Table of Contents
Khavda Renewable Energy Park Project Details | |
Project Name | Khavda Renewable Energy Park |
Project Type | Greenfield |
Sector | Energy |
Subsector | Solar & Wind |
Project Value | INR 1.5 Lakh crores (USD 18.7 billion) |
Project Status | 2031 MW (operational) |
Project Location | Vighakot village, Kutch district, Gujarat, India |
Power Generated | 30 GW (26 GW solar + 4 GW wind) |
Project Developer | AGEL (Adani Green Energy Limited), Gujarat Industrial Power Company Limited (GIPCL), Gujarat State Electricity Corporation Limited (GSECL), NTPC Renewable Energy Limited, Sarjan Realities Limited (SRL), Solar Energy Corporation of India Limited (SECI). |
Operated By | AGEL (Adani Green Energy Limited) |
Owned By | AGEL (Adani Green Energy Limited) |
Construction Start Date | December 2020 |
Project Commissioned Date | 2030 (expected) |
Special Mention | World’s Largest Renewable Energy Park |
Project Overview
Khavda Renewable Energy Park is a 30 GW solar + wind project that is set to become the world's largest renewable energy park once commissioned. Spanning over 72,400 hectares, this Khavda park is five times the size of Paris. This project will power 16.1 million homes and will avoid 58 million tonnes of CO2 emissions annually. Of the 30 GW capacity, 2 GW has already been operationalized by AGEL (Adani Green Energy Limited).
.webp)
This project includes TOPCon, N-Type bifacial solar modules and aims to generate 81 billion units of clean electricity and create 15,000 employment opportunities, boosting the national economy.
Project Background
The Khavda Renewable Energy Park is an innovative hybrid project combining solar and wind energy. This project is a part of AGEL's ambitious goal of 500 GW of renewable energy capacity by 2030.
The project is planned, constructed, and operated in the resource-rich region of Gujarat. It is located in the Kutch district of Gujarat, an arid, non-cultivable land suitable for renewable energy development. This region receives solar irradiation of 2,060 kWh/m²/year and a wind speed of 8 meters per second, making it optimal for hybrid renewable energy projects.
AGEL entered several partnerships with other companies, such as NTPC Renewable Energy Limited, TotalEnergies, and many more.
The NTPC Renewable Energy Limited, a subsidiary of NTPC, one of India's top renewable energy companies, built a 397.7 MW ground-mounted solar project in Khavda Solar PV Park Block- 4.
The solar trackers for this 397.7 MW project were supplied by NEXTracker. Vikram Solar supplied solar module supply for this project. Sterling and Wilson Renewable Energy, one of the top solar EPC companies in the world, will perform operations and maintenance for the solar PV power project for 3 years.
Vikram Solar, one of India's top solar panel manufacturers, has also supplied solar modules for 1,255 MW for the Khavda Solar Project. These modules are cutting-edge bifacial DCR modules boasting a minimum capacity of 540 Wp, meeting the Approved List of Models and Manufacturers (ALMM) standards.
The Khavda Renewable Energy Park has witnessed some project milestones:
In February 2024, About 551 MW of the project was commissioned.
In March 2024, Khavda Renewable Energy Park achieved an operational capacity of 1000 MW, which includes installing approximately 2.4 million solar modules.
As of 2025, about 2000 MW capacity is operational at the Khavda Renewable Energy Park.
Project Location
The Khavda Renewable Energy Park is identified at Vighakot BSF Post, near the International Border in the Kutch district. The park is planned across 72,400 hectares of land allocated under the Government Waste Land Policy.
An approach road of 16.26 km was constructed, along with the widening and strengthening of the existing 40.83 km road, completed by 31st December 2021. The land was issued by the Government of Gujarat with the condition that developers have to develop 50% of capacity in 3 years and 100% capacity in 5 years from the time of commission of the approach road (31st December 2021).
Its location connects the park to India's central grid through a 765 kV transmission line for effective power distribution to over 16.1 million homes.
Project Cost
The Khavda Renewable Energy Park is being built with a project cost of INR 1.5 Lakh crores (USD 18.7 billion). On 3rd September 2024, TotalEnergies announced its joint venture with AGEL for the Khavda project in Gujarat. Under this agreement, Total Energies is investing an equity investment of USD 444 million for this project.
Project Timeline

2024: In July, a 250 MW wind turbine became operational
2024: In September, TotalEnergies entered into a joint venture with AGEL.
Technical Specifications
Solar | |
|---|---|
Parameter | Details |
Total Solar Capacity | 26 GW |
Solar Modules Installed (as of March 2024) | 2.4 million |
Module Technology | TOPCon, N-type, Bifacial |
Tracking System | Horizontal, Single-axis Tracking |
Solar CUF (Capacity Utilization Factor) | 33% |
.webp)
Wind | |
|---|---|
Parameter | Details |
Total Wind Capacity | 4 GW |
Wind Turbine Rotor Diameter | 160 meters |
Wind Turbine Tip Height | 200 meters |
Wind CUF (Capacity Utilization Factor) | 38% |
Total Project Capacity: 30 GW
Contractors
Park Developers | Solar-Wind Hybrid capacity (MW) | Allocated Land in (Ha.) |
Adani Green Energy Limited (AGEL) | 9500 | 19000 |
National Thermal Power Corporation Limited (NTPC) | 4750 | 9500 |
Sarjan Realities Limited (SRL) | 4750 | 9500 |
Gujarat State Electricity Corporation Limited (GSECL) | 3325 | 6650 |
Solar Energy Corporation of India Limited (SECI) | 3000 (only wind) | 23000 |
Gujarat Industrial Power Company Limited (GIPCL) | 2375 | 4750 |
Total | 27,700 MW | 72,400 Ha |
*The remaining 2,300 MW allocation is yet to be confirmed.
