The data center market in Poland, located in Central and Eastern Europe, is attracting global and regional operators to establish their presence around Warsaw, and the new AI-focused campuses and hyperscale projects are also emerging in cities like Bielsko-Biała, Poznan, and Krakow. The country’s location, energy infrastructure, connectivity, and government support with digitalization measures are bringing investments from international technology companies and colocation providers.
Rising Investments in AI and Hyperscale Infrastructure
Microsoft announced it will invest USD 1.52 billion in AI, cybersecurity, and cloud infrastructure in Poland by 2026. Switch Datacenters is building the WAW1 campus for an IT load of 100 MW, while the DL Invest Group and Boosteroid are collaborating to develop a hyperscale campus in Bielsko-Biała with up to 200 MW capacity. For now, Atman is developing a 43 MW IT power Warsaw-3 (WAW-3) facility consisting of 50,000 servers, and DATA4 is spending USD 697.63 million on the Jawczyce campus expansion for 60 MW of capacity by 2030.
Sustainability and AI Driving New Developments
Many projects are targeting low PUE operations, renewable energy sourcing, liquid and hybrid cooling technologies, and modular infrastructure for AI workloads. The Polish government’s Digitalization Strategy through 2035 includes AI factories in Poznan and Krakow between 2026 and 2027, strengthening the country as a growing European hub for hyperscale cloud, AI computing, edge infrastructure, and next-generation digital services.
In this article we highlight the top 5 upcoming data centers in Poland. The following highlights new and expanding developments as per official company announcements and government sources.
Top 5 Upcoming Data Centers in Poland
The upcoming data centers in Poland listed in the table below are ranked by IT load: Bielsko-Biala Data Center, Switch WAW1 Data Center, Data4 Jawczyce Data Center, Atman Waw-3 Data Center, and Green AI Data Center.
Data Center | Location | Capacity |
Bielsko-Biała Data Center | Bielsko-Biała | 200 MW |
Switch WAW1 Data Center | Mory, Warsaw Region | 100+ MW |
Data4 Jawczyce Data Center | Ozarow Mazowiecki | 60 MW |
Atman WAW-3 Data Center | Duchnice | 43 MW |
Green AI Data Center | Warsaw | 20 MW |
Bielsko-Biała Data Center
DL Invest Group and Boosteroid are collaborating to develop a hyperscale data center platform focused on ultra-low-latency digital services across Europe.
The partnership creates a distributed network of up to 12 data centers across Europe. These facilities support cloud services, GPU-intensive AI workloads, and real-time gaming applications that require low latency.
The companies are developing the first project in Bielsko-Biała, Poland, where they plan to build the region's largest data center campuses. The project highlights Poland’s importance for AI-ready and edge computing infrastructure in Central and Eastern Europe.
The development focuses on a low-latency architecture, where proximity between users and computing infrastructure improves cloud gaming performance and real-time digital experiences.
Key Project Details
Parameter | Details |
Project Name | DL Invest Group and Boosteroid Data Center Campus |
Location | Bielsko-Biała, Poland |
Development Type | Hyperscale AI and cloud gaming data center |
Planned Total Capacity | Up to 200 MW |
Initial Development Phase | 50–82 MW |
Planned Data Center Network | Up to 12 facilities across Europe |
Main Workload Focus | Cloud gaming, AI, HPC, real-time streaming |
Existing Power Infrastructure | Over 80 MW available |
Infrastructure Model | Distributed low-latency edge computing |
The Bielsko-Biała Data Center is planned to reach up to 200 MW of total capacity, with the initial phase to provide between 50 MW and 82 MW. The partners are planning a European network of up to 12 facilities. The campus will support cloud gaming and real-time streaming workloads. The project has access to more than 80 MW of power infrastructure and operates on a distributed, low-latency edge computing model.
Strategic Infrastructure Features
Feature Category | Details |
Primary Use Cases | AI workloads, cloud gaming, HPC |
Compute Architecture | GPU-centric infrastructure |
Cooling Technologies | Advanced cooling systems |
Network Objective | Ultra-low-latency connectivity |
Expansion Capability | Scalable hyperscale expansion |
Location Advantage | Central and Eastern Europe's proximity |
Why the Bielsko-Biała Location Was Selected
The Bielsko-Biała site is an industrial infrastructure with energy availability and logistics connectivity. It is a former manufacturing complex that provides access to more than 80 MW of power infrastructure, allowing faster deployment timeframes and support for GPU-intensive computing workloads.
