New details have emerged about Amazon Web Services' planned data center campus in Kozani, Greece, following the publication of an environmental impact assessment.

 

The project is expected to deliver 300 MW of power capacity and 240 MW of IT capacity across four buildings containing 20 data halls, with the potential to scale up to 1 GW in the future.

Site Details and Building Specifications

The campus is being developed in partnership with the Public Power Corporation (PPC) and will be located at the former Agios Dimitrios coal-fired power plant in Kozani, a city in northern Greece in the western part of Macedonia. The Agios Dimitrios Power Station, owned by PPC, was the largest of Greece's power plants but was shut down earlier this year.

The campus itself will occupy around 45 hectares, with the four buildings totaling 77,360 square meters (832,695 square feet). Each building will be identical, reaching 36 meters (118 feet) in height, and will feature aluminum composite panel facades, with landscaping around the perimeter of the site.

 

Reuse of Coal Plant Infrastructure

AWS and PPC intend to make use of some of the infrastructure left behind by the former coal power station. The campus will connect to the existing 400 kV substations at Agios Dimitrios via two new underground cable lines.

 

The development will make use of transmission capacity that was once needed by the 1.55 GW coal plant.

Trusted by Leading EPCs & Manufacturers

Find the Latest Data Center Projects in Greece

Gain exclusive access to our industry-leading database of data center opportunities with detailed project timelines and stakeholder information

Request Free Trial → Learn More →

No credit card Up-to-date coverage

 

Cooling and Water Consumption

According to the environmental impact assessment, between 60 and 90 percent of the cooling load will use water, depending on the ambient climate in the area. The remainder will rely on air cooling.

 

Annual water consumption is estimated at approximately 203,000 cubic meters.

Timeline and Investment

PPC is expected to receive the terms for connecting to the national electricity system soon, and the 300 MW agreement is expected to be finalized by the first quarter of 2027. Following this, equipment will be ordered, and construction is hoped to begin in the summer of 2027, with completion targeted by the end of 2028.

PPC is investing USD 1.1 billion in the project, with AWS expected to contribute a similar amount for the IT infrastructure. AWS holds the option to expand the campus to 1 GW and has exclusivity for this capacity until May 2027.

AWS's Broader Presence in Greece

AWS does not currently operate a cloud region in Greece, but the company launched a Local Zone in Athens in July 2026.

 

The company signed four Power Purchase Agreements in the country in November 2024, covering the 44.4 MW Vermio wind farms; the 35.4 MW Mesokorfi wind farm; and the 29.5 MW Koukouras wind farm.

Stay Ahead of Greece's Data Center Construction Boom

Where will the next hyperscale campus break ground in Greece? With demand for colocation and edge capacity surging across the continent, the answer changes weekly.

 

Whether you are a contractor targeting mechanical and electrical packages, a supplier of cooling and power infrastructure, or an investor tracking market momentum, timing is everything in the Greek data center sector. Deals are won by those who identify opportunities before tender documents hit the public domain.

 

The Global Project Tracking (GPT) platform by Blackridge Research gives you a live view of Greece's data center pipeline, from early-stage planning to hyperscale expansions.

 

  • Upcoming Projects

  • Tender Notices

  • Contract Awards

  • Projects Under Construction

  • Completed Projects

 

Do not let the next major Greek data center opportunity pass you by. Book a Free Demo today and see how the Global Project Tracking (GPT) platform by Blackridge Research keeps you ahead of the competition.

Tags

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile