GERC Hears Petition on Delays in 36 MW Wind-Solar Hybrid Project Commissioning in Gujarat
The Gujarat Electricity Regulatory Commission (GERC) in Gandhinagar recently heard a petition filed by a company against the Gujarat Energy Transmission Corporation Limited (GETCO) regarding delays in the commissioning of a 36 MW Wind-Solar Hybrid Power Plant. The petitioner is seeking an extension for the Scheduled Date of Commissioning (SCOD), citing unforeseen “Force Majeure” events as the primary reason for the delay.
Infrastructure Sharing Dispute
The dispute centers on the technical requirements for grid connectivity and the implications of sharing transmission infrastructure with another developer. The company had initially planned to set up the hybrid project at GETCO's 66kV Gangiyavadar Substation. According to the petition, the delay was primarily due to GETCO's directive to allow another generator to share the power evacuation infrastructure.
This sharing arrangement increased the total required capacity from 36 MW to 45 MW, combining the petitioner's 36 MW and the other developer's 9 MW. The petitioner highlighted that this increase required a critical change in technical specifications, specifically the Current Transformer (CT) ratio.
Technical Modifications Required
The original ratio was set at 400/1 Amp for 36 MW, but after the other developer's inclusion, it had to be revised to 450/1 Amp to accommodate the combined 45 MW capacity. This change necessitated new approvals and the procurement of additional equipment, resulting in significant delays. The petitioner stated that the project is now nearly complete, with over INR 200 Crores invested, and is only awaiting the final changeover.
40+ reviews
Find the Latest Renewable Energy Projects in India
Gain exclusive access to our industry-leading database of Renewable Energy opportunities with detailed project timelines and stakeholder information.
Collect Your Free Leads Here!
No credit cardUp-to-date coverage
Joined by 750+ industry professionals last month
GETCO's Response
GETCO countered the claims, stating that the petitioner was aware of the possibility of sharing the infrastructure from the beginning. The connectivity approval documents for both phases of the project included provisions for sharing the infrastructure with other developers, ensuring the optimal use of the substation assets. GETCO emphasized that the lead generator was required to update the CT ratio based on the total capacity being shared, and noted that the petitioner itself had requested consideration of the 45 MW capacity for the CT ratio update in prior communications.
They also highlighted that the line for the 30 MW project, which expired in July 2025, was intended to be shared for the additional 6 MW connectivity.
Commission's Direction
The GERC bench acknowledged that any change in granted connectivity would naturally require an update in the CT ratio, which in turn affects transmission structure and design. The Commission noted that arguments from both sides have been completed but directed GETCO to file a reply to the petitioner's amendment application, along with a written submission, within two weeks.
The petitioner was granted a similar two-week period to submit a rejoinder and its own written submission before the Commission issues its final order. This case highlights the complexities associated with grid connectivity and infrastructure sharing for hybrid power projects, particularly when changes in project scope necessitate technical modifications and regulatory approvals, which can impact commissioning timelines and investments.
Also Read: Oyster Renewable Wins INR 1,844 Crore Loan for 342 MW Hybrid Power Project in Madhya Pradesh
Connect with Decision-makers about the Latest Renewable Energy Projects in India for business Opportunities.
Subscribe to our database on Renewable Energy Projects and Tenders in India to get access to reliable and high-quality insights on upcoming, under-construction, and completed Solar Photovoltaic (PV) Projects across the world or in your desired geographical location.
Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.