The location allows cloud gaming services for users across Central and Eastern Europe, reducing latency and improving gameplay responsiveness, a feature important for cloud gaming platforms where transmission delays can negatively affect user experience.
Importance of Low-Latency Infrastructure
Low latency is a key factor in cloud gaming and real-time AI applications. In this environment, remote servers transmit every user action, process it, and return the result to the player with minimal delay. To achieve this goal, companies deploy distributed infrastructure, including edge data centers, closer to user populations.
Key Industry Benefits
Industry Impact | Description |
Cloud Gaming Growth | Improved gameplay responsiveness and user experience |
AI Infrastructure Expansion | Increased GPU processing capacity |
Edge Computing Development | Faster localized data processing |
Digital Infrastructure Growth | Expansion of hyperscale facilities in Europe |
Technology Accessibility | Wider access to high-performance gaming services |
Sustainability and Future Expansion
The hyperscale facilities that support streaming infrastructure and the modular campus allow for the deployment of computing resources. The project aligns with the “neocloud” trend, where next-generation cloud infrastructure combines high-performance computing, localized processing, and low-latency connectivity.
Trusted by Leading EPCs & Manufacturers
Looking for Poland's Data Center Market Insights?
Explore the latest hyperscale, AI-ready, and colocation developments across Poland to identify emerging investment opportunities and digital infrastructure trends.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
Switch WAW1 Mory Data Center
Switch Datacenters is building an AI-ready data center campus, WAW1, in the Mory area near Warsaw, Poland. The project is designed as a power-dense facility. The WAW1 campus's 100+ MW IT load development’s first construction phase will begin in 2026. The initial phase will deliver 60 MW of IT capacity.
Switch Datacenters is integrating renewable energy procurement, energy-efficient infrastructure, low PUE and WUE design targets, and green heat reuse initiatives. The company will secure renewable energy through power purchase agreements (PPAs) to operate the campus entirely on renewable energy.
The facility will feature modular high-density power distribution, and its cooling technologies will include liquid, air, and hybrid configurations.
Key Project Details
Parameter | Details |
Project Name | Switch Datacenters Warsaw 1 (WAW1) |
Location | Mory, Warsaw Region, Poland |
Development Type | Wholesale AI-ready data center campus |
Planned Total IT Load | 100+ MW |
First Phase IT Capacity | 60 MW |
Utility Feeders (First Phase) | 90 MVA |
Total Surface Area | 53,810 sqm |
White Space Area | 18,720 sqm |
Number of Data Halls | 22 |
Construction Start | Expected in 2026 |
Energy Supply Target | 100% Renewable Energy |
Cooling Technologies | Liquid, Air, Hybrid Cooling |
Sustainability Features | Low PUE, low WUE, heat reuse |
Connectivity | Major carrier connectivity available |
Switch Data Centers' Warsaw 1 (WAW1) campus is designed for a planned total IT load exceeding 100 MW. The first phase will deliver 60 MW of IT capacity, supported by 90 MVA utility feeders. The campus area covers 53,810 square meters, with 18,720 square meters of white space and 22 data halls.
Sustainability and Energy Strategy
WAW1 data center is built to support operational efficiency and reduce environmental impact. Switch Data Centers plans to integrate renewable energy sourcing through local energy PPAs and is developing a green heat reuse project to utilize excess heat generated by the facility.
The project’s modular infrastructure enables scaling power and cooling systems to support high-density AI computing workloads. By combining cooling options and renewable energy integration, WAW1 is set to become a major sustainable, hyperscale, AI-focused data center development in Poland.
Infrastructure and Security Features
Feature Category | Details |
Building Structure | Steel frame building with bio-based material choices |
Cooling Design | Hybrid dry and air cooling systems |
Parking | Complimentary on-site parking |
Physical Security | 24/7 on-site security officers |
Access Control | Card readers and biometric readers |
Surveillance | CCTV and motion detection systems |
Entry Security | Man-trap single entry system |
Also Read
Data4 Jawczyce Data Center
Data4 Jawczyce Data Center is located in the municipality of Ozarow Mazowiecki. The Data4 Group has expanded its Polish operations with the inauguration of a second data center facility at the Jawczyce campus near Warsaw.
