Table of Contents
| Project at a Glance | |
| Project Name | Scroby Sands Offshore Wind Farm |
| Project Type | Greenfield |
| Capacity | 60 MW |
| Project Location | Offshore Great Yarmouth, UK (North Sea) |
| Sector | Energy |
| Subsector | Wind Energy |
| Project Value | GBP 77 Million |
| Project Status | Operational |
| Project Developer | E.ON UK |
| Operating Company | RWE Renewables |
| Turbine Model | Vestas V80 |
| First Power Generation | 2004 |
Overview
The Scroby Sands Offshore Wind Farm is 2.5 km offshore of Great Yarmouth, Norfolk coast in the North Sea. It is one of the first offshore wind farm projects in the UK. Developed by E.ON UK and operational since 2004, it features 30 Vestas V80 turbines with a combined capacity of 60 megawatts.

This greenfield project provides electricity equivalent to the needs of 41,000 British homes. Currently Owned and managed by RWE Renewables, Scroby Sands continues to contribute to the region's energy security and environmental sustainability efforts, showcasing the viability of offshore wind farms in meeting substantial electricity demands.
Project Background
Scroby Sands wind farm is one of 18 projects with innovative designs proposed under the Crown Estates Round 1 licensing awards. The offshore wind project faced challenges due to its unique location on a sandbank (sea bed) highly affected by coastal erosion. Procurement began in 2003 despite the challenges, with construction commencing in November of the same year. The project involved nearly 200 people in installing the foundations and about 60 individuals dedicated to the erection and commissioning of the turbines. By late 2004, the wind farm was commissioned and handed over to E.ON UK. The site generates electricity for the EDF network via a 33kV connection, highlighting its importance in the region's renewable energy landscape.
The wind farm comprises 30 wind turbine generators supplied by Vestas Celtic Wind Technology, which also provides the foundations and offshore cabling. EDF, the local District Network Operator, established the grid connection through a new 33kV substation, which houses the wind farm's control system. Offshore engineering design company Ode supervised the construction and currently manages the site. Onshore cabling was handled by Pirelli Cables from Wrexham, with NACAP UK Ltd. installing the cables. Vestas continues to maintain the offshore wind turbines.
Project Location Map

Scroby offshore wind farm is located on the shallow water of Scroby Sands sandbank in the North Sea, 2.5 kilometers off Great Yarmouth, Norfolk coast.
Technical Specifications
| Technical data | Value |
| Total installed capacity | 60 MW |
| Energy generation per year | 171 GWh |
| Number of turbines | 30 |
| Name of turbine manufacturer and rating | Vestas V80 2 MW |
| Hub height | 68 m above sea level |
| Rotor diameter | 80 m |
| Piles | Diameter: 4.2 m Length: 40 to 50 m Weight: up to 200 tonnes |
| Tower | Diameter: 30 m Length: 4.2 m Weight: 60 tonnes |
| Turbine | Nacelle weight: 110 tonnes Blade weight: 65 tonnes |
The Scroby Sands Offshore Wind Farm, developed by E.ON UK (formerly PowerGen Renewables Offshore), consists of 30 wind turbines, each 4.2 meters in diameter and driven up to 30 meters into the seabed. The nearest monopile, supporting a 2 MW Vestas V80 turbine with an 80-meter rotor diameter, is only 2.3 kilometers from the shore. Each foundation is a 200-ton cylindrical steel tube, up to 50 meters long, manufactured in Scotland by Cambrian Engineering and Isleburn Mackay Macleod and installed by Mammoet Van Oord using a 'Jumping Jack' installation vessel.
This vessel hammered the piles into the seabed with a hydraulic ram. The turbines, delivered in five parts, include two 30-meter tower sections, three 40-meter blades, and a nacelle containing the gearbox, generator, and transformer. Installation, carried out by A2SEA and Seacore, took about eight weeks.
Find Offshore Wind Project And Tender Leads Around the World Claim Your Free Leads Now!
The wind farm’s electrical system features three 33kV circuits connecting the turbines to the local distribution network at the Admiralty Road substation in Great Yarmouth. These circuits can be reconfigured offshore to facilitate maintenance and minimize the impact of a failure. The offshore armored cables, laid by CNS Ltd., have three power cores and a fiber optic control core and are buried up to 3 meters deep using a cable plow. Concrete mattresses provide additional protection where burial depth is less than 3 meters.
Selected turbines are equipped with navigation lights, radar reflectors, foghorns, and aircraft warning lights to ensure safety. The total nominal power capacity of the wind farm is 60,000 kW, and its installation base and operations and maintenance are located in Great Yarmouth, UK.
Project Timeline