In December 2024, NTPC REL (Renewable Energy Limited) welcomed bids for a 1200 MW solar project at the Khavda renewable energy park. The bid is conducted for the Balance of System (BOS) package to develop a 1,200 MW (Interstate Transmission System) ISTS-connected solar PV project at Khavda Park-South Block in the Rann of Kutch, Gujarat. The project comprises four 300 MW blocks.
The selected bidder will be awarded the scope for design, engineering, manufacturing, supply, transportation, installation, testing, and commissioning of the solar photovoltaic plant, excluding the supply of solar PV modules, which will be provided by NTPC REL.
Study/Assessment | Consultant |
|---|---|
Environment & Social Impact Assessment (ESIA) | Arcadis |
Critical Habitat Assessment (CHA) | |
Climate Change Risk Assessment (CCRA) | |
Human Rights Risk Assessment (HRRA) | |
Environment & Social Due Diligence (ESDD) | AECOM |
E&S Action Plan (ESAP) Monitoring | |
Monitoring of Bird and Bat populations |
Suppliers
Supplier | Supplied | Capacity |
|---|---|---|
NEXTracker | Solar Tracking System | 397.7 MW |
Vikram Solar | Solar Modules | 1,255 MW |
Investors
Adani Green Energy Limited is a major Khavda Renewable Energy Green Park investor. It has invested about INR 1.5 Lakh crores in this project. In 2024, Total Energies recently announced a joint venture with AGEL under this agreement. Total Energies is investing USD 444 million for the 1,150 MWac (1,575 MWp) solar portfolio in Khavda in Gujarat.
Khavda Renewable Energy Park Completion Date
The Khavda Renewable Energy Park is expected to be completed by 2030, with a total installed capacity of 30 GW. Once fully commissioned, it will become the world’s largest renewable energy project.
Benefits
Waterless Robotic Cleaning: An innovative solution to clean the dust accumulation on solar panels, contributing to the United Nations Sustainable Development Group (UNSDG) 6 - Providing Clean Water and Sanitation) by conserving water in the arid Kutch region and maximizing electricity generation.
Developing Indigenous Resilient Supply Chain: Promoting localized procurement of WTGs (Wind Turbine Generating System) and solar trackers.
Reduction in Pollution: This project avoids about 58 million tons of carbon dioxide annually, promoting clean electricity free from fossil fuels.
Avoiding Fossil Fuel Dependence: Promoting green electricity, this project ensures that about 60,300 tons of coal are avoided annually.
Expanding Employment Opportunities: This project promises about 15,200+ direct jobs during construction and post-completion.
Conclusion
The Khavda Renewable Electricity Project is a 30 GW project planned, built, and operated by Adani Green Energy Limited (AGEL), a subsidiary of the Adani Group. As of March 2025, about 2 GW of the total capacity is operational. It is spread across 72,400 hectares of land allocated under the Government Waste Land Policy by the Gujarat government.
The INR 1.5 lakh crore project, funded by Adani Green Energy Limited, is a hybrid project that features solar and wind energy, and it will produce about 81 billion units of renewable energy electricity generation sufficient to power about 16.1 million households. The Adani Group targets this project completion by 2030. This project is a part of AGEL's ambitious goals of 500 GW of renewable energy capacity by 2030 and is set to become the world's largest renewable energy project once fully commissioned.
FAQ'S
Is Khavda the world's largest renewable energy park?
Yes, Khavda is set to become the world's largest renewable energy park with a capacity of 30 GW ( 26 GW solar + 4 GW wind). Currently, it operates a 2 GW capacity, which is expected to be fully commissioned by 2030.
Who is the owner of Khavda Renewable Energy Park?
Adani Green Energy Limited (AGEL), a subsidiary of the Adani Group, owns the 30 GW Khavda renewable energy park.
What is the new project in Kutch Adani?
Khavda Renewable Energy Park, the world's largest renewable energy park with a 30 GW capacity, is built by Adani Green Energy Limited (AGEL), a subsidiary of the Adani Group.
What is the cost of the Khavda power plant?
INR 1.5 lakh crores is the cost of the Khavda power plant, funded by Adani Green Energy Limited (AGEL).
How big is the Khavda Renewable Energy Park?
The Khavda renewable energy park is planned and constructed across 72,400 hectares of land allocated under the Government Waste Land Policy by the Gujarat government.
Stay Updated on the Latest Renewable Energy Projects in India!
Subscribe to Blackridge’s Renewable Power Projects in India database to get access to reliable and high-quality insights on upcoming, in-progress, and completed renewable power projects across the world or in your desired geographical location.
Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.
Start a free demo to take your business to the next level!
Why Blackridge’s Global Projects Tracker?
Blackridge’s Global Projects Tracker covers projects from 150 countries and is updated with real-time, accurate, and authentic project developments. By subscribing to our Renewable Energy Projects in India database, you can get access to key contact details of ongoing and upcoming projects, project timelines and overviews, and regular alerts on project developments, all served to you through an easy-to-use interface.
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.