The company's investment plans in Poland include expanding the first campus building in 2023 to meet demand across Central Europe.
Sustainability-Focused Campus Development
The project emphasizes sustainability and climate resilience, low PUE targets, modular construction methods, and participation in European climate adaptation measures.
Key Project Details
Parameter | Details |
Project Name | Data4 Jawczyce Campus |
Location | Ozarow Mazowiecki near Warsaw, Poland |
New Data Center Capacity | 10 MW |
Total Planned Campus Capacity | Up to 60 MW |
Campus Area | 4 hectares |
Total Built Space | Approx. 50,000 sqm |
Dedicated IT Space | Approx. 15,000 sqm |
Planned Investment by 2030 | Around USD 697.17 million |
Jobs Expected | Approx. 400 direct and indirect jobs |
Current Reported PUE | 1.27 |
Target PUE | Below 1.3 |
Energy Source | 100% low-carbon energy |
Sustainability Certification | BREEAM Excellent |
Planned Capacity and Investment Details
Data4 Jawczyce Data Center will add 10 MW of capacity, bringing the full campus to up to 60 MW. Spread across 4 hectares, the campus will include 50,000 square meters of built space and 15,000 square meters of dedicated IT space. The company's investment in the project will be USD 697.17 million by 2030, creating 400 direct and indirect jobs. The campus operates with a PUE of 1.27 and aims to keep it below 1.3. It plans to run on 100% low-carbon energy, aiming to achieve BREEAM certification. Excellent sustainability certification.
Atman WAW-3 Data Center
Atman WAW-3 data center, located in Duchnice near Warsaw, is the largest colocation investment to date. The facility is designed for clients requiring large-scale colocation infrastructure.
Strategic Location and Connectivity Advantages
The WAW-3 campus is positioned 30 minutes from downtown Warsaw, providing access to scalable power infrastructure and multiple redundant telecommunications links from various carriers. The campus opened its first building with adequate IT power capacity; however, the full campus can accommodate over 50,000 servers.
Atman’s Market Position in Poland
Atman has more than 25 years of experience in data center services and has been a leading colocation and hosting provider in Poland for over a decade.
Key Project Details
Parameter | Details |
Project Name | Atman Data Center Warsaw-3 (WAW-3) |
Location | Duchnice near Warsaw, Poland |
Net Colocation Space | 204,200 sq ft (approx. 19,000 sqm) |
Planned Server Capacity | More than 50,000 servers |
Target IT Power | 43 MW |
Initial Building IT Power | 14.4 MW |
Primary Target Customers | Hyperscalers, AI companies, enterprise clients |
Connectivity | Multiple redundant telecom carrier links |
Capacity and Infrastructure Overview
Atman Data Center Warsaw-3 (WAW-3) will offer approximately 204,200 square feet (approximately 19,000 square meters) of colocation space and support more than 50,000 servers, with an IT power capacity of 43 MW. The initial building phase will deliver 14.4 MW of IT power. The facility will have redundant telecom carrier connections for reliable connectivity.
Trusted by Leading EPCs & Manufacturers
Need Customized Data Center Research or Market Intelligence?
Get detailed reports on hyperscale developments, AI infrastructure trends, renewable energy adoption, and regional data center investments tailored to your business requirements.
Request Free Trial → Learn More →
No credit card Up-to-date coverage
Poland’s Digital Infrastructure and AI Expansion Strategy
Poland’s Ministry of Digital Affairs has outlined AI development plans for 2026–2027 to increase computing capacity, expand data center infrastructure, develop AI factories, and improve cybersecurity frameworks.
The country will establish AI-focused facilities in Poznan and Krakow to support supercomputing, research, enterprise innovation, and the digitalization of public administration.
Key Government Initiatives
Initiative | Details |
AI Factories | Planned in Poznań and Kraków |
Focus Areas | Supercomputing, AI, data centers |
Strategic Timeline | 2026–2027 |
National Strategy | Digitalization Strategy through 2035 |
Main Objectives | AI infrastructure, cybersecurity, digital services |
LIM Data Centers Expansion
The LIM Data Center, located in central Warsaw, has announced new colocation spaces through LIM DC-2 and LIM DC-3 to address market demand for server infrastructure and colocation services.
The facility has over 20 years of operational experience offering telecom-neutral connectivity to more than 100 national and international telecom operators, ISPs, and cloud providers.
The facility’s design provides a wide range of options, from individual rack units to separated colocation segments for enterprise and telecommunications customers.
Key Project Details
Parameter | Details |
Project Name | LIM DC-2 and LIM DC-3 |
Location | Warsaw, Poland |
Service Type | Colocation and server infrastructure |
Telecom Connectivity | Access to 100+ telecom operators |
Experience | Over 20 years |
Infrastructure Features | Redundant power, air conditioning, high availability |
Support Availability | 24/7/365 technical support |
Infrastructure and Service Capabilities
The LIM DC-2 and LIM DC-3 facilities offer connectivity to more than 100 telecom operators, and their infrastructure includes redundant power systems and high-availability features with 24/7/365 technical assistance.
Microsoft Data Center and AI Expansion in Poland
Microsoft announced an investment of USD 0.82 billion to expand its data centers in Poland. The investment will be complete in 2026 to strengthen cybersecurity and computing capabilities.
Growth of Poland’s Cloud Region
The company launched the first cloud computing region in Central and Eastern Europe near Warsaw, Poland, in 2023, consisting of three independent data center complexes. The 2026 investment represents the second phase of Microsoft’s expansion in Poland.
The project will collaborate with the Polish Armed Forces to enhance cybersecurity.
Key Project Details
Parameter | Details |
Company | Microsoft |
Investment Value | Nearly USD 0.82 billion |
Additional Announced Investment | USD 700 million |
Completion Timeline | 2026 |
Existing Cloud Region | Operational since 2023 |
Number of Existing Data Center Complexes | 3 |
Main Focus Areas | AI, cybersecurity, cloud computing |
Location | Mazovia region near Warsaw |
Microsoft has invested USD 0.82 billion and announced an additional investment of USD 700 million, which it will complete by 2026. The company has been operating a cloud region in the Mazovia region near Warsaw since 2023 with three existing data center complexes. At the government level, Poland is also providing support through planned AI factories in Poznan and Kraków. These initiatives focus on supercomputing development under the country’s Digitalization Strategy through 2035, with developments planned for 2026 and 2027.
Also Read
Conclusion
The upcoming data center developments in Poland, with planned projects collectively representing several hundred megawatts of IT capacity, renewable energy integration, and billions of dollars in infrastructure spending, can be considered an important hub in Central and Eastern Europe.
AI, Sustainability, and Hyperscale Growth Driving the Market
With developments such as Atman WAW-3, Data4 Jawczyce, Switch WAW1, and Microsoft’s cloud expansion, while Bielsko-Biała focuses on low-latency AI and cloud gaming infrastructure, the market is becoming attractive to local and international players. Projects focus on renewable energy procurement, cooling systems, and modular designs to support AI and GPU-intensive computing.
Future Outlook for Poland’s Digital Infrastructure
As demand for AI infrastructure, cloud computing, and real-time digital applications continues to rise across Europe, Poland is well-positioned to become an important data center hub. Supported by government digitalization programs and growing investor confidence, the country will play a key role in expanding sustainable data center infrastructure in Europe.
Track Poland’s Data Center Opportunities with Confidence
As Poland accelerates its expansion in hyperscale, AI-ready, and cloud-focused digital infrastructure, staying updated on upcoming data centers in Poland is essential to remain competitive in Central and Eastern Europe’s rapidly evolving digital economy.
Looking for reliable, real-time insights into data center projects across Poland and the European market?
Unlock powerful market intelligence with Blackridge Research’s Global Project Tracking (GPT) Platform, your trusted solution to track data center projects across every stage:
Upcoming Projects
Tender Announcements
Contract Awards
Projects Under Construction
Completed Developments
From hyperscale campuses near Warsaw and AI-ready facilities in Bielsko-Biała to emerging cloud, edge, and carrier-neutral infrastructure developments across Poland, gain early access to verified project intelligence and discover new business opportunities in Europe’s growing digital infrastructure sector.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.