Contractors Involved
| Company | Role |
| E ON ROWL Ltd | Developer |
| ODE | Management |
| Vestas | Offshore EPIC Contractor (Engineering, Procurement, Installation, Commissioning) |
| Pirelli Cables Ltd | Onshore Cable Supply |
| NACAP Infrastructure Ltd | Onshore Cable Installation |
| EDF Energy | Onshore Cable Connection |
| Halliburton KBR | Project Management |
| AEI Cables | Offshore Cable Supply |
| LICengineering A/S | Design of Monopile Foundation & Scour Protection |
| Cambrian Engineering | Supply of Steel Piles |
| Isleburn Mackayard, Macleod | Supply of 15 Piles |
| Mammoet Van Oord | Installation of Foundation & Scour Protection |
| crus Subsea Ud | Installation of Infield & Export Cables |
| Oceanteam; Stemat Marine Service | Barge, Tug, & Multipurpose Support Vessel |
| A2Sea | Installation of 24 Turbines |
| Seacore Ltd | Installation of 6 Turbines |
Project Benefits
The Scroby Sands Offshore Wind Farm offers environmental, economic, and social benefits. By preventing the release of 75,000 tonnes of harmful greenhouse gasses annually, the wind farm contributes to CO2 reduction, mitigating climate change and promoting a healthier atmosphere. In terms of energy supply, the wind farm generates enough green electricity to power 41,000 homes, providing clean energy solutions.
Economically, the wind farm boosts the local economy, particularly during its construction phase, by creating employment opportunities for the local workforce. The wind turbine foundations act as artificial reefs, enhancing marine biodiversity by supporting marine life. The local environment, community, and wildlife thus benefit from the wind farm's presence. From a social perspective, the wind farm adds an intriguing feature to the Norfolk coastline, attracting tourists and benefiting the local tourism industry.
Project Cost
The total cost of the Scroby Sands project, including five years of operations and maintenance (O&M), amounted to GBP 80 million. This expenditure was supported by a GBP 10 million government grant awarded to E.ON UK. The project costs were divided across different phases: development, construction, and operations. The development phase accounted for GBP 1.737 million, or 2.2% of the total budget. The construction phase, the most significant expenditure, consumed GBP 71.511 million, representing 89.3% of the total costs. The operations phase accounted for GBP 6.825 million, or 8.5% of the overall budget.
Current and Future Outlook
As the Scroby Sands Offshore Wind Farm celebrated its 20th anniversary on May 24, 2024, it faced a significant challenge when a turbine caught fire on August 15, 2023. The incident, which produced thick plumes of black smoke, has raised concerns about the safety and integrity of aging wind farm infrastructure. Moving forward, the focus will be on investigating the causes of the fire, implementing safety measures, and ensuring the continued reliability and efficiency of the wind farm as it ages.
Conclusion
The Scroby Sands Offshore Wind Farm, a pilot project in the UK's renewable energy sector, has been operational since 2004. Wind farms provide substantial environmental and economic benefits. Despite facing challenges such as the recent turbine fire, the wind farm continues to play a critical role in the region's energy supply and environmental sustainability. As it moves forward, ongoing efforts to address safety concerns and maintain infrastructure integrity will ensure its continued success and contribution to green energy.
Connect with decision-makers of offshore wind projects around the globe for business opportunities.
Subscribe to our Global Offshore Wind Farm Project and Tender Database to access reliable and high-quality insights on upcoming, in-progress, and completed offshore plant projects worldwide or in your desired location.
Our user-friendly platform provides essential details, timely updates, key stakeholder contact information, and business opportunities tailored for engineering companies, industry professionals, investors, and government agencies.
Start a free demo to take your business to the next level!
Leave a Comment
We love hearing from our readers and value your feedback. If you have any questions or comments about our content, feel free to leave a comment below.
We read every comment and do our best to respond to them all.