Topaz Solar Farm: One of the Largest Solar PV Projects in the US

project_profile

Topaz Solar Farm: One of the Largest Solar PV Projects in the US

Updated on May 19, 2026, 07:01 PM IST
Written by Ashish Joshi
Edited by Siddhi Jain

 

 

 

 

 

 

 

 

Project at a Glance 

 

 

 

 

 

 

 

 

 

 

Project Name 

 

 

 

Topaz Solar Farm

 

 

 

 

 

 

 

 

 

Project Type

 

 

 

Greenfield 

 

 

 

 

 

 

 

 

 

Sector

 

 

 

Power

 

 

 

 

 

 

 

 

 

Subsector

 

 

 

Solar

 

 

 

 

 

 

 

 

 

Project Value

 

 

 

USD 2.44 billion

 

 

 

 

 

 

 

 

 

Project Status

 

 

 

Completed/ Commissioned

 

 

 

 

 

 

 

 

 

Project Location

 

 

 

San Luis Obispo County, California

 

 

 

 

 

 

 

 

 

Power Generated

 

 

 

550 MW

 

 

 

 

 

 

 

 

 

Project Developer

 

 

 

First Solar

 

 

 

 

 

 

 

 

 

Operated By

 

 

 

First Solar

 

 

 

 

 

 

 

 

 

Owned By

 

 

 

BHE Renewables (Berkshire Hathaway Energy)

 

 

 

 

 

 

 

 

 

Construction Start Date

 

 

 

2011

 

 

 

 

 

 

 

 

 

Project Commissioned Date

 

 

 

2015

 

 

 

 

 

 

 

 

Project Overview

The Topaz solar farm is a 550 MW solar farm in San Luis Obispo County, California. Developed, operated, and maintained by First Solar, this solar farm is one of the biggest solar farms in the US. The project is spread across 9.5 square miles, equivalent to 4,600 football fields, and produces about 550 MWac power sufficient to supply clean energy through electricity to 180,000 homes.

 

topaz solar farm california

Source: nasa.gov

 

The Topaz Solar project includes ground-mounted cadmium telluride-made solar PV modules and an electrical collection system that converts Direct current (DC) power to Alternating current (AC) power. 

 

This power will be delivered to a substation within the project for collection and conversion from 34.5 kV to 230 kV for delivery through the Pacific Gas and Electric switching station. The Pacific Gas and Electric switching station is interconnected to the Morro Bay to Midway 230-kV transmission line. 

 

Project Background

The Department of Energy (DOE) proposed the Topaz Solar Farm to increase the availability of electricity generated from renewable energy projects in the US. This includes the construction of several solar PV facilities and their associated transmission and support facilities. The Topaz Solar Farm generates sufficient electricity power for about 180,000 homes annually. This solar project was built with an estimate of saving about 8,564,790 metric tons of carbon dioxide over its lifetime.

 

Land Analysis

Topaz Solar Farms, Limited Liability Corporation (LLC), the project proponent, purchased about 10,000 acres of Land to develop the facility. About 4,100 acres of the total land acquired has been used for the project development. The entire project was divided into two study areas, Study Area A and Study Area B for a project feasibility study.

 

 

 

 

 

 

 

 

 

 

Project Element

 

 

 

Alternative A

 

 

 

Alternative B

 

 

 

 

 

 

 

 

 

 

 

Study Area (acres)

 

 

 

7,800

 

 

 

6,300

 

 

 

 

 

 

 

 

 

 

 

Estimated Developed Area (acres)

 

 

 

up to 4,100

 

 

 

up to 4,000

 

 

 

 

 

 

 

 

 

 

 

Overhead 34.5-kV Collector Lines (miles)

 

 

 

12

 

 

 

8

 

 

 

 

 

 

 

 

 

 

 

Access Roads (miles)

 

 

 

22

 

 

 

22

 

 

 

 

 

 

 

 

 

 

Both the study areas had similarly sized solar generating equipment, a switching station, a project substation, a monitoring and maintenance facility, a Solar Energy Learning Center, and infrastructure such as roads and fencing. Both proposals were considered but eliminated by the Department of Energy because they did not meet the need and purpose of the project or for other reasons provided in Section 2.1.3 of the Environmental Impact Statement (EIS), such as technical feasibility issues, environmental impacts, and legal and regulatory constraints.  

 

Topaz Solar Farm Location

topaz solar farm location

 

The Topaz Solar Farm is located in eastern San Luis Obispo County, California, approximately six miles northwest of the Carrizo Plain National Monument and one mile north of the community of California Valley.

 

 

Topaz Solar Farm Cost

The Topaz Solar Farm project cost is around USD 2.44 billion. This cost includes the interest amount during the time of construction. It is one of the biggest solar farm in the US was built with a solar capacity of 550 MW.

 

Trusted by Leading Manufacturers & EPCs

Find The Latest Solar Photovoltaic (PV) Projects In The United States

Gain exclusive access to our industry-leading database of Solar Photovoltaic Projects opportunities with detailed project timelines & stakeholder information

Request Free Trial Learn More

No credit card Up-to-date coverage

 

Project Timeline

topaz solar farm timeline

 

In January 2019, Topaz Solar Farm received full contract payment for January 2019 post-petition energy deliveries to PG & E. This is consistent with the terms of the PPA signed by both parties.

 

Project Specifications

 

 

 

 

 

 

 

No of solar photovoltaic modules used

 

 

 

9 million

 

 

 

 

 

 

 

 

 

No of Solar arrays

 

 

 

460 Solar PV Arrays

 

 

 

 

 

 

 

 

 

Solar Panel Tracking Type

 

 

 

Fixed

 

 

 

 

 

 

 

 

 

Solar module Type

 

 

 

Thin-film cadmium telluride 

 

 

 

 

 

 

 

 

 

Solar project type

 

 

 

Ground-mounted solar project

 

 

 

 

 

 

 

 

 

 

Topaz Solar Farm Contractors & Suppliers

 

 

 

 

 

 

 

 

 

Role

 

 

 

Company

 

 

 

Details

 

 

 

 

 

 

 

 

 

 

 

EPC Contractor

 

 

 

First Solar

 

 

 

Turn-key engineering, procurement, and construction contract

 

 

 

 

 

 

 

 

 

 

 

Solar Module Supplier

 

 

 

First Solar

 

 

 

9 million cadmium telluride solar PV modules

 

 

 

 

 

 

 

 

 

 

 

Project Owner

 

 

 

Berkshire Hathaway Energy (Formerly known as MidAmerican Energy Holdings Company)

 

 

 

MidAmerican Energy Holdings Company purchased the ownership in 2011

 

 

 

 

 

 

 

 

 

 

 

Operations & Maintenance (O&M)

 

 

 

First Solar

 

 

 

Operate and maintain the project under a 25-year, fixed-fee operating and maintenance agreement.

 

 

 

 

 

 

 

 

 

 

Investors

The United States (US) Department of Energy (DOE) issued a federal loan guarantee to the Royal Bank of Scotland to provide funding to Topaz Solar Farms, Limited Liability Corporation (LLC). The entire project was built at a cost of USD 2.44 billion. 

 

Trusted by Leading Manufacturers & EPCs

Get a Customized United States (US) Solar Photovoltaic (PV) Market Report

Gain exclusive access to industry trends and market outlook covering major players in the industry.

Request Free Trial Learn More

No credit card Up-to-date coverage

 

Topaz Solar Farm Ownership Changes

First Solar was responsible for Engineering, Procurement, and Construction (EPC), project development, solar module supply, and operation and maintenance. During construction in 2011, First Solar sold the ownership of the 550 MW Topaz project to MidAmerican Renewables, a subsidiary of MidAmerican Energy Holdings Company. 

 

The Ownership transfer to MidAmerican Energy Holdings Company was completed by 31st January 2012 under a 25-year, fixed-fee operating and maintenance agreement with First Solar. 

 

In April 2014, MidAmerican Energy Holdings Company renamed itself as Berkshire Hathaway Energy. Currently, BHE Renewables, a subsidiary of Berkshire Hathaway Energy, owns the Topaz Solar farm, with First Solar as the O&M for 25 years. The electricity produced is being purchased by Pacific Gas and Electric Company (PG&E).

 

Power Purchase Agreement for Topaz Solar Farm (PPA)

A long-term Power Purchase Agreement (PPA) was sold to Pacific Gas and Electric Company (PG&E). Under this 25-year PPA agreement, PG&R will purchase the electricity from the Topaz Solar farm and provide 33% of this electricity to its customers under the mandated Government Executive Order S-21-09. Under this order issued by the California Governor in 2009, about 33% of the electricity sold in California must be generated from renewable energy sources.

 

 

Challenges for the Topaz Solar Farm

In October 2011, the North County Watch and Carrizo Commons filed a lawsuit against the 550 MW Topaz Solar Farm. The lawsuit claimed the project land was home to several protected species, such as San Joaquin kit fox, giant kangaroo rat, and blunt-nosed leopard lizard. 

 

First Solar signed a habitat restoration agreement with North County Watch and Carrizo Commons. Under this agreement, this 550-megawatt plant will have 35 years of operation, after which it will be decommissioned, and the land habitat will be restored. The restoration also includes preservation of approximately 22,000 acres of off-site lands.

 

Conclusion

Topaz Solar Farm is a 550 MW ground-mounted cadmium telluride fixed-tracking solar panels project developed and operated by First Solar. It was initially owned by First Solar but was later acquired by MidAmerican Renewables, a subsidiary of MidAmerican Energy Holdings Company, in 2011, which renamed itself Berkshire Hathaway Energy. The project is now owned by BHE Renewables, a subsidiary of Berkshire Hathaway Energy.

 

The project was built at a project cost of USD 2.44 billion, which was funded by the Royal Bank of Scotland through a federal loan guarantee issued by the Department of Energy. This utility-scale solar project has sufficient power generation capacity to supply power for about 180,000 homes.

 

 Topaz Solar Farm began its commercial operation in 2015 and continues to be one of the largest solar plant in the US.

 

 

Stay Updated on the Latest Solar PV Projects in the United States!

Subscribe to Blackridge’s US Solar Photovoltaic (PV) Projects Database and get access to:

 

  • Reliable and high-quality insights

  • Upcoming, in-progress, and completed construction

  • EPC projects 

  • Essential details on key stakeholder contact information

  • Timely updates
     

Start a free demo to unlock new business opportunities!

Tags

Leave a Comment

We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.

We read every comment and do our best to respond to them all.

Protected by Cloudflare Turnstile