As part of its community engagement for this project, Neoen is supporting a local cultural center in the Haut-Limousin area.
500 MW Launched in France So Far This Year
The four projects form part of a broader acceleration of Neoen's construction activity in France during 2026. Xavier Barbaro, Neoen Group CEO, noted that the French team has launched the construction of over 500 MW of capacity so far this year, which he described as a major contribution toward the company's global annual target of 2 GW of new capacity.
Neoen's total capacity in France now exceeds 2.5 GW in operation or under construction, of which 1.8 GW is owned by the company and 700 MW is managed on behalf of third parties.
The company stated that a further 300 MW is expected to enter construction in France over the next 12 months, pointing to a continuing pipeline of activity beyond the four projects announced this week.
Executive Statements Highlight Scale of French Operations
Christophe Desplats-Redier, CEO of Neoen France, said the latest projects reflect the hard work and commitment of Neoen's French team, calling 2026 an important year for the company in France given the launch of several landmark projects. He also thanked local stakeholders, grid operator Enedis and Neoen's industrial partners.
Barbaro, commenting on the broader significance of the announcements, said the company is proud to be accelerating the transition to a low-carbon, competitive, and reliable energy future in France and globally.
Powering Your Pipeline: Stay Ahead of the France Energy Infrastructure Race
The energy transition across France is accelerating at a pace that leaves little room for guesswork. From offshore wind expansions in the North Sea to grid modernization programs spanning the continent, the volume of power sector activity has never been greater, and neither has the competition for a share of it.
Organizations that rely on fragmented data sources or outdated project intelligence risk missing critical windows for tendering, partnership, and investment. A consolidated, real-time view of the French power landscape is no longer a luxury; it is a fundamental requirement for staying competitive.
The Global Project Tracking (GPT) platform by Blackridge Research brings together comprehensive, continuously updated intelligence across the full lifecycle of power projects throughout France, giving your team the clarity and confidence to act decisively.
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
See how the Global Project Tracking (GPT) platform by Blackridge Research can sharpen your strategy across France's power sector. Book a Free Demo with our team today.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.