The Lithuanian state-controlled Ignitis Group has proposed postponing a 700-megawatt offshore wind farm project in the Baltic Sea worth around USD 3.37 billion, the company said in a statement.
Proposal to Delay While Preserving the Option to Resume
Ignitis Group and its subsidiary Ignitis Renewables will ask the Lithuanian energy and finance ministries to delay the project by adjusting its implementation schedule while preserving the option to resume it when conditions change.
"Lithuania needs to increase its power generation capacity from stable renewable sources, and offshore wind is one of the most stable. However, it is important to choose a path for the further development of the offshore wind farm project that creates the greatest value while best serving the state's interests," Ignitis Group CEO Darius Maikstenas said.
READ NEXT: Ofgem Launches Record $4.69 Billion Tender Round for Hornsea 3 Offshore Transmission Link
Permit and Audit Timetable
A construction permit is expected to be issued in the near future, while a recommendation by the National Audit Office to decide on the project's further implementation must be acted on by the end of the year, according to the company's statement. Ignitis Renewables said it was continuing preparatory work and making the necessary investments to secure a construction permit in 2027.
Key issues to be resolved include aligning the project schedule with the actual duration of offshore wind farm development, linking financial commitments to the start of construction, accelerating procedures for onshore infrastructure, and adapting design and work organisation rules for offshore wind projects.
Trusted by Leading EPCs & Manufacturers
Find the Latest Offshore Wind Farm Projects in Lithuania
Gain exclusive access to our industry-leading database of offshore wind opportunities with detailed project timelines and stakeholder information.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
Three Options on the Table
A cost-benefit analysis prepared by Ignitis Group outlines three options: freezing the project, seeking partners in neighboring countries and European funding, or proceeding with construction while increasing the final electricity tariff for consumers.
Last week, the Seimas Audit Committee decided to ask the government to coordinate the process and instruct the Energy Ministry to lead an assessment of the prospects for the first offshore wind farm project.
It also called on the Finance Ministry to immediately assess whether the letter of shareholder expectations submitted to Ignitis was in line with market conditions, electricity demand forecasts, and return-on-investment requirements.
Political Voices Urging Caution
In late September, Deputy Energy Minister Ignas Junevičius said a commercial offshore wind farm could be built in Lithuania in the future if electrification progressed successfully, domestic industry expanded, or large foreign energy consumers were attracted to the country.
In July, Energy Minister Lukas Savickas said there was no point in pursuing the development of the first offshore wind farm simply for the sake of completing the project. He pledged to make an immediate decision on its future.
Prime Minister Mindaugas Sinkevičius also stressed that Lithuania would not rush to decide how many offshore wind farms it needed and would not seek to implement state projects that were not economically justified.
Also in July, Lithuania's former Energy Minister Žygimantas Vaičiūnas said the offshore wind farm project was currently unfeasible. He said the two offshore wind projects in the Baltic Sea planned by the previous Conservatives-led government had been a mistake.
Audit Found Costs Up, Returns Down
According to the National Audit Office, which audited the project last autumn, market changes since 2023 have increased its cost by 27 percent, while its projected returns have fallen by 40 percent.
The country's energy and finance ministries are expected to make a final decision on the project's future by the end of this year.
Powering Ahead: How Lithuania's Energy Transition Creates Opportunities for Project Intelligence
What does it take to stay ahead in Lithuania's rapidly transforming power sector? With grid modernization programs, offshore wind installations, and hydrogen-ready gas plants reshaping the energy landscape, the difference between winning and watching comes down to one thing: knowing which projects are moving and when.
Every megawatt of capacity added across Lithuania begins as a pipeline entry, a tender, and then a contract award. Teams that track these stages early position themselves to bid smarter, partner better, and plan with confidence. Teams that don't are left reacting to headlines.
This is where the Global Project Tracking (GPT) platform by Blackridge Research becomes indispensable. It consolidates power sector project intelligence across Lithuania into a single, continuously updated source, giving you visibility from early planning all the way through commissioning.
Upcoming Projects
Tender Notices
Contract Awards
Projects Under Construction
Completed Projects
See how leading power sector businesses across Lithuania use the Global Project Tracking (GPT) platform by Blackridge Research to sharpen their strategy and capture new opportunities. Book a free demo today and take the first step toward complete project visibility